Town of Hopedale v. Alderman & MacNeish, Inc.

13 Mass. L. Rptr. 91
CourtMassachusetts Superior Court
DecidedMarch 12, 2001
DocketNo. 990099
StatusPublished

This text of 13 Mass. L. Rptr. 91 (Town of Hopedale v. Alderman & MacNeish, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Hopedale v. Alderman & MacNeish, Inc., 13 Mass. L. Rptr. 91 (Mass. Ct. App. 2001).

Opinion

Fecteau, J.

This matter is before the court on defendant’s, Alderman & MacNeish, Inc., motion for summary judgment seeking dismissal of plaintiff, Town of Hopedale’s, complaint. The present action arises from a Contract for Architect Services between the parties under which the defendant was to provide architectural services related to renovations and construction of an addition to the Memorial Elementary School in the Town of Hopedale. As a result of the perceived failings of the defendant’s performance, plaintiff brought the present action on January 15, 1999 alleging in its complaint claims lying in both negligence and breach of contract. Defendant, in its present motion, contends that all of the plaintiffs claims lie in tort, rather than contract and negligence, and are barred as a matter of law by the applicable three-year statute of limitations as stated in G.L.c. 260, Sec. 2B. The plaintiff, however, asserts that, since the defendant made express warranties as to its performance under the contract between the parties, it may bring a breach of contract claim and that the six-year statute of limitations of G.L.c. 260, Sec. 2 applies to said claim. Alternatively, plaintiff contends that even if the three-year statute of limitations of G.L.c. 260, Sec. 2B is found to apply to all of its claims, there are still disputed material facts as to whether the plaintiffs complaint was filed within the applicable three years. The court heard the parties in argument on January 22, 2001.1 For the following reasons the defendant’s motion for summary judgment is DENIED.

FACTUAL BACKGROUND

On January 20, 1994, the plaintiff and the defendant entered into a contract for architectural services related to renovations and construction of an addition to the Memorial Elementary School in Hopedale (“the project”). Congress Construction Company, Inc. (“Congress”) was the general contractor on the project. The contract for architectural services entered into by the parties contained the following provisions as to the defendant’s performance:

1)The Architect shall be responsible for the professional and technical accuracy and the coordination of all designs, drawings, specifications, estimates and other work furnished by him or his consultants and subcontractors. The Architect shall staff his offices with sufficient personnel to complete the services required under this contract in a prompt and continuous manner, and shall meet the approval schedule and submittal dates established during the course of this AGREEMENT.

Article 5, section 5.1.

2) Upon the award of the construction contract the Architect and his consultants shall, for the purposes of protecting the Awarding Authority against defects and efficiencies in the work of the Project: (1) be charged with general administration of the construction contract; (2) furnish the General Contractor with information to assist in establishing lines and grades and such large scale drawings and full sized detailed drawings as maybe required; (3) promptly check and approve, schedules, shop drawings and other submissions by the General Contractor; (4) visit the site of the Project; (5) conduct semi-final and final inspections of the construction project and report the results of such inspections in writing to the Awar ding Authority; (6) report to the Awarding Authority weekly in writing on the progress of construction; (7) recommend condemnation of all project work observed by the Architect which fails to conform to the Contract Documents; (8) decide all questions regarding interpretation of or compliance with the Contract Documents; (8) decide all questions regarding interpretation of or compliance with the Contract Documents; (9) review and act on all request for change in plans, specifications, or contracts for the Project; and (10) furnish working plans and specifications for any such change.
The Architect shall be familiar with the provisions of the General Laws for payment to contractors and shall submit to the Awarding Authority all requisitions for payment submitted by the general contractor. With respect to each such requisition, he or she shall certify to the best of the Architect's knowledge that the percentage of work included in the requisition is accurate and the work performed conforms with the contract documents . . . Timely payments of general contractors is required by General Laws Chapter 30, section 39K; therefore, the Architect shall establish office procedures assuring either immediate mail or messenger delivery of the requisition for payment to the Awarding Authority, and shall process requisition for payment within forty-eight hours of receipt.

Article 6, sec 6.1, para 5.

3)... The Architect shall indemnify and save harmless the Awarding Authority, and all municipal boards, commissions, departments or officers against suits, claims of liability for or on account of any injuries to persons or damage to property to the extent that the same are the result of the negligence of the Architect in the performance of work covered by this AGREEMENT and/or failure to comply with the terms and conditions of this AGREEMENT, whether by himself or his employees, consultants or subcontractors.

[93]*93Article 15, sec. 15.5.

4) The project scope shall consist of the following: ... All Architectural-Engineering Services to produce construction and bid documents, bidding and construction inspection services as required to meet the requirements of the Massachusetts Board of Education, and all other applicable laws, codes, and ordinances.

Attachment A, para D.

The construction contract between the plaintiff and Congress, to which the defendant was not a party, but in which some of its duties were discussed, contained both the standard form of General Conditions and two forms of supplementary conditions. The General Conditions to the construction contract documented that “(a]s to acts or failures to act occurring prior to the relevant date of Substantial Completion, any applicable statute of limitations shall commence to run and any alleged cause of action shall be deemed to have accrued in any and all events not later than such date of Substantial Completion.” The construction contract also called for the completion of the project in time for the beginning of the 1995 school year, but said completion was delayed and alternative facilities had to be used for the first 2 months of the school year.

The plaintiff alleges that the defendant was responsible for the delay in completion of the project. In particular, the plaintiff alleges that the defendant failed to properly identify a wetland resource on the property at the beginning of the project, and failed to obtain an Order of Conditions. The Department of Environmental Protection raised the wetland issue in November of 1994, while construction was proceeding, and required a change in the building plans which caused delay and resulted in a change order of $ 101,459.00 for extra work. The plaintiff has acknowledged that it knew on or before November 22, 1994 that the defendant had failed to properly identify an existing wetland resource and that it began to incur expenses as result of the defendant’s failure to properly identify said wetland resource by December 28, 1994.

In addition to the wetland issue, plaintiff has alleged several design defects which allegedly resulted in substantial cost overruns and related expenses.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Hendrickson v. Sears
310 N.E.2d 131 (Massachusetts Supreme Judicial Court, 1974)
Pederson v. Time, Inc.
532 N.E.2d 1211 (Massachusetts Supreme Judicial Court, 1989)
Bowen v. Eli Lilly & Co.
557 N.E.2d 739 (Massachusetts Supreme Judicial Court, 1990)
Friedman v. Jablonski
358 N.E.2d 994 (Massachusetts Supreme Judicial Court, 1976)
Town of Mansfield v. GAF Corp.
364 N.E.2d 1292 (Massachusetts Appeals Court, 1977)
Community National Bank v. Dawes
340 N.E.2d 877 (Massachusetts Supreme Judicial Court, 1976)
Riley v. Presnell
565 N.E.2d 780 (Massachusetts Supreme Judicial Court, 1991)
Anthony's Pier Four, Inc. v. Crandall Dry Dock Engineers, Inc.
489 N.E.2d 172 (Massachusetts Supreme Judicial Court, 1986)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Flesner v. Technical Communications Corp.
575 N.E.2d 1107 (Massachusetts Supreme Judicial Court, 1991)
Cassesso v. Commissioner of Correction
456 N.E.2d 1123 (Massachusetts Supreme Judicial Court, 1983)
Klein v. Catalano
437 N.E.2d 514 (Massachusetts Supreme Judicial Court, 1982)
Franklin v. Albert
411 N.E.2d 458 (Massachusetts Supreme Judicial Court, 1980)
Starr v. Fordham
648 N.E.2d 1261 (Massachusetts Supreme Judicial Court, 1995)
Somerset Savings Bank v. Chicago Title Insurance
649 N.E.2d 1123 (Massachusetts Supreme Judicial Court, 1995)
Citation Insurance v. Gomez
426 Mass. 379 (Massachusetts Supreme Judicial Court, 1998)
Coca-Cola Bottling Co. v. Weston & Sampson Engineers, Inc.
695 N.E.2d 688 (Massachusetts Appeals Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
13 Mass. L. Rptr. 91, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-hopedale-v-alderman-macneish-inc-masssuperct-2001.