Town of Renner v. Wiley

458 S.W.2d 516, 1970 Tex. App. LEXIS 1985
CourtCourt of Appeals of Texas
DecidedJuly 17, 1970
Docket17442
StatusPublished
Cited by4 cases

This text of 458 S.W.2d 516 (Town of Renner v. Wiley) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Renner v. Wiley, 458 S.W.2d 516, 1970 Tex. App. LEXIS 1985 (Tex. Ct. App. 1970).

Opinion

DIXON, Chief Justice.

On February 19, 1969 appellee N. Bruce Wiley filed suit seeking injunctive relief against appellant Town of Renner, Texas and also against Texas Power & Light Company. In his amended petition appellee asks that Town of Renner be commanded to desist and refrain from interfering with the connection of electrical power utilities to appellee’s land. As to Texas Power & Light Company appellee asks for a mandatory injunction directing the Company to furnish his land with electrical power utilities. *

*518 On October 10, 1969 the trial court rendered judgment granting both injunctions. Only Town of Renner has appealed.

This is the second time these litigants have brought their continuing controversy to us on appeal. For the previous appeal see Town of Renner v. Bruce Wiley, 429 S.W.2d 945 (Tex.Civ.App., Dallas, 1968, no writ).

The Town of Heath, Texas, with our permission, has filed a brief as Amicus Curiae. In its brief Amicus Curiae supports the position of appellant Town of Renner.

The evidence consists of stipulations, a number of exhibits and answers to interrogatories.

STIPULATIONS

The parties stipulated that appellee Wiley is the owner of 3.17 acres of land on which he started construction of a trailer court in April 1967 and had occupied the land with two trailers at that time. On September 13, 1967 the trailer court was completed as to eleven spaces and in 1967 some time after December 18, 1967 Wiley completed the court as to twenty-eight spaces and made application to Texas Power & Light Company for additional utility connections. The application was acknowledged and accepted by Texas Power & Light Company, but the installation of the additional service was never completed. Wiley has made several attempts to obtain the additional power from Texas Power & Light Company.

On July 23, 1968 appellee Wiley presented an application to the Town of Ren-ner for a building permit and certificate of occupancy and the Town Commission met on July 29, 1968 to consider the application. On that date the Commission passed a resolution deferring action on Wiley’s application to allow the applicant to amend his application to conform to the Town’s ordinances.

EXHIBITS

Among the exhibits which were intro-ducted into evidence without objection were ordinances of the Town of Renner dated November 18, 1966 (Comprehensive Zoning Ordinance and an ordinance providing for the issuance of building permits); March 18, 1968 (Comprehensive Zoning Ordinance and an ordinance pertaining to the subdivision of land); July 1, 1968 (prescribing regulations pertaining to the building of structures for human habitation); August 12, 1968 (in regard to fire limits and construction, alteration, removal, demolition, equipment, use and occupancy, location and maintenance of buildings); December 9, 1968 (electrical installation and maintenance) ; March 6, 1969 (installation, operation and maintenance of plumbing).

ANSWERS TO INTERROGATORIES

In answering interrogatories appellant Town of Renner stated that there was no record of an application for a building permit prior to December 8, 1967 and no record of a building permit being issued prior to said date; Texas Power & Light Company has never made a request for any permit with regard to the application of Wiley; the position of Temporary Building Inspector was created on November 18, 1966; every application for a building permit has been referred to either the Temporary Building Inspector, or the Building Inspector, the number being twenty-six; appellant has no objection to Texas Power & Light Company furnishing additional power, poles and meters to appellee’s land so long as the poles to be set do not unreasonably interfere with traffic — however before Texas Power & Light Company is authorized to connect its services to any building constructed, or altered, or any building moved into town, or from one location to another within the Town, a building permit and a certificate of occu-pany must be procured, showing the compliance with all the ordinances and regulations of the Town; the procedure neces *519 sary to obtain a building permit is to file an application with the Town Secretary; to obtain a certificate of occupancy, file a request with the Town Secretary for an inspection of the building for which a certificate of occupancy is desired.

In answer to interrogatories Boyd Williams, District Manager of Texas Power & Light Company, stated that the Company did not refuse the application of Wiley for additional service; the Company started the job of furnishing power to appellee but stopped because the Town had not issued a permit to Wiley; the Company gives service to each applicant within the corporate limits of the Town when furnished by the Town with a certificate of occupancy.

In answer to interrogatories Texas Power & Light Company stated that (1) by application dated January 11, 1968 Wiley requested the installation of additional poles and service lines; (2) the Company did not complete the furnishing of the additional service because (3) the Town of Renner informed the Company that Wiley had not secured a building permit and a certificate of occupancy; (4) the Town had contacted the Company and (5) furnished the Company with a copy of the ordinance of November 18, 1966 providing that no firm holding franchise from the Town should furnish light or power to any building erected structurally altered or moved within the Town unless the owner should obtain a building permit and a certificate of occupancy; and (6) the franchise that the Company holds from the Town provides that service furnished by the Company to the inhabitants of Renner shall be subject to the rules and regulations of the Town.

FINDINGS OF FACT AND CONCLUSIONS OF LAW

The trial court filed findings of fact and conclusions of law. Among the findings were the following:

“3. That plaintiff commenced construction of a trailer court on the 3.173 acres of land in April of 1967, and occupied the land with two trailers. That on September 13, 1967, the trailer court was complete as to eleven spaces, and that in 1967, some time after December 18, 1967, the trailer court was completed as to twenty-eight spaces.
4. That, in December of 1967, when the trailer court was complete, all drainage, plumbing and sewerage systems were also complete.
5. That there is no evidence in the record that the drainage, plumbing or sewerage systems as completed, were substandard or unsatisfactory.
6. In January of 1968, plaintiff made application to defendant, TEXAS POWER & LIGHT CO., for additional electrical service which application was acknowledged and accepted by TEXAS POWER & LIGHT CO.
7. That TEXAS POWER & LIGHT CO. was ready and willing to furnish the additional electrical power service requested by plaintiff.
8. That TEXAS POWER & LIGHT CO. did not furnish the additional electrical power service requested by plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Texas Attorney General Opinion
Texas Attorney General Reports, 1999
Opinion No.
Texas Attorney General Reports, 1999
City of Dallas v. Crownrich
506 S.W.2d 654 (Court of Appeals of Texas, 1974)
City of University Park v. Benners
485 S.W.2d 773 (Texas Supreme Court, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
458 S.W.2d 516, 1970 Tex. App. LEXIS 1985, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-renner-v-wiley-texapp-1970.