Town of Richmond v. Cowan

CourtVermont Superior Court
DecidedFebruary 13, 2007
Docket102-05-02 Vtec
StatusPublished

This text of Town of Richmond v. Cowan (Town of Richmond v. Cowan) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Richmond v. Cowan, (Vt. Ct. App. 2007).

Opinion

STATE OF VERMONT

ENVIRONMENTAL COURT

} Town of Richmond, } Plaintiff, } } v. } Docket No. 102-5-02 Vtec } Isaac Cowan, } Defendant. } }

Decision and Order

This is an enforcement case related to the placement of a retaining wall on the

property of Defendant Isaac Cowan. A description of the property and the resolution of

other issues involved with this property, including the location of the flood plain in relation

to the property, may be found in Environmental Court Docket Nos. 73-2-02 Vtec, 74-2-02

Vtec, 222-12-03 Vtec, 60-4-04 Vtec, and 105-5-06 Vtec; in Superior Court Docket No. S145-03

CnC; and in the decision of the Vermont Supreme Court in 2005 VT 126.

The Town of Richmond is represented by Mark L. Sperry, Esq.; Defendant is

represented by John W. O’Donnell, Esq.; Intervenors Erica Ell and Edward Gaston are

represented by David L. Grayck, Esq. The issue of whether there was a violation was

concluded by this Court’s decision and order of June 9, 2003, issued in this case and in

Docket No. 73-3-02 Vtec. As of June 9, 2003, the only remaining issues in this enforcement

case related to what injunctive relief and monetary penalty, if any, would be appropriate

for the violation. However, the scheduling of a hearing on those remaining issues was

suspended while litigation proceeded on the mapped and actual location of the flood plain

in relation to the property.

1 Three years later, after the remaining litigation had concluded, an evidentiary

hearing was scheduled in this case before Merideth Wright, Environmental Judge. At the

2006 hearing, Defendant conceded that the entire retaining wall could be treated as being

within the flood plain for the purposes of this enforcement action, and agreed to the

removal of the retaining wall. The Court ordered on the record of that hearing that the

retaining wall was to be removed, and requested the parties to file in writing their

stipulation as to the remedial methodology involved with the removal of the retaining wall.

The hearing proceeded only on the issue of the appropriate penalty for the violation.

The parties were given the opportunity to submit written requests for findings and

memoranda of law. Upon consideration of the parties’ stipulation, the evidence, and the

written memoranda and proposed findings, the Court finds and concludes as follows.

Because the parties agreed as to the removal of the retaining wall and the remedial

site work required on the property, the remaining dispute is over what litigation expenses

in this and in the other docket numbers should be considered in setting the penalty amount

in this case. Defendant does not dispute that the penalty may account for the Town’s costs

of obtaining the June 2003 order, but does dispute whether the Town is entitled to any of

its expenses regarding the floodplain determination based on later engineering survey

work.

The June 2003 order determined that the retaining wall was built in violation of the

original permit, as that permit required the retaining wall to be built outside the floodplain,

defined in the Zoning Regulations by its location on the Federal Emergency Management

Agency maps and the most current Flood Insurance Rate Maps. The retaining wall consists

of 196 concrete blocks, each 32 cubic feet in volume and weighing 4,800 pounds. The

question of whether injunctive relief requiring the removal of the retaining wall was

appropriate, however, was reserved in that decision, to allow Defendant to pursue the

possibility of surveying his individual parcel and applying for a revision of the floodplain

2 location on his parcel. Zoning Regulations § 6.8.2. After the survey work had been

completed, the Zoning Administrator and the DRB denied Defendant’s request for that

revision; this Court and the Vermont Supreme Court ruled in Defendant’s favor that he

was entitled to a determination of the actual location of the floodplain on his property, that

is, that the DRB should have reached the merits of his application based on his engineering

surveys. In re Appeal of Cowan, 2005 VT 126, ¶¶10–11. The Supreme Court remanded the

matter to the DRB for that determination.

None of the costs of the litigation from the June 9, 2003 order to the December 13,

2005 remand decision of the Supreme Court should be considered in the monetary penalty

to be imposed in this enforcement action, as the enforcement action was simply on hold

while the parties litigated whether Defendant was entitled to a determination of the actual

on-the-ground surveyed floodplain pertaining to his property, as opposed to the mapped

floodplain.

However, as of the remand order from the Supreme Court, the engineering

determination of whether the retaining wall was in the actual surveyed floodplain (as

opposed to the undisputed fact from the June 2003 decision and order that it was in the

mapped floodplain) was relevant to the appropriate injunctive relief in this enforcement

action. That is, it was relevant to whether all or some part of the retaining wall should have

been ordered to be removed, as that issue was still being contested.

The DRB hearing on the remand order was March 8, 2006; the DRB’s decision was

issued on April 20, 2006. It was appealed to this court in May in Docket No. 105-5-06, and

was withdrawn as moot at the merits hearing scheduled together with this enforcement

case for August 2, 2006.

The Town employed an engineering firm to assist it in determining (and in

evaluating Defendant’s engineer’s determination of) the location of the surveyed flood

plain on Defendant’s property. The Town’s engineer came to the August 2, 2006 hearing

3 prepared to testify as to the location of the flood hazard district and that the entire

retaining wall was actually in the flood hazard district, as well as to testify regarding the

hazards that could result in a 100-year flood if the floodwaters were to undermine the wall

and allow the concrete blocks to be deposited in the stream or to travel downstream onto

other property in flood conditions. The Town’s engineering costs, including the Town’s

costs of preparing the engineering testimony for trial, should be considered in setting an

appropriate penalty in this matter.

However, the Town seeks its attorney’s fees, zoning administrator’s time, and

engineering fees for everything it has expended on litigation involving this property, as if

all the litigation were related to the enforcement action. Much of it has not been related to

the enforcement action. Rather, some of that time and those fees were expended on the

litigation, ultimately unsuccessful from the Town’s point of view, involving whether

Defendant was entitled to have the surveyed location of the flood plain evaluated on his

property.

The Court has attempted to determine from Exhibits 17, 22, and 24, and the

testimony of Mr. Rodjenski, which expenses can be attributed to the litigation that resulted

in the 2003 court order (including the motions for summary judgment), and which

expenses can be attributed to the engineering work and witness preparation regarding the

surveyed floodplain location, after the remand from the Supreme Court. The Court

anticipates setting a penalty that recognizes both sets of costs, but excludes costs accrued

during the period from June 9, 2003 through December 13, 2005. The Court does intend to

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Appeal of Cowan
2005 VT 126 (Supreme Court of Vermont, 2005)
State of Vermont Agency of Natural Resources v. Riendeau
603 A.2d 360 (Supreme Court of Vermont, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
Town of Richmond v. Cowan, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-richmond-v-cowan-vtsuperct-2007.