Town of Richmond v. Cowan

Vermont Superior Court·Decided June 4, 2007·No. 102-05-02 Vtec·Published

Opinion

STATE OF VERMONT

ENVIRONMENTAL COURT

} Town of Richmond, } Plaintiff, } } v. } Docket No. 102-5-02 Vtec } Isaac Cowan, } Defendant. } }

Decision and Order on Pending Motions and Penalty

This is an enforcement case related to the placement of a retaining wall on the

property of Defendant Isaac Cowan. In its Decision and Order of February 13, 2007,1 the

Court resolved the timing and conditions of the order for injunctive relief, but required

additional memoranda relating the bills submitted in evidence to the specific components

of the parties’ arguments relating to the penalty amount. The Town of Richmond is

represented by Mark L. Sperry, Esq. and Defendant is represented by John W. O’Donnell,

Esq. Intervenors Erica Ell and Edward Gaston are represented by David L. Grayck, Esq.,

but have not taken an active role in the arguments relating to the penalty phase of this

enforcement case.

To assess an appropriate penalty, it is necessary to understand the timeline of all the

related litigation. The beginning date for the violation is September 1, 2001, after the

expiration of the period to cure the violation given in the August 23, 2001 Notice of

1 The Town moved to correct the date of issuance of the decision found on page 8 of the decision to conform to the actual date of issuance (as stamped on the first page of the decision) of February 13, 2007; that correction has been made.

1 Violation.

The issue of whether there was a violation was concluded by this Court’s decision

and order of June 9, 2003 (issued in this case, in Docket No. 73-3-02 Vtec, and in a related

superior court case, Docket No. S145-03 CnC), slip op. at p. 7:

In Docket No. 102-5-02 Vtec, the Town requests injunctive relief and a monetary penalty in an enforcement action against Appellant for the construction of the existing retaining wall. Appellant failed to appeal the August 23, 2001 Notice of Violation and therefore cannot contest the violation. If Appellant intends to remove the existing retaining wall when and if the house is built, that may go to the appropriateness or timing of the injunctive relief, but not to the existence of the violation. Appellant’s motion for summary judgment must be DENIED and summary judgment GRANTED to the Town on the issue the existence of the violation as to the existing retaining wall.

That decision, as altered by the motion to alter granted at a conference held on July 1, 2003,

concluded Docket No. 73-3-02 Vtec. However, the parties proceeded over the summer of

2003 to prepare for a consolidated trial both in this enforcement case and in the related

superior court case (regarding approval of the proposed septic system). Although the trial

was originally scheduled for October of 2003, the parties informed the Court at a

conference held on September 2, 2003 that two new applications were being filed that

should be coordinated with these matters, one regarding the installation of rip-rap and the

other regarding the placement of the house location on the property. At a follow-up

conference on September 29, 2003, the trial was postponed (initially to January of 2004).

The February 13, 2007 order stated that the Court anticipated setting a penalty that

would exclude costs accrued during the period from June 9, 2003 through December 13,

2005. However, the Town is correct in its argument that the June 9, 2003 order should not

be used as the suspension date for the parties’ expenses in the enforcement case. Rather,

the parties’ work on the motion to alter and on trial preparation continued towards the

expected use of the scheduled October 2003 and January 2004 trial dates for the

2 enforcement case. A review of the docket entries in all of the related cases reflects that the

remedy and penalty issues in the enforcement case were being prepared for an October

2003 trial through the summer of 2003. At an October 10, 2003 conference they were

rescheduled for a January 28, 2004 hearing, so that two new applications filed at the DRB

on the installation of rip-rap and the placement of the house could be heard with it.

In December of 2003, Defendant appealed the denial of the house location (Docket

No. 222-12-03 Vtec) and initially the parties hoped to include that appeal in the already-

scheduled trial. However, also in late 2003 the Town adopted new septic regulations,

under which Defendant filed a new application for septic system approval. The parties

agreed that if it were granted it would conclude the superior court case, that the January

trial date also could not be used, and that trial on the Environmental Court cases should

be further postponed, and trial dates were again reserved for May and June of 2004.

On January 14, 2004 Defendant had also applied to the Zoning Administrator (and

later appealed to the DRB) for a determination that the actual on-the-ground or surveyed

boundary of the flood hazard district was different from that shown on the maps defining

the district. Defendant appealed the DRB’s March 31, 2004 decision (which had declined

to make such a determination) to this Court in Docket No. 60-4-04 Vtec on April 6, 2004.

Because both other pending cases (the above-captioned enforcement case and Docket No.

122-12-03 Vtec) depended on the location of the flood hazard district boundary, the parties

and the Court agreed that the May and June hearing dates, including any hearing on

injunctive relief and the appropriateness or components of a monetary penalty, should be

postponed until the resolution of Docket No. 60-4-04 Vtec. The enforcement case was

therefore suspended as of April 6, 2004. The period of violation from September 1, 2001

through April 6, 2004 was 948 days.

For the purposes of assessing the parties’ costs of preparing evidence for the

redetermination proceeding, we must use the date on which the Supreme Court upheld

3 this Court’s decision and remanded the matter for the DRB to proceed with the merits of

the floodplain redetermination. On the other hand, for the purposes of assessing the total

number of days of violation, and the avoided-cost time period during which Defendant

avoided having to remove the retaining wall, we must use the date on which the DRB ruled

on the merits of that proceeding, that is, on which the DRB first determined that the

retaining wall was in the surveyed floodplain (as well as in the mapped floodplain): April

20, 2006.

The DRB’s decision was appealed in Docket No. 105-5-06 Vtec. At the August 2,

2006 hearing,2 Defendant conceded that the entire retaining wall could be treated as being

within the flood plain for the purposes of this enforcement action, and Docket No. 105-5-06

Vtec was concluded as withdrawn at the hearing, without the presentation of evidence.

The hearing proceeded with the presentation of evidence only on the issue of an

appropriate penalty for the violation in the enforcement case, as the Court granted

injunctive relief at that hearing and required the parties to file a stipulation as to the

methodology involved with the removal of the retaining wall. After the parties filed their

memoranda of law and that stipulation, the Court’s Decision and Order issued February

13, 2007, imposed the agreed remedial order, but requested further memoranda separating

and analyzing the various components of the parties’ evidence and arguments as to the

appropriate penalty amount, the last of which was filed on March 23, 2007. The period

Free access — add to your briefcase to read the full text and ask questions with AI

Town of Richmond v. Cowan, (Vt. Ct. App. 2007).

Town of Richmond v. Cowan (Town of Richmond v. Cowan) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Town of Hinesburg v. Dunkling
711 A.2d 1163 (Supreme Court of Vermont, 1998)
State of Vermont Agency of Natural Resources v. Riendeau
603 A.2d 360 (Supreme Court of Vermont, 1991)