Town of Hull v. Massachusetts Port Authority

806 N.E.2d 901, 441 Mass. 508, 2004 Mass. LEXIS 216
CourtMassachusetts Supreme Judicial Court
DecidedApril 21, 2004
StatusPublished
Cited by8 cases

This text of 806 N.E.2d 901 (Town of Hull v. Massachusetts Port Authority) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Hull v. Massachusetts Port Authority, 806 N.E.2d 901, 441 Mass. 508, 2004 Mass. LEXIS 216 (Mass. 2004).

Opinion

Ireland, J.

This case requires us to interpret, for the first time, the provision set forth in G. L. c. 30, § 62H, fourth par., that creates an exception to the time limit for challenges to environmental impact reports if the project proponent has “knowingly concealed a material fact or knowingly submitted false information.” The town of Hull (town) commenced an action seeking, inter alla, a judgment declaring that the Massachusetts Port Authority (Massport) failed to comply with the Massachusetts Environmental Policy Act, G. L. c. 30, §§ 61-62H (MEPA), in its environmental impact report (EIR) concerning its Logan airside improvements planning project (airport project), and seeking an order that “Massport’s negligent operation of Logan International Airport constitutes a public nuisance.”2 The action was not commenced within the applicable time limits, and the town invoked G. L. c. 30, § 62H, fourth par., to overcome that time bar. A Superior Court judge granted Massport’s motion for summary judgment and denied the town’s motion for partial summary judgment.3 The town appealed. We granted Massport’s application for direct appellate review.

On appeal, the town argues that the judge erred in granting summary judgment in favor of Massport, because he decided issues of fact in considering the town’s claim that Massport knowingly concealed material facts or submitted false information (G. L. c. 30, § 62H, fourth par.) in its EIR. The town also asserts that the judge erred, as a matter of law, in determining that the town could not bring a nuisance claim against Massport. Because we conclude that, in the circumstances of this case, (1) the concealment or false information provision set forth in G. L. c. 30, § 62H, fourth par., does not apply; and (2) the town may not bring a nuisance claim against Massport, because the Legislature has sanctioned the activity, we affirm the judgment of the Superior Court.

Facts and procedural background. We recite the facts with all inferences drawn in favor of the town, as the nonmoving [510]*510party, Coveney v. President & Trustees of the College of the Holy Cross, 388 Mass. 16, 17 (1983), reserving certain details for our discussion. “An order granting summary judgment will be upheld if the judge ruled on undisputed material facts and his rulings were correct as a matter of law.” Garweth Corp. v. Boston Edison Co., 415 Mass. 303, 304 (1993), and cases cited.

On July 31, 1995, in keeping with the requirements of Federal and State law, Massport filed an environmental notification form (ENF) with the Secretary of the Executive Office of Environmental Affairs (Secretary) that set forth the airport project, which was its plan to deal with airport delay at Logan International Airport (Logan).4 The airport project proposal included the construction of a new runway (runway 14-32), taxiway improvements, and as suggested by the Federal Aviation Administration (FAA), a reduction in the runway approach minimum altitude requirements for aircraft.5

On November 22, 1995, the Secretary issued a certificate on the ENF pursuant to § 62A of MEPA, determining that the airport project required an EIR and describing the issues to be addressed therein. The Secretary determined that Massport had to evaluate each alternative set forth in the ENF to compare, in part, the impact of the airport project on air quality and noise.

Massport filed its draft environmental impact report (DEIR) in February, 1999. In the DEIR, four alternatives were analyzed: [511]*511(1) runway 14-32, taxiway improvements, reduced approach minimum altitudes for certain runways, and peak period pricing6 ; (2) all actions contained in the first alternative except runway 14-32; (3) only reduced approach minimum altitudes for certain runways, and peak period pricing; and (4) no action. In its DEIR, Massport identified a modified version of the first alternative (i.e., all action except peak period pricing) as its “preferred” alternative.

On May 7, 1999, the Secretary issued a certificate on the DEIR, determining that it complied with MEPA and MEPA regulations (301 Code of Mass. Regs. §§ 11.00 [1998]). However, the Secretary also required Massport to address a number of issues in its final EIR (FEIR). Public notice of Mass-port’s FEIR was made on May 9, 2001. The FEIR stated that using the preferred alternative would result in a reduction in noise exposure and improved air quality.

On June 6, 2001, the town submitted to the Secretary a report entitled “Errors and Omissions, Massport’s flawed SDEIS/ FEIR”7, 8 (town’s report) in response to the FEIR. On June 15, 2001, after staff review of the town’s report and other extensive public comment, the Secretary issued a certificate on the FEIR, which stated that it complied with MEPA and the relevant regulations.9 The Secretary noted that the airport project generated “an enormous volume of public comments” and that members of his staff met with town officials, among others. [512]*512Subsequently, Massport adopted findings relative to the airport project, pursuant to § 61 of MEPA.10

Under § 62H of MEPA, a party has 120 days from the time it has notice of availability of the FEIR (in this case, May 9, 2001) to commence an action alleging that the FEIR failed to comply with §§ 62-62G of MEPA. However, § 62H, fourth par., contains what we shall refer to as the “concealment” exception, which states that if “an agency or person proposing a project has knowingly concealed a material fact or knowingly submitted false information,” the time limitation does not apply.

The October 15, 2001, action the town filed was past the statutory deadline. In the complaint, the town requested a declaratory judgment (G. L. c. 231 A) to determine the parties’ rights, duty, status, and legal relations pursuant to § 61 of MEPA. The town utilized the concealment exception in § 62H, fourth par., alleging that Massport failed to disclose material facts and knowingly submitted false, misleading, and deceptive information in its ENF, DEIR, FEIR, and findings, thus allowing Massport to avoid its obligations to provide soundproofing to many homes and businesses, including Hull High School, and to “minimize damage to the environment” under § 61 of MEPA.

Although the judge denied Massport’s motion to dismiss the allegations in the town’s complaint on the ground that it failed to meet the statutory deadline pursuant to G. L. c. 30, § 62H (noting that the town had shown enough to allow it to invoke the concealment exception, because the town had alleged fraud with sufficient particularity pursuant to Mass. R. Civ. P. 9 [b], 365 Mass. 751 [1974]), he later granted Massport’s motion for summary judgment, the subject of this appeal.

[513]*513 Discussion.

1. MEPA.

a. General statutory scheme. In interpreting the concealment exception contained in § 62H, fourth par., of MEPA, we first consider the concealment exception in the context of MEPA’s legislative purpose and administrative scheme, discussed in Enos v. Secretary of Envtl. Affairs, 432 Mass. 132, 136-142 (2000). See Sierra Club v. Commissioner of the Dep’t of Envtl. Mgt., 439 Mass. 738 (2003); Cummings v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rossano v. Massachusetts Port Authority
2012 Mass. App. Div. 69 (Mass. Dist. Ct., App. Div., 2012)
Town of Canton v. Commissioner of Massachusetts Highway Department
919 N.E.2d 1278 (Massachusetts Supreme Judicial Court, 2010)
Town of Canton v. Paiewonsky
25 Mass. L. Rptr. 378 (Massachusetts Superior Court, 2008)
Evans v. Lorillard Tobacco Co.
22 Mass. L. Rptr. 91 (Massachusetts Superior Court, 2007)
Saxonis v. City of Lynn
817 N.E.2d 793 (Massachusetts Appeals Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
806 N.E.2d 901, 441 Mass. 508, 2004 Mass. LEXIS 216, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-hull-v-massachusetts-port-authority-mass-2004.