Town of Melville v. Safeco Ins. Co. of America
This text of 651 So. 2d 404 (Town of Melville v. Safeco Ins. Co. of America) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
TOWN OF MELVILLE, Plaintiff-Appellee,
v.
SAFECO INSURANCE COMPANY OF AMERICA, Defendant-Appellant.
Court of Appeal of Louisiana, Third Circuit.
*406 Jeffrey Michael Bassett, Opelousas, for Town of Melville.
Richard Mary, Baton Rouge, for Safeco Ins. Co. of America.
Before YELVERTON, THIBODEAUX and DECUIR, JJ.
THIBODEAUX, Judge.
Defendant, Safeco Insurance Company of America, appeals the trial court's judgment of their liability as the surety on a performance bond. The town of Melville contracted with Mar-Len to perform improvements to the town's sewer collection system. Mar-Len defaulted on its contract by leaving the project before completion. Safeco was the surety on the performance bond for Mar-Len.
Mar-Len demanded arbitration under its contract with the town. In the arbitration proceedings, the town was awarded $63,321.00, plus interest. The town of Melville sued Safeco in a separate district court proceeding and filed a motion for partial summary judgment against Safeco for the sum awarded in arbitration. Safeco opposed the motion, asserting it had personal defenses which were not presented in the arbitration proceedings.
The trial court granted the town's motion for partial summary judgment, finding the arbitration award bound Safeco for $63,321.00. This court affirmed. Town of Melville v. Safeco Insurance Company of America, 589 So.2d 625 (La.App. 3d Cir.1991). On writs to the supreme court, our judgment was reversed in a per curiam decision. The case was remanded to district court to allow Safeco to present issues of material fact related to personal defenses which may not be precluded by the arbitration award.
In district court, the parties submitted the evidence taken in the arbitration proceedings and other documents. The trial judge found Safeco was obligated by its performance bond to pay completion costs of the job Mar-Len contracted to perform. The trial judge determined the parties ratified the arbitration award by seeking judicial recognition of the award. He awarded $63,321.00 plus legal interest until paid, and also awarded $75,000.00 in attorney's fees as due under the contract and the performance bond.
We affirm the trial court's ruling on the liability of Safeco, the limits of the arbitration award, and the attorney's fees due under the contract and bond.
ISSUES
The central issue on appeal is whether an arbitration award is binding on a surety when the principal has defaulted on its contract.
LAW & DISCUSSION
The trial judge did not err in his application of the law. The facts found by the trial judge are reasonable in light of the record, and he properly applied the law. We find the trial judge's reasons for judgment are legally sound and logically articulated and hereby incorporate them into this opinion and adopt them as our own.
The trial judge wrote:
"In May of 1983, the Town entered into a written contract with Mar-Len of Louisiana, Inc. for the construction of a sewage collection system for the Town. The contract obligated Mar-Len to furnish a surety bond of $1,588,630.00, which it did furnish. Safeco became surety on the bond on May 31, 1983."
"Mar-Len defaulted on the contract and ceased performing any work on the project on August 14, 1985."
*407 "Thereafter, on the recommendations of its engineer, the Town, through its attorney, formally terminated the contract by a letter dated September 27, 1985."
"The instant suit was then filed against Mar-Len and Safeco. Safeco filed its exception of prematurity relying on the arbitration clause in the contract between the Town and Mar-Len."
"A dispute arose over the validity of the arbitration clause in the contract and in the suit entitled `Town of Melville v. Mar-Len, Civil Docket No. 85-0425-A', Judge Pavy upheld the validity of the arbitration clause."
"Mar-Len then sought relief under arbitration. An arbitration hearing was held and the panel rendered an opinion on September 27, 1987 wherein Mar-Len was ordered to pay to the Town the sum of $63,321.00 plus legal interest from the date of the award until paid. (See Plaintiff's Exhibit #6). The sum awarded in arbitration was the sum awarded in the Town's motion for summary judgment."
"Safeco assumes the position that it is not responsible under its bond for the sums awarded by the arbitration panel. It relies on Civil Code Article 3047 as it is written today. The instant case is governed in part by C.C.-Art. 3061 as it was written when the facts of this case occurred."
"The Civil Code articles on Suretyship as written when the facts of this case occurred are not fully applicable to this case because these articles pertain to commercial suretyships and not compensated sureties. See comments under C.C.-Art. 3062, as written today; LSA-R.S. 9:4812(E)(2). The instant case is one governed by the Public Contracts Law, R.S. 38:2211 et seq."
"LSA-R.S. 38:2216, as it was written during the time frame of this case, provided that the party to whom a public contract had been awarded was obligated to `furnish good and solvent bond ... for the faithful performance of his duties.' While LSA-R.S. 9:4812(E)(2) provides a compensated surety on a contract for private works with a similar remedy provided to commercial sureties by C.C.-Art. 3062 (formerly C.C.-Art. 3061), no comparable provision is found in the statutes relating to sureties on contracts for public works. But the appellate courts have held that former C.C.-Art. 3061 was applicable to public works contracts. See State v. Wilco Construction Company, Inc., 393 So.2d 885 (La. App. 4th Cir.1981)."
"The performance bond of Safeco in this case provides in pertinent part the following:
`... (The surety) shall fully indemnify and save harmless the Owner (Town) and Government from all costs and damages which it may suffer by reason of failure to do so, and shall reimburse and repay the Owner and Government all outlay and expense which the Owner and Government may incur in making good any default ...'
The Court construes this language as obligating Safeco to pay for the costs of completion of the job that Mar-Len had contracted to perform."
"The contested issues were submitted to arbitration pursuant to contractual provisions in the construction contract between the Town and Mar-Len. No one, including this Court, has been able to offer any explanation for the award made by the arbitrators in this case. The award, in this Court's opinion was subject to judicial attack, but the parties to the arbitration apparently ratified the award by seeking judicial recognition. See Housing Authority of New Orleans v. Henry Ericsson Co., 2 So.2d 195, 197 La. 732 (1941)."
"This Court considers the $63,321.00 arbitration award only as setting the upper limits of Safeco's obligation. The award of an arbitrator is res judicata. Bergeron v. Gassen, 185 So.2d 106 (La.App. 4th Cir.1966). In Wiemann v. Marnegra, [sic] 112 La. 305, 36 So. 358 (1904) the Supreme Court held that `A Judgment in favor of the principal is necessarily conclusive in favor of the surety since the liability of the principal is the only bond upon which that of the surety can be predicated; and for the same reason a judgment against the principal is conclusive in favor of the surety insofar as that no judgment for a greater amount can be rendered against him.'" (Emphasis added)
*408
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
651 So. 2d 404, 94 La.App. 3 Cir. 1039, 1995 La. App. LEXIS 513, 1995 WL 81891, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-melville-v-safeco-ins-co-of-america-lactapp-1995.