Town of Poughkeepsie v. Holden Construction Co.

104 A.D.2d 873, 480 N.Y.S.2d 384, 1984 N.Y. App. Div. LEXIS 20339
CourtAppellate Division of the Supreme Court of the State of New York
DecidedOctober 9, 1984
StatusPublished
Cited by1 cases

This text of 104 A.D.2d 873 (Town of Poughkeepsie v. Holden Construction Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Poughkeepsie v. Holden Construction Co., 104 A.D.2d 873, 480 N.Y.S.2d 384, 1984 N.Y. App. Div. LEXIS 20339 (N.Y. Ct. App. 1984).

Opinion

— In an action to recover on performance bonds, defendants Holden Construction Co., Inc. (Holden) and Republic Insurance Company (Republic) separately appeal from a judgment of the Supreme Court, Dutchess County (Jiudice, J.), entered February 3, 1983, which awarded damages to plaintiff payable by both appellants.

Judgment modified, on the law, by deleting the decretal paragraph designated “(a)” and the other provisions thereof against Holden and the action is severed as to Holden. As so modified, judgment affirmed, with costs to the town payable by Republic, and new trial granted as to Holden only.

[874]*874On or about August 24, 1972, defendant Holden made an application to the Town of Poughkeepsie (town) for approval of a subdivision site plan entitled “ ‘Holden On Hudson’ Phase I”. The town granted approval of the aforesaid subdivision map provided, inter alia, that Holden post a performance bond pursuant to subdivision 1 of section 277 of the Town Law to guarantee the completion of certain water and sanitary sewers, roads and storm sewers. On or about March 8,1974, Holden, as principal, defendants Schwartz and Silver as coprincipals, and Republic as surety, executed and delivered two bonds to the town in satisfaction of the aforesaid contractual provisions. The sole condition of the bonds, which were identical in terms, was that if within two years from the date of the bonds, the principal, Holden, completed the construction and installation of the bonded work, then the bonds were to be null and void; otherwise the bonds were to remain in full force and effect.

Holden commenced work on the project and by March, 1976 had completed some 50% to 60% of the total project. Work however was discontinued by Holden and although construction of all of the apartment units had been commenced by Holden, none of the units were fully completed so as to be ready for occupancy. Holden also commenced but failed to complete installation and construction of the water and sanitary sewers, storm sewers and roads pursuant to the terms set forth in the subdivision map and the aforesaid bonds.

Holden thereafter defaulted on its mortgage to its construction lender, Bankers Trust Company (bank). The bank ultimately foreclosed on the mortgage and acquired title to the uncompleted project. In November, 1977, the bank and the town reached an agreement whereby the bank assumed the responsibility of completing the bonded improvements and to bear the cost thereof in consideration for the town’s promise to declare the two bonds in default and make a demand upon Republic to comply with its obligations thereunder. If Republic did not comply with the demand, the town agreed to institute an action to recover on the bonds. Any proceeds received from Republic either pursuant to the demand or as a result of a lawsuit were to be remitted to the bank.

In January, 1978, the town declared the two bonds in default and demanded payment from Republic in the amount of the bonds. Republic refused to comply with the demand stating that the bank, by taking over possession of the subject premises, assumed the obligations of Holden, and, thus, would have to perform the work in accordance with the municipal resolutions. In April, 1978, the town commenced an action against Holden, [875]*875Silver, Schwartz and Republic seeking recovery of the full amounts of the two bonds. Republic interposed an answer containing several affirmative defenses. Republic also cross-claimed against Holden, Silver and Schwartz.

In August, 1978, Republic moved for summary judgment on its cross claim and the town cross-moved for summary judgment on its complaint. Republic opposed the town’s summary judgment motion on the basis, inter alia, that the town did not suffer any loss due to Holden’s default because there were no residents at the time of the default and thus none of the bonded improvements were necessary under subdivision 1 of section 277 of the Town Law. In addition, Republic noted that the town would not suffer a loss since the bank was actively negotiating to sell the project to a new developer which planned to complete the project in accordance with the town’s subdivision requirements.

During the pendency of the summary judgment motions, the bank entered into a written agreement with a new developer, Chelsea Ridge Associates (Chelsea), whereby the developer agreed to complete the project in accordance with the town’s subdivision map requirements. Paragraph 3 of the agreement stated, inter alia, “Purchaser further acknowledges that there is now substantial work that remains to be done in connection with the construction of roads, storm and sanitary sewers and water lines in order to satisfy the requirements of the Town, as referred to in the Letter Agreement, and as set forth in a certain map, with which purchaser is also familiar, entitled, ‘Holden on Hudson Phase F (the ‘Work’). Purchaser confirms its understanding that the purchase price for the Premises of $400,000 this day paid by Purchaser to Seller was reduced to reflect the cost of performing the Work, whether done by Purchaser or another, and the right of Seller to receive all proceeds recovered on the bonds, as provided for in the Letter Agreement, in consideration of Seller’s undertaking to reimburse the Town for the cost of the Work and the expenses incurred in prosecuting the claim on the bonds; and Purchaser acknowledges that it has agreed to, and did, purchase the Premises for such price after having first made its own investigation and determination of all costs that may be incurred in order to perform and complete the Work to the satisfaction of the Town. Accordingly, Purchaser covenants and agrees as follows, each of said covenants and agreements to survive the closing of title and delivery of the deed which occurred this day”.

Subsequently, the town’s cross motion for summary judgment was granted and a judgment was entered against Republic in the full amount of the bonds. Republic was awarded partial [876]*876summary judgment against Holden and Schwartz as to liability only.

Republic appealed from so much of the judgment as granted summary judgment against it. On appeal, Republic essentially maintained that since there were no residents of the subdivision project at the time of Holden’s default, no public improvements were necessary and thus no recovery on the bonds was warranted under subdivision 1 of section 277 of the Town Law. By decision and order dated August 13, 1979, this court remitted the matter for a trial solely to assess the town’s damages resulting from the developer’s breach (Town of Poughkeepsie v Holden Constr. Co., 71 AD2d 886).

Prior to the trial on damages, Republic made a motion pursuant to CPLR 2221 and 4404 for renewal, and to vacate Special Term’s granting of summary judgment against it on the basis of newly discovered evidence. Republic stated, inter alia, that subsequent to the submission of its appeal, it had learned that the developer Chelsea had fully completed the bonded improvements without any cost to the town and, thus, no loss was suffered by the town as a result of Holden’s default. Special Term granted Republic renewal, but upon further consideration, adhered to its original decision as modified by this court’s order.

Thereafter, a trial was held solely on the issue of damages. At the conclusion of the trial, judgment was entered against Republic and Holden in the full amount of the bonds. Both Republic and Holden appeal from said judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Peekskill v. Continental Insurance
999 F. Supp. 584 (S.D. New York, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
104 A.D.2d 873, 480 N.Y.S.2d 384, 1984 N.Y. App. Div. LEXIS 20339, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-poughkeepsie-v-holden-construction-co-nyappdiv-1984.