Town of Grand Chute v. U.S. Paper Converters, Inc.

600 N.W.2d 33, 229 Wis. 2d 674, 1999 Wisc. App. LEXIS 844
CourtCourt of Appeals of Wisconsin
DecidedJuly 30, 1999
Docket98-2797
StatusPublished
Cited by3 cases

This text of 600 N.W.2d 33 (Town of Grand Chute v. U.S. Paper Converters, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Grand Chute v. U.S. Paper Converters, Inc., 600 N.W.2d 33, 229 Wis. 2d 674, 1999 Wisc. App. LEXIS 844 (Wis. Ct. App. 1999).

Opinion

MYSE, P.J.

The Town of Grand Chute (Town) appeals a judgment dismissing its zoning enforcement suit against U.S. Paper Converters, Inc., and R & D Controls, Inc. (collectively USPC). The suit alleged that USPC violated the Town's conditional site plan approval by maintaining a private road contrary to the Town's requirement that the road be removed upon completion of a public road on USPC's property. The Town contends that the trial court erred when it concluded that the Town lacked authority to enforce its conditional approval because it was required but failed to show USPC's noncompliance with an announced rule, standard or requirement forming the basis for the Town's action. The Town further contends that USPC waived its claim that the Town lacked authority because USPC failed to give notice pursuant to § 893.80, STATS., failed to exhaust administrative remedies, and failed to initiate certiorari review. USPC cross-appeals, contending that the Town lacks statutory authority to require site plan approval as a condition precedent to issuing a building permit for a use permitted in the industrial district as a matter of right.

We conclude that the Town possessed legal authority to conditionally approve USPC's site plan and that the Town's site plan ordinance identifying access and traffic flow as a factor of site plan review is a sufficiently specific basis for the planning commission's determination. Accordingly, we reverse the judgment and remand wdth directions to grant the Town's injunc *678 tion. Because our conclusion is dispositive, we need not address the Town's other claims of error. Sweet v. Berge, 113 Wis. 2d 61, 67, 334 N.W.2d 559, 562 (Ct. App. 1983) (only dispositive issues need be addressed). Because we conclude that the Town is authorized to establish the right of approval for industrial site development within its boundaries, USPC's cross-appeal fails.

Background

USPC owns property located in an industrial district in the Town of Grand Chute on which it was constructing a paper converting plant. Because the plant's anticipated size exceeded 30,000 square feet, the Town's ordinances required USPC to submit a site • plan for the Town's planning commission's approval. USPC's general contractor applied to the Town for a building permit and submitted a site plan showing a roadway along the property's northern property line from the plant to Casaloma Drive. USPC built this roadway to Town road specifications, anticipating its dedication as a public road. The Town granted USPC a culvert permit for access from the northern property line roadway. The USPC property also includes a public road along its southern border accessing Casaloma Drive, which had not been completed at the time USPC began construction.

USPC's general contractor began construction on the plant and on the northern roadway before obtaining either a building permit from the building inspector or site plan approval from the planning commission. The contractor excavated and graded the roadway. When Town officials discovered work had been done prior to site plan approval, the building inspector issued a "stop work order." The next day, *679 USPC's site plan came before the Town's planning commission for approval. Commission members objected to the construction's commencement before site plan approval and to the northern roadway's entrance onto Casaloma Drive, in view of the present level of traffic congestion and its locatiori directly opposite a residence.

Rather than approving the site plan, the commission referred the matter to the Town attorney, who drafted an agreement providing that: (1) the contractor would cease work involving construction of a public roadway other than the private road; and (2) the Town chairman did not object to the construction of the private roadway for USPC's exclusive use as long as it is not considered a public roadway. Although the contractor and the Town chairman signed the agreement, it was not brought before the commission.

The planning commission eventually voted to approve the USPC site plan on condition that: (1) the private road be removed as soon as the Department of Transportation installed the public road; and (2) a landscape and lighting plan be submitted to the commission for approval. After the southern public road was completed, USPC did not remove the private road, claiming that its trucks could not negotiate the southern public road's steep grade in winter months. The Town Board passed a resolution directing that the private road be removed in thirty days.

When USPC continued to use the private road, the Town brought a zoning enforcement action against USPC seeking a declaration that USPC unlawfully maintained a private road built to handle semi-truck traffic in violation of the Town's planning commission's conditional site plan approval. The Town's enforcement action also sought injunctive relief ordering *680 USPC to discontinue utilizing the road and to remove it at USPC's expense.

The action first proceeded to trial only on the declaratory judgment portion of the case. The trial court concluded that pursuant to §§ 61.34 and 62.23(4), Stats., the Town had ¿authority to require site plan approval, that the Town's eventual approval was conditioned on the private road's removal as soon as the public road was available, that the condition was ripe requiring the road's removal, and that USPC's continued use of the private road violated the approval granted.

At the trial on the injunction request, USPC offered legal authority that it argued cast in doubt the Town's authority to enforce its initial denial of site plan approval, absent a showing of noncompliance with a stated rule or regulation. After the parties briefed the issue, the court reversed its declaratory judgment that the private road violated the conditional site approval. The trial court concluded that the Town was required to show, but could not establish, noncompliance with an announced or stated rule, standard or requirement as a basis for non-approval of the site plan. After denying the Town's motion to reconsider, the court entered judgment. The Town appealed and USPC filed its cross-appeal.

Analysis

Whether the Town lacked authority to seek enforcement of its conditional site plan approval requires the interpretation of applicable statutes and town ordinances. The construction and application of ordinances and statutes to a particular set of facts present questions of law we review de novo. Eastman v. *681 City of Madison, 117 Wis. 2d 106, 112, 342 N.W.2d 764, 767 (Ct. App. 1983); Grosse v. Protective Life Ins. Co., 182 Wis. 2d 97, 105, 513 N.W.2d 592, 596 (1994).

We first consider the Town's authority to adopt ordinances authorizing the Town's planning commission to review and approve site plans as a condition precedent to issuing a building permit. Section 61.34(1), Stats., grants broad home rule authority to towns which have adopted village powers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
600 N.W.2d 33, 229 Wis. 2d 674, 1999 Wisc. App. LEXIS 844, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-grand-chute-v-us-paper-converters-inc-wisctapp-1999.