Town of Grand Chute v. Outagamie County

2004 WI App 35, 676 N.W.2d 540, 269 Wis. 2d 657, 2004 Wisc. App. LEXIS 8
CourtCourt of Appeals of Wisconsin
DecidedJanuary 13, 2004
Docket03-1897-FT
StatusPublished
Cited by7 cases

This text of 2004 WI App 35 (Town of Grand Chute v. Outagamie County) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Grand Chute v. Outagamie County, 2004 WI App 35, 676 N.W.2d 540, 269 Wis. 2d 657, 2004 Wisc. App. LEXIS 8 (Wis. Ct. App. 2004).

Opinion

HOOVER, PJ.

¶ 1. Outagamie County appeals a declaratory judgment determining it is liable for one-half the costs of repairing a bridge in the Town of Grand Chute. 1 The County argues the court erred when it determined "cost" and "cost of construction or repair" are synonymous under Wis. Stat. § 81.38(2). The County also argues that it is only liable for its half of the amount the Town states in its initial petition for aid, not any amount incurred after the petition is approved. We reject the County's arguments and affirm the judgment.

Background

¶ 2. Wisconsin Stat. § 81.38 is entitled "Town bridges or culverts; construction and repair; county aid." After a town votes to construct or repair a bridge and has raised its portion of the cost, it can file a bridge *660 aid petition with the county, seeking funding assistance. Wis. Stat. § 81.38(1). The statute essentially obligates the county to pay for one-half the cost of constructing or repairing the town's bridge. Wis. Stat. § 81.38(2). 2

¶ 3. The County and the Town stipulated to the facts. Outagamie County and the Town of Grand Chute both participate in this cost-sharing scheme. The Town submitted three bridge aid petitions, which the County denied. The particular dispute in this case arises because Wis. Stat. § 81.38(2) refers to both "cost" and "cost of construction or repair."

¶ 4. Thus, the County believes that when the statute says the County shall pay half the "cost of construction or repair," the phrase is more restrictive than simply "cost" and therefore some items are not taxable to the County's half of the bill. Specifically, the County has declined to pay for engineering, DNR permit, and easement acquisition costs in this case, even though it has historically paid for these items.

¶ 5. The Town brought this action for declaratory judgment, seeking a declaration of what costs ought to be included in the cost-sharing. The Town also sought a declaration regarding the rights and responsibilities of the parties relating to allowing bidding on the construction projects. Although not listed in the complaint, an issue arose regarding whether the petition for aid had to be submitted on the County's form or whether the Town could draft its own petition. The County counterclaimed, seeking a declaration that permissible costs under the statute must be itemized in the petition and that unidentified costs may be denied by the County.

*661 ¶ 6. The trial court concluded the County was responsible for its share of the construction or repair cost as set forth in Wis. Stat. § 81.38. The court concluded that the disputed items in this case were "costs" as well as "costs of construction" for which the County had to pay one-half. It concluded that the Town could use its own aid petition and that that the Town could seek bids on the bridge projects. 3 The court made no explicit ruling regarding whether the Town needed to identify or itemize its costs, although this does not preempt our review in this case. Outagamie County appeals.

Discussion

¶ 7. The grant or denial of a declaratory judgment is left to the circuit court's discretion. Jones v. Secura Ins. Co., 2002 WI 11, ¶ 19, 249 Wis. 2d 623, 638 N.W.2d 575. However, when the exercise of discretion is based on a question of law, we review the question de novo benefiting from the circuit court's analysis. Id. When facts are stipulated, all that remains is a question of law. Lewis v. Physicians Ins. Co., 2001 WI 60, ¶ 9, 243 Wis. 2d 648, 627 N.W.2d 484. Statutory interpretation is also a question of law. Jungbluth v. Hometown, Inc., 201 Wis. 2d 320, 327, 548 N.W.2d 519 (1996). 4 The goal of statutory interpretation is to discern legislative intent. See County of Jefferson v. Renz, 231 Wis. 2d 293, 301, *662 603 N.W.2d 541 (1999). If the meaning of the statute is clear, we do not look beyond its language. Jungbluth, 201 Wis. 2d at 327.

Cost v. Cost of Construction or Repair

¶ 8. Wisconsin Stat. § 81.38(2) states:

The county shall pay the cost in excess of $750 up to $1,500. The town and county shall each pay one-half of the cost of construction or repair above $1,500. In determining the cost of construction or repair of any culvert or bridge, the cost of constructing or repairing any approach not exceeding 100 feet in length shall be included. (Emphasis added.)

¶ 9. The County argues that because "cost" is used in the first part of the statute and "cost of construction or repair" is used in the second part, this construction necessarily means that some costs are excluded from the County's half of the bridge total. In other words, "cost" may be all encompassing, but "cost of construction or repair" is specific and limited and does not include items such as engineering design fees, permit fees, or easement acquisition costs.

¶ 10. The trial court concluded that engineering, permit, and easement costs "are required for the construction. They are not discretionary expenses and the court not only finds them to be 'costs', but finds them to be 'costs of construction.'"

¶ 11. We agree with the trial court that engineering, permit, and easement costs are required for construction. Indeed, the parties stipulated that "Engineer *663 ing design services are . .. required for the general bridge reconstruction specifications" and the DNR "now requires hydraulic engineering studies as a condition for approving bridge construction ...Moreover, we know of no reason why a town would incur unnecessary costs. Whatever the costs, a town is responsible for half of them. It has no incentive to raise the project costs with unnecessary expenses.

¶ 12. Because the statute's main focus is construction or repair of bridges, it is evident to us that "cost," in the context of the entire statutory scheme, is merely shorthand for "cost of construction or repair." Use of the word "cost" is not intended to somehow limit "cost of construction or repair."

Whether the Town Must List All Costs In and Be Bound By Its Petition

¶ 13. The County argues that all project costs must be listed with specificity in the bridge aid petition.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McFarland State Bank v. Sherry
2012 WI App 4 (Court of Appeals of Wisconsin, 2011)
Town of Madison v. County of Dane
2008 WI 83 (Wisconsin Supreme Court, 2008)
Town of Madison v. County of Dane
2007 WI App 177 (Court of Appeals of Wisconsin, 2007)
Lenticular Europe, LLC v. Cunnally
2005 WI App 33 (Court of Appeals of Wisconsin, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
2004 WI App 35, 676 N.W.2d 540, 269 Wis. 2d 657, 2004 Wisc. App. LEXIS 8, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-grand-chute-v-outagamie-county-wisctapp-2004.