Town Pump, Inc. v. Petroleum Tank Release Compensation Board

2008 MT 15, 176 P.3d 1017, 341 Mont. 139, 2008 Mont. LEXIS 15
CourtMontana Supreme Court
DecidedJanuary 22, 2008
DocketDA 07-0078
StatusPublished
Cited by1 cases

This text of 2008 MT 15 (Town Pump, Inc. v. Petroleum Tank Release Compensation Board) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town Pump, Inc. v. Petroleum Tank Release Compensation Board, 2008 MT 15, 176 P.3d 1017, 341 Mont. 139, 2008 Mont. LEXIS 15 (Mo. 2008).

Opinion

JUSTICE COTTER

delivered the Opinion of the Court.

¶1 Town Pump’s Dillon, Montana, service station location experienced a release from its petroleum underground storage tanks in December 2002. In December 2003 Town Pump applied to the Petroleum Tank Release Compensation Board (Board) for a determination of eligibility for reimbursement for its costs in conducting the cleanup of the diesel fuel at the spill site. Relying on the statutes and regulations in effect at the time of the release, the Board determined that Town Pump was not eligible for reimbursement. Town Pump proceeded to a contested case proceeding. An administrative hearings examiner affirmed the Board’s determination and granted summary judgment for the Board. Town Pump filed an action in the First Judicial District Court challenging the administrative ruling. The District Court affirmed the Board. Town Pump appeals. We affirm.

ISSUE

¶2 A restatement of the issue on appeal is:

¶3 Did the District Court err when it affirmed the Board’s application of the version of the release reimbursement statute in effect at the time the release occurred, rather than the version of the statute in effect at the time reimbursement was sought?

FACTUAL AND PROCEDURAL BACKGROUND

¶4 In July 2002 Town Pump applied to the Montana Department of Environmental Quality (DEQ) for a permit to replace the underground piping for its petroleum tanks at its service station in Dillon, Montana. The DEQ issued the requested permit and in November 2002 Town Pump Dillon was re-opened with new piping and release detection. During the five day period from December 8-12,2002, several sensors and alarms associated with the underground storage tank (UST) leak detection system for Town Pump Dillon were repeatedly triggered. Believing that the alarms were not indicative of an actual release of petroleum product from the tanks but rather were simply “bugs” that needed to be worked out of the new system, Town Pump did not immediately notify DEQ of any problems.

¶5 On December 10, a technician with the company that had installed the containment and alarm system at Town Pump Dillon *141 stopped by just to check on the new system. The manager told him some of the alarms had been triggered. The technician investigated, bailed a small amount of fuel from one of the sumps and tightened a fitting. The record is not clear whether he returned to the store on December 11, but he did return on December 12 after the supervisor of Town Pump’s Technical Assistance Group (TAG) 1 called and notified him that the sensors indicated a loss of approximately 1,000 gallons of fuel. The technician pumped several hundred gallons of fuel from the sumps during which time he detected and repaired a blown gasket that was causing the fuel leak. Town Pump TAG supervisor called DEQ at approximately 2 p.m. on December 12, reported the unusual operating condition including the alarms and sensors, and notified DEQ that Town Pump was in a potential release situation. On December 13, it was confirmed that Town Pump Dillon had experienced a release as that term is defined in § 75-11-302(24), MCA (2001). The company subsequently undertook and completed a cleanup to the satisfaction of the relevant agencies.

¶6 In December 2003 Town Pump filed an application for reimbursement from the Petroleum Tank Release Fund (the Fund) as authorized by § 75-11-301-321, MCA. In January 2005 the Board denied Town Pump’s application for eligibility for reimbursement on the ground that Town Pump had failed to notify DEQ within 24 hours of the release as required by the laws in effect at that time, i.e., § 75-11-308, MCA (2001) and Admin. R. M. 17.56.502 (1995). Town Pump appealed this initial Board ruling. In December 2005 the administrative hearing examiner issued its proposed order granting the Board’s motion for summary judgment and finding Town Pump ineligible for reimbursement. In March 2006 the Board adopted the hearing examiner’s proposed order and issued its final decision finding Town Pump ineligible for reimbursement from the Fund. In April 2006 Town Pump filed a Petition for Review of Order of the Petroleum Tank Release Compensation Board in the First Judicial District Court. In December 2006 the District Court issued its Decision and Order affirming the Board’s ruling. Town Pump filed a timely appeal.

STANDARD OF REVIEW

¶7 This case involves a legal conclusion only. The district court reviews the administrative agency’s legal conclusion for correctness *142 and we apply the same standard of review to the district court’s determination. Solid Waste Cont. v. Dep. of Pub. Ser. Reg., 2007 MT 154, ¶ 16, 338 Mont. 1, ¶ 16, 161 P.3d 837, ¶ 16.

DISCUSSION

¶8 Issue: Did the District Court err when it affirmed the Board’s application of the version of the release reimbursement statute in effect at the time the release occurred, rather than the version of the statute in effect at the time reimbursement was sought?

¶9 This case arose out of disagreement over which of the following statutes applies to Town Pump’s request for reimbursement of cleanup costs. Town Pump maintains that the eligibility statute in effect at the time it filed its application for eligibility applies, while the Board determined that it was the statute in effect at the time Town Pump Dillon experienced its release which applies here.

¶10 The statute in effect at the time of the release, § 75-11-308, MCA (2001), provided, in relevant part:

(1) An owner or operator is eligible for reimbursement for the applicable percentage as provided in 75-ll-307(4)(a) and (4)(b) of eligible costs caused by a release from a petroleum storage tank only if:
(a) the release was discovered on or after April 13, 1989;
(b) the department is notified of the release in the manner and within the time provided by law or rule;
(e) with the exception of the release, the operation and management of the tank complied with applicable state and federal laws and rules that the board determines pertain to prevention and mitigation of petroleum releases when the release was discovered and remained in compliance following discovery of the release ....

The notification rule referred to in § 75-ll-308(l)(b), MCA (2001), above, required notice to DEQ within 24 hours of the occurrence of “[u]nusual operating conditions,” regulatory examples of which included “erratic behavior of product dispensing equipment” or “the sudden loss of product from the tank system.” Admin. R. M. 17.56.502(2) (1995). The regulations also required an owner/operator to notify DEQ within 24 hours of “[m]onitoring results from a release detection method required under [the regulations] that indicate a release may have occurred unless: [t]he monitoring device is found to be defective, and is immediately repaired, recalibrated or replaced, and *143 additional monitoring does not confirm the initial result....” Admin. R. M. 17.56.502(3)(a) (1995).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

K & R Partnership v. City of Whitefish
2008 MT 228 (Montana Supreme Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
2008 MT 15, 176 P.3d 1017, 341 Mont. 139, 2008 Mont. LEXIS 15, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-pump-inc-v-petroleum-tank-release-compensation-board-mont-2008.