Town of Richmond v. Cowan

Vermont Superior Court·Decided February 13, 2007·No. 102-05-02 Vtec·Published

Opinion

STATE OF VERMONT

ENVIRONMENTAL COURT

}

Town of Richmond, } Plaintiff, } }

v. } Docket No. 102-5-02 Vtec }

Isaac Cowan, } Defendant. } }

Decision and Order

This is an enforcement case related to the placement of a retaining wall on the property of Defendant Isaac Cowan. A description of the property and the resolution of other issues involved with this property, including the location of the flood plain in relation to the property, may be found in Environmental Court Docket Nos. 73-2-02 Vtec, 74-2-02 Vtec, 222-12-03 Vtec, 60-4-04 Vtec, and 105-5-06 Vtec; in Superior Court Docket No. S145-03 CnC; and in the decision of the Vermont Supreme Court in 2005 VT 126.

The Town of Richmond is represented by Mark L. Sperry, Esq.; Defendant is represented by John W. O’Donnell, Esq.; Intervenors Erica Ell and Edward Gaston are represented by David L. Grayck, Esq. The issue of whether there was a violation was concluded by this Court’s decision and order of June 9, 2003, issued in this case and in Docket No. 73-3-02 Vtec. As of June 9, 2003, the only remaining issues in this enforcement case related to what injunctive relief and monetary penalty, if any, would be appropriate for the violation. However, the scheduling of a hearing on those remaining issues was suspended while litigation proceeded on the mapped and actual location of the flood plain in relation to the property.

Three years later, after the remaining litigation had concluded, an evidentiary hearing was scheduled in this case before Merideth Wright, Environmental Judge. At the 2006 hearing, Defendant conceded that the entire retaining wall could be treated as being within the flood plain for the purposes of this enforcement action, and agreed to the removal of the retaining wall. The Court ordered on the record of that hearing that the retaining wall was to be removed, and requested the parties to file in writing their stipulation as to the remedial methodology involved with the removal of the retaining wall. The hearing proceeded only on the issue of the appropriate penalty for the violation.

The parties were given the opportunity to submit written requests for findings and memoranda of law. Upon consideration of the parties’ stipulation, the evidence, and the written memoranda and proposed findings, the Court finds and concludes as follows.

Because the parties agreed as to the removal of the retaining wall and the remedial site work required on the property, the remaining dispute is over what litigation expenses in this and in the other docket numbers should be considered in setting the penalty amount in this case. Defendant does not dispute that the penalty may account for the Town’s costs of obtaining the June 2003 order, but does dispute whether the Town is entitled to any of its expenses regarding the floodplain determination based on later engineering survey work.

The June 2003 order determined that the retaining wall was built in violation of the original permit, as that permit required the retaining wall to be built outside the floodplain, defined in the Zoning Regulations by its location on the Federal Emergency Management Agency maps and the most current Flood Insurance Rate Maps. The retaining wall consists of 196 concrete blocks, each 32 cubic feet in volume and weighing 4,800 pounds. The question of whether injunctive relief requiring the removal of the retaining wall was appropriate, however, was reserved in that decision, to allow Defendant to pursue the possibility of surveying his individual parcel and applying for a revision of the floodplain

location on his parcel. Zoning Regulations § 6.8.2. After the survey work had been completed, the Zoning Administrator and the DRB denied Defendant’s request for that revision; this Court and the Vermont Supreme Court ruled in Defendant’s favor that he was entitled to a determination of the actual location of the floodplain on his property, that is, that the DRB should have reached the merits of his application based on his engineering surveys. In re Appeal of Cowan, 2005 VT 126, ¶¶10–11. The Supreme Court remanded the matter to the DRB for that determination.

None of the costs of the litigation from the June 9, 2003 order to the December 13, 2005 remand decision of the Supreme Court should be considered in the monetary penalty to be imposed in this enforcement action, as the enforcement action was simply on hold while the parties litigated whether Defendant was entitled to a determination of the actual on-the-ground surveyed floodplain pertaining to his property, as opposed to the mapped floodplain.

However, as of the remand order from the Supreme Court, the engineering determination of whether the retaining wall was in the actual surveyed floodplain (as opposed to the undisputed fact from the June 2003 decision and order that it was in the mapped floodplain) was relevant to the appropriate injunctive relief in this enforcement action. That is, it was relevant to whether all or some part of the retaining wall should have been ordered to be removed, as that issue was still being contested.

The DRB hearing on the remand order was March 8, 2006; the DRB’s decision was issued on April 20, 2006. It was appealed to this court in May in Docket No. 105-5-06, and was withdrawn as moot at the merits hearing scheduled together with this enforcement case for August 2, 2006.

The Town employed an engineering firm to assist it in determining (and in evaluating Defendant’s engineer’s determination of) the location of the surveyed flood plain on Defendant’s property. The Town’s engineer came to the August 2, 2006 hearing

prepared to testify as to the location of the flood hazard district and that the entire retaining wall was actually in the flood hazard district, as well as to testify regarding the hazards that could result in a 100-year flood if the floodwaters were to undermine the wall and allow the concrete blocks to be deposited in the stream or to travel downstream onto other property in flood conditions. The Town’s engineering costs, including the Town’s costs of preparing the engineering testimony for trial, should be considered in setting an appropriate penalty in this matter.

However, the Town seeks its attorney’s fees, zoning administrator’s time, and engineering fees for everything it has expended on litigation involving this property, as if all the litigation were related to the enforcement action. Much of it has not been related to the enforcement action. Rather, some of that time and those fees were expended on the litigation, ultimately unsuccessful from the Town’s point of view, involving whether Defendant was entitled to have the surveyed location of the flood plain evaluated on his property.

Free access — add to your briefcase to read the full text and ask questions with AI

Town of Richmond v. Cowan, (Vt. Ct. App. 2007).

Town of Richmond v. Cowan (Town of Richmond v. Cowan) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In Re Appeal of Cowan
2005 VT 126 (Supreme Court of Vermont, 2005)
State of Vermont Agency of Natural Resources v. Riendeau
603 A.2d 360 (Supreme Court of Vermont, 1991)