Town of Sturbridge v. Mobil Corp.

195 F. Supp. 2d 330, 2002 U.S. Dist. LEXIS 6912, 2002 WL 602733
CourtDistrict Court, D. Massachusetts
DecidedMarch 29, 2002
DocketCIV.A. 01-40019-NMG
StatusPublished
Cited by2 cases

This text of 195 F. Supp. 2d 330 (Town of Sturbridge v. Mobil Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Sturbridge v. Mobil Corp., 195 F. Supp. 2d 330, 2002 U.S. Dist. LEXIS 6912, 2002 WL 602733 (D. Mass. 2002).

Opinion

MEMORANDUM AND ORDER

GORTON, District Judge.

This case arises from the contamination of the water of Well No. 1 (“the Well”) in the Town of Sturbridge, Massachusetts (“the Town”), by the contaminant, Methyl Tertiary Butyl Ether (“MTBE”). It has been determined that the contaminant leaked into the soil from two nearby gasoline filling stations.

One of the stations is located at 365 Main Street in Sturbridge (“the Mobil site”) and is owned and operated by Defendant Mobil Corporation (“Mobil”). The other station is located at 400 Main Street in Sturbridge (“the ARCO/Shell site”). Defendant Atlantic Richfield Company (“ARCO”) held a leasehold interest on the property at 400 Main Street from the early 1970’s until 1985 and subleased the property to a number of tenants who, one after the other, operated the gasoline station. In 1985, ARCO conveyed its leasehold interest to Defendant Shell Oil Products Company (“Shell”).

Defendant Shell reported that, in November, 1984, three underground storage tanks at the ARCO/Shell site failed tightness tests and were leaking contaminants. ARCO began response actions to curtail the threat of release of hazardous materials into the environment. In 1989, Shell assumed responsibility for those response actions. The ARCO/Shell site is “upgra-dient of’ (drains toward) and within 700 feet of the Well.

Defendant Mobil reported that, prior to July, 1990, oil and hazardous materials were found in the groundwater and soil at the Mobil site. In January, 1991, the Mobil site was designated as a “priority disposal site” by the Massachusetts Department of Environmental Protection (“DEP”). The Mobil Site is upgradient of and within 1,100 feet of the Well.

In 1985, the DEP assigned the Well an “emergency status” requiring Sturbridge to cease using the Well because of the release and threat of release of oil and hazardous materials from the underground storage tanks at the Mobil and ARCO/ Shell sites. Because of the emergency status, the Well was taken “off line” and the Town was allowed to use it only in case of fire or if the other two Town wells became unusable.

On January 8, 1991, the Town sent a letter to ARCO stating:

As you know, Sturbridge Town Well # 1 has been out of service since 1987 due to the threat of contamination from the former ARCO station (now Shell) on Route 20. Due to increasing water demands in the Town and the exclusive use of the remaining 2 wells for the past 3 + years, we are now faced with a potentially dangerous situation should a fire create a large demand and/or should one of the remaining wells go out of service for any reason. The Town, therefore, requests that action be taken immediately to restore Well # 1 to service or develop a new well.
It is our understanding that Shell Oil Company has assumed some responsibility in this matter and is currently funding further study at the site. Part of this study is pumping Well # 1 to determine whether or not any contaminants will be drawn into the Well, however, the test cannot be completed until the Well is cleaned (inactivity has caused *332 clogging) to increase capacity from the current 30 GPM +/- to the rated capacity of 410 GPM +/-. Shell has indicated to us that they are not responsible for the cleaning of the well, therefore, we are looking to ARCO to assume responsibility for the work (estimated to cost approximately $10,000) and to make provisions for the development of a new well should it prove to be necessary.
We trust that the documentation provided adequately demonstrates that the well has clogged due to the inactivity caused by the forced shutdown to avoid contamination of the municipal water supply. Pursuant to this, we ask that ARCO proceed with the cleaning of the well and, if found to be necessary, the planning for the development of a new well. If this work does not commence within 30 days, the town will be forced to take legal action.

The contaminant MBTE was, and continues to be, detected in the water in the Well. Historically, MBTE levels in the Well ranged from 10 to 12 parts per billion (“ppb”) of MBTE. On May 10, 1993, it was discovered that the Well contained 79.7 ppb of MBTE. That unusually high level of MBTE did not, however, render the Well unusable or unsafe. At a meeting held on June 8,1993, the DEP and the Town noted that the demand for water in the Town had increased dramatically. They outlined possible options for meeting the Town’s short-term and long-term water needs, including investigating possible leaks, installing a new well, increasing production from Well # 3, rehabilitating Well # 2, conducting wellhead treatment and installing an air sparging curtain between the Mobil Station and the Well. 1

On July 10, 1996, the DEP issued a Water Management Permit to the Town authorizing the withdrawal of water from all of the Town’s wells, including the Well, effective July 10, 1996 and expiring on August 31, 2013. On that same day, the DEP noted that until the Well was operational, the Town would likely continue to suffer water shortages.

On December 17, 1997, Attorney Peter Feuerbach from the law firm of Kopelman & Paige sent a demand letter to Mobil, Shell and ARCO notifying them that:

the Town has suffered property damage, both real and personal, in the form of diminution in value of its land due to the release and threat of release of oil and hazardous materials at and from the Shell/ARCO site and the Mobil site and the subsequent loss of use and damage •to Well. No. 1.

In October, 1998, the Town discovered that rehabilitation of the Well would not be feasible and that it would have to obtain a new water supply and develop a new well to meet its increasing water demand.

The Town’s water supply consultant has recommended a treatment system that will cost $100,000 for the first year of operation plus $50,000 for each subsequent year. The consultant has also recommended investigating the possible development of a new water system at an estimated cost of $150,000.

On December 12, 2000, the Town brought suit against Mobil, Shell and ARCO in Worcester Superior Court alleging property damage pursuant to M.G.L. c. 40 § 39G and the Massachusetts Oil and Hazardous Material Release Prevention and Response Act, M.G.L. c. 21E § 5, nuisance and negligence. It sought reim *333 bursement for costs incurred as a result of the contamination under M.G.L. c. 21E §§ 4 and 11A, damages, injunctive relief, fees and costs. The case was removed to this Court on February 9, 2001 based on diversity jurisdiction pursuant to 28 U.S.C. §§ 1332 and 1441(a) and (b).

Defendant Shell brought cross-claims against ARCO for contribution and contractual indemnity and against Mobil for contribution. Defendant Mobil asserted cross-claims against Shell for contribution under M.G.L. c. 231B and 21E § 4. Finally, ARCO brought cross-claims against Shell for breach of contract, declaratory judgment pursuant to M.G.L. c. 231A and two counts for contribution pursuant to M.G.L. c.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mystic Landing, LLC v. Pharmacia Corp.
417 F. Supp. 2d 120 (D. Massachusetts, 2006)
Lewis v. General Electric Co.
254 F. Supp. 2d 205 (D. Massachusetts, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
195 F. Supp. 2d 330, 2002 U.S. Dist. LEXIS 6912, 2002 WL 602733, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-sturbridge-v-mobil-corp-mad-2002.