Peter Kiewit Sons' Co. v. Department of Transportation

635 P.2d 740, 30 Wash. App. 424, 1981 Wash. App. LEXIS 2785
CourtCourt of Appeals of Washington
DecidedOctober 12, 1981
Docket4614-II
StatusPublished
Cited by4 cases

This text of 635 P.2d 740 (Peter Kiewit Sons' Co. v. Department of Transportation) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peter Kiewit Sons' Co. v. Department of Transportation, 635 P.2d 740, 30 Wash. App. 424, 1981 Wash. App. LEXIS 2785 (Wash. Ct. App. 1981).

Opinion

Reed, C.J.

— The Washington State Department of Transportation (State) appeals from a summary judgment order releasing Peter Kiewit Sons' Company (Kiewit) from its low bid on a highway construction project and enjoining the State from declaring a forfeiture of Kiewit's bid bond. We reverse and remand for a full trial on the merits.

On October 22, 1979, the State advertised for bids on a *426 major highway construction project entitled East Mercer Interchange-Phase I. Bid opening was set for 10 a.m. on November 28, 1979. On the morning of the bid opening, a representative of Kiewit submitted a bid dated November 26, 1979. As required, Kiewit also posted a bid bond in the amount of 5 percent of its bid.

Of the four bids received, Kiewit's bid, in the amount of $9,931,749.57, was the lowest. The other three were $12,128,632.87; $12,827,309.09; and $14,986,516.65 respectively. The State's estimate for the project was $9,718,747.32.

On December 5, 1979, Kiewit notified the State by telephone that it suspected a mistake in its bid. The State received notice of Kiewit's claimed mistake by telegram on December 7, 1979, and by letter on December 10, 1979. The letter requested that the State release Kiewit from its bid and from forfeiture of the bid bond. The State rejected these claims of mistake and Kiewit was awarded the contract on December 13, 1979.

On December 17, 1979, Kiewit filed a declaratory judgment action, asking the court to relieve it from its bid and to exonerate its bid bond. By filing an affidavit and motion, Kiewit obtained an order to show cause why summary judgment should not be granted in its favor. The State responded by filing several affidavits in support of its argument that there were genuine issues of material fact that precluded summary disposition of the matter. The trial court concluded that the pleadings and affidavits raised no genuine issues of material fact and granted summary judgment in favor of Kiewit.

After the trial court's decision the State determined that the most appropriate course of action was to reject all the remaining bids and readvertise. This determination was based on the fact that acceptance of the second low bid, which exceeded the State's estimate for the cost of the project by more than 7 percent, would have resulted in the loss of federal matching funds. The specifications accompanying the second call for bids contained an incentive clause, *427 not present in the original specifications, whereby the State agreed to pay the construction company a bonus of $300,000 if the work were completed prior to September 1, 1981. Under this new call for bids, Kiewit was again the low bidder. Kiewit has since been awarded the new contract and is proceeding with the project.

On this appeal the State argues that summary judgment allowing rescission of the bid was inappropriate because there were genuine issues of material fact as to whether the errors in the bid justified equitable relief. The State also contends that even if the facts did warrant rescission of Kiewit's bid, they did not justify an injunction preventing the forfeiture of the bid bond. Kiewit takes issue with these contentions and further urges that the State is precluded from challenging the summary judgment because it entered into a stipulation at the trial that there were no genuine issues of material fact. Kiewit has also moved to dismiss this appeal on the grounds of waiver and estoppel.

We turn first to Kiewit's motion to dismiss this appeal. Kiewit contends that the State has waived, or is estopped, from appealing the summary judgment because Kiewit has subsequently been awarded a contract for the same work under a new call for bids. Specifically, Kiewit argues that at the time summary judgment was granted by the trial court the State was required to choose between (1) awarding the contract to the second lowest bidder and seeking forfeiture of the bid bond and other damages on appeal, or (2) foregoing appeal and readvertising for bids.

We find this argument to be unfounded. Washington cases recognize that performance of a contract, by a party having the right to rescind, constitutes a waiver of that right. Red-Samm Mining Co. v. Port of Seattle, 8 Wn. App. 610, 508 P.2d 175 (1973); J.J. Welcome & Sons Constr. Co. v. State, 6 Wn. App. 985, 497 P.2d 953 (1972). These cases might be applicable by analogy if the State were presently attempting to obtain a reversal of the trial court's decision in order to compel Kiewit to perform the original contract at the price of the first bid. However, that *428 is not the purpose of this appeal. The State is merely attempting to avail itself of its statutory remedy (i.e., forfeiture of the bid bond) for Kiewit's breach of the original contract. The right to pursue this remedy is not dependent on whether the State awards the original contract to the second lowest bidder or readvertises for new bids. The right to reject all remaining bids and readvertise is expressly sanctioned by the same statute which provides for forfeiture of the bid bond where the successful bidder fails to honor its bid. RCW 47.28.100. Moreover, the basic purpose of bid bonds is to afford protection against a change in status involving substantial damages, loss or detriment by the party soliciting bids. Puget Sound Painters, Inc. v. State, 45 Wn.2d 819, 278 P.2d 302 (1954). In the instant case, Kiewit's failure to honor its bid occasioned substantial time delay and resulted in the State having to supplement the specifications accompanying the second call for bids with the $300,000 incentive clause. Therefore the State suffered a detrimental change in status despite the fact that it eventually entered into a new contract with Kiewit pursuant to the readvertisement.

Having concluded that Kiewit's motion to dismiss must be denied, we turn now to the merits of the appeal.

The first issue we must consider is whether the State's affirmative response to the trial court's question, "Do you both agree that this, as a practical matter, ought to be decided now?", constituted a stipulation that there were no genuine issues of material fact. We conclude that it did not. To be effective, the terms of a stipulation must be definite and certain. 73 Am. Jur. 2d Stipulations § 2 (1974). Here, the court's inquiry did not clearly and definitely ask if the State agreed or conceded that there were no factual issues.

The remaining question is whether the errors in Kiewit's bid were the type of mistakes which are recognized as warranting equitable relief. The existence of any issue of material fact in this regard would conclusively establish that the trial court's order granting summary judgment was inap *429 propriate. Morris v. McNicol,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gill v. Waggoner
828 P.2d 55 (Court of Appeals of Washington, 1992)
Broberg v. Boling
331 P.2d 570 (Supreme Court of Kansas, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
635 P.2d 740, 30 Wash. App. 424, 1981 Wash. App. LEXIS 2785, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peter-kiewit-sons-co-v-department-of-transportation-washctapp-1981.