Town of La Conner v. American Construction Co.

585 P.2d 162, 21 Wash. App. 336, 1978 Wash. App. LEXIS 1931
CourtCourt of Appeals of Washington
DecidedSeptember 25, 1978
Docket5320-1
StatusPublished
Cited by6 cases

This text of 585 P.2d 162 (Town of La Conner v. American Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of La Conner v. American Construction Co., 585 P.2d 162, 21 Wash. App. 336, 1978 Wash. App. LEXIS 1931 (Wash. Ct. App. 1978).

Opinion

*337 Dore, J.

— Plaintiff Town of La Conner sued American Construction Company, Inc., and Safeco Insurance Company of America for forfeiture of a bid bond posted by the defendants in connection with American's bid on a municipal sanitary sewer system. The trial court held fór the defendants. Plaintiff appeals. We affirm.

Issues

Issue 1: Was there substantial evidence to support the trial court's judgment of dismissal?

Issue 2: Did the trial court err in finding that American Construction Company had made an "error," and in holding that such defendants acted in complete good faith, without negligence and had promptly notified plaintiff on discovering the error, and consequently its bid bond should not be forfeited?

Issue 3: Did the trial judge err in admitting into evidence defendants' exhibit No. 17?

Facts

The trial court's findings of fact Nos. 2, 3, 4 and 5 are unchallenged and, therefore, will be considered verities. They are succinctly stated and we believe it would be helpful to set them forth in text.

Finding of fact No. 2:

On or about June 13, 1974, plaintiff issued a call for bids for Sewerage and Water System Improvements, Schedules 1 through 5. Bid opening was set for July 15, 1974. Specifications for the project work and drawings were prepared by plaintiff's authorized engineers, Stevens, Thompson & Runyan. Prior to bid date, plaintiff issued Addendum No. 1 dated July 10, 1974, and Addendum No. 2 dated July 11, 1974, to the Specifications. Defendant American obtained a copy of the Specifications, Drawings, Addendum and Bid Forms for the purpose of considering submitting a bid.

Finding of fact No. 3:

On July 15, 1974, defendant American submitted a bid upon Schedule 5, together with a Bid Bond in the amount of 5% of its bid, which bond was furnished by *338 defendant Safeco, as surety. The bids were opened on July 15, 1974, and bids were received upon Schedule 5 as follows, together with the plaintiff's engineer's estimate.
Plaintiff's Engineer's Estimate $200,109.00
American 171,530.62
A. H. Powers, Inc. 241,445.40
Snelson, Inc. 247,120.15

The bids and plaintiff's engineer's estimate for Item No. 5, 6" channel crossing, were as follows:

Plaintiff's Engineer's Estimate $105,000.00
American 35,000.00
A. H. Powers, Inc. 80,000.00
Snelson, Inc. 132,250.00

Finding of fact No. 4:

When defendant American learned of the bid results, it noted the large discrepancy between its bid, the other bids and the plaintiff's engineer's estimate. It then reviewed its bid and the Specifications and Drawings and Addendums and considered that the Specifications with respect to Item No. 5 were confusing and subject to interpretation other than as defendant American had interpreted it, and that if its interpretation was not correct, then it had made an error in its bid.

Finding of fact No. 5:

Under date of July 22, 1974, defendant American informed plaintiff by letter (Exhibit No. 10) of its interpretation of the Specifications and pointed out the confusion and directed that its bid should be disregarded unless its interpretation as described was acceptable to plaintiff for performance of the contract work. Plaintiff did not make any response to defendant American's July 22, 1974, letter under September 19, 1974. The Specifications were confusing, largely as a result of the change made in the Specifications by Addendum No. 2. The Specifications provided that plaintiff had procured a permit from the Army Corps of Engineers for performance of the channel crossing work. In fact, no such permit had been then obtained, and none was issued for the work until August 19, 1974. The Specifications required the contractor to perform the channel crossing work in *339 accordance with the Corps of Engineers permit. The conditions of the Corps of Engineers permit conflicted with the Specifications as amended by Addendum No. 2.

(Italics ours.)

Without making any response to defendant American's letter on August 20, 1974, plaintiff accepted the bid of American and notified such defendant that it was awarded the contract and directed it to prepare a contract in the amount of its bid. American refused because of the error in its bid. Plaintiff then awarded the contract to the second bidder, A. H. Powers, Inc., for the precise amount of the latter's bid. Powers subsequently completed the contract work.

Decision

Issues 1 and 2: Clover Park School Dist. 400 v. Consolidated Dairy Prods. Co., 15 Wn. App. 429, 433, 550 P.2d 47 (1976), set forth the guidelines the court should follow in determining whether or not a successful bidder would be able to rescind a bid contract and avoid forfeiture of his bid bond. On pages 433-35 the court stated:

The propriety of relief from a contract when a mistaken bid calculation is promptly made known to the offeree is discussed in Donaldson v. Abraham, 68 Wash. 208, 122 P. 1003 (1912) and Puget Sound Painters, Inc. v. State, 45 Wn.2d 819, 278 P.2d 302 (1954). In those cases, erroneously computed bids were submitted to governmental entities along with mandatory bid bonds, and the error in each case was immediately made known to the offeree. The bidder in each case was successful in preventing forfeiture of its bid bond.
In Puget Sound Painters, Inc. v. State, supra, the court set forth guidelines as to when forfeiture of a bid bond should be enjoined — and by clear inference, when a bid contract can be rescinded — where a unilateral and material mistake is made in the offeror's bid and the error is called to the attention of the offeree before he has changed his position in reliance thereon. Under these guidelines relief will be decreed:
(a) if the bidder acted in good faith, and (b) without gross negligence, (c) if he was reasonably prompt in *340 giving notice of the error in the bid to the other party, (d) if the bidder will suffer substantial detriment by forfeiture, and (e) if the other party's status has not greatly changed, and relief from forfeiture will work no substantial hardship on him.

Puget Sound Painters, Inc. v. State, supra at 823.

However, rescission of an agreement once made must be prompt upon discovery of the facts warranting such an action. Bayley v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gill v. Waggoner
828 P.2d 55 (Court of Appeals of Washington, 1992)
Peter Kiewit Sons' Co. v. Department of Transportation
635 P.2d 740 (Court of Appeals of Washington, 1981)
City of Devils Lake v. St. Paul Fire & Marine Insurance
497 F. Supp. 595 (D. North Dakota, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
585 P.2d 162, 21 Wash. App. 336, 1978 Wash. App. LEXIS 1931, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-la-conner-v-american-construction-co-washctapp-1978.