Rieger v. Schulte & Eicher

151 S.W. 395, 151 Ky. 129, 1912 Ky. LEXIS 778
CourtCourt of Appeals of Kentucky
DecidedDecember 10, 1912
StatusPublished
Cited by11 cases

This text of 151 S.W. 395 (Rieger v. Schulte & Eicher) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rieger v. Schulte & Eicher, 151 S.W. 395, 151 Ky. 129, 1912 Ky. LEXIS 778 (Ky. Ct. App. 1912).

Opinion

Opinion of the Court bt

Judge Lassing

Affirming.

[130]*130Elizabeth and Amelia Rieger entered into a contract with Adam Lahner, by which he undertook to erect a building for them, in Latonia, Ky., according to certain plans and specifications, for $4,730. He sublet a large part of the work, and bought the material, used in the building, from various firms and individuals. Lyman Walker, an architect, prepared the plans and specifications and superintended the building. The owners advanced to the contractor money from time to time, as the work progressed until the building was completed, at which time they had paid to him $3,031.38. It appears that certain of the subcontractors and material-men were not paid. They filed mechanics’ and materialmen’s liens against the property, and later instituted suits, in which they sought to have the property sold and the proceeds applied to the discharge of the debts due them. Shortly thereafter, while these suits were pending, the Rieger sisters filed suit against the contractor, in which they sought to recover damages alleged to have been sustained by them by reason of his failure to erect the building according to the plans and specifications under which he contracted to do the work. They set up the particulars in which the building failed to conform to the requirements of the plans and specifications, and sought to set oft this claim of unliquidated damages for $1,643.50 against the liens which the subcontractors and materialmen were asserting against their property, and asked that the suit filed by them be consolidated with those filed by the subcontractors and materialmen, and the issues of fact be transferred to the common law docket for trial by a jury. These motions were overruled. The answer of appellants to the claims asserted by the subcontractors and materialmen was, in all material respects, the same as the claim set up in their petition for damages against the contractor. Proof of claims was heard before the master, and, in due time, he reported his findings. In this report he sustained the claim of each of the subcontractors and materialmen. On exceptions to this report, the Rieger sisters again asked that the question of fact raised in the pleadings be submitted to a jury for its determination. This motion was overruled. Upon consideration of the case, on exceptions to the master’s report, the court, with some slight changes, found that the report was correct, and subject to these minor errors, which were eliminated, the report was [131]*131confirmed, and judgment entered, giving to each of the' claimants a lien upon the property for the amounts so adjudged to him and directed it sold in satisfaction thereof. The owners appeal, and seek a reversal upon two grounds. It is insisted for them,- first, that they were entitled to a trial by jury of the issue made between them and the subcontractors and materialmen, and that the failure of the court to grant them a jury trial was a violation of that right guaranteed to them by section 7 of the Constitution and expressly authorized by section 12 of the Code of Practice; and second, that the finding of the chancellor on the disputed question of fact is not supported by the evidence, and his judgment should be reversed for this reason.

The record shows that there were nine subcontractors and materialmen who asserted claims for liens, amounting in the aggregate to about $2,070. The owners claim that the contract price of $4,730 should be abated by the sum of $1,643. This amount was based upon the following items:

Damage suffered because the foundation was built some 12 to 16 inches higher than it should have been ...................... $1,000.00

Cost of four additional steps, necessitated by the higher foundation ............... 10.00

Two copings or gratings left out .......... 20.00

Extra dirt left out ....................... 14.70

Cementing cellar, erroneously left out of contract .............................. 98.30

Defective mill work, stair work, flooring, glass, plumbing, roofing and electric work dapaaged ............................. 500.00

It will thus be seen that, if appellants’ contention be sustained in toto, the contractor, if he has been paid nothing, would be entitled to a lien upon the building for $3,087, this being the contract price less the amount which appellants claim is due them because of the damage in the construction of the building. The subcontractors and materialmen have a lien upon the building to the extent of the amount for which the contractor was entitled to a lien. Counsel for appellants seems to recognize this principle as correct, but insists that, inasmuch as the contractor was, during the progress of the work, paid something more than $3,000, his lien or [132]*132right to a lien has been canceled; and hence, the subcontractors and materialmen are not entitled to liens, although they had not been paid. This is not the law. The subcontractors and materialmen are entitled to a lien for the work done and material furnished in the erection of a building, although the owner thereof has been paid the full contract price. The only limitation upon the right of the subcontractor and materialman is that the sum total of their claims may not exceed the contract price. If the owner settles with the contractor, and leaves the claim of the subcontractor or material-man unsatisfied, under the plain provision of the statute, he is bound to pay them although the effect of this may be to require him to pay twice for the building. It is no defense to the claim of the subcontractor or materialman, who has complied with the íequirements of the statutes and whose work and material are of the standard as to quality and kind called for in the contract, that the owner had paid the contractor. Hence, there are really but two questions raised by the pleadings in. this case. First, were the defects in the building, set up and relied upon by appellants, such as were properly chargeable to any of the subcontractors and materialmen who were asserting these liens; and second, if so, to what extent should their liens be abated? These are the questions which counsel for appellants insists should have been submitted to the jury.

The lien of a subcontractor or a materialman is a creature of the statute. In the absence of a statute, they have no lien, unless there existed some contractual relation between them and the owner of the building. An examination of the statute creating the lien discloses the fact that provision is made, not only for establishing and perfecting the lien, but also for the method to be pursued in enforcing it. It is an equitable proceeding, and it is apparent that the Legislature did not intend that the method of procedure, in cases arising under this act, should be the same as those prevailing in ordinary equitable actions. If so, there was no necessity for providing, in detail in the act, for the preparation of the case for trial; but it would have been sufficient to say, after providing for the creation of the lien, that, in the enforcement thereof, the procedure should be the same as in other equitable actions. The very fact that the Legislature provided for a different course is the best evidence that it was not contemplated [133]*133that the mode of procedure governing ordinary equitable actions should control.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Woodson Bend, Inc. v. Masters' Supply, Inc.
571 S.W.2d 95 (Court of Appeals of Kentucky, 1978)
Ohio Oil Co. v. Smith-Haggard Lumber Co.
156 S.W.2d 111 (Court of Appeals of Kentucky (pre-1976), 1941)
Commercial Union Assurance Co. v. Howard
76 S.W.2d 246 (Court of Appeals of Kentucky (pre-1976), 1934)
Tracy v. C. M. McClung Company
285 S.W. 956 (Court of Appeals of Kentucky (pre-1976), 1926)
McClain and Canaday v. Coleman
270 S.W. 736 (Court of Appeals of Kentucky (pre-1976), 1925)
Miller v. Thompson
229 P. 696 (Arizona Supreme Court, 1924)
Keith v. Commonwealth
243 S.W. 293 (Court of Appeals of Kentucky, 1922)
Carter v. Flegle
232 S.W. 621 (Court of Appeals of Kentucky, 1921)
Phillips v. Stone
208 Ill. App. 478 (Appellate Court of Illinois, 1917)
Monyahan v. City of Lancaster
182 S.W. 862 (Court of Appeals of Kentucky, 1916)
Scott v. Kirtley
179 S.W. 825 (Court of Appeals of Kentucky, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
151 S.W. 395, 151 Ky. 129, 1912 Ky. LEXIS 778, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rieger-v-schulte-eicher-kyctapp-1912.