Town Lake Joint Venture, Ron Mullen and Joseph E. Thompson v. Lumbermen's Investment Corporation

CourtCourt of Appeals of Texas
DecidedJune 30, 1993
Docket03-91-00563-CV
StatusPublished

This text of Town Lake Joint Venture, Ron Mullen and Joseph E. Thompson v. Lumbermen's Investment Corporation (Town Lake Joint Venture, Ron Mullen and Joseph E. Thompson v. Lumbermen's Investment Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town Lake Joint Venture, Ron Mullen and Joseph E. Thompson v. Lumbermen's Investment Corporation, (Tex. Ct. App. 1993).

Opinion

TOWN LAKE V LIC
IN THE COURT OF APPEALS, THIRD DISTRICT OF TEXAS,


AT AUSTIN




NO. 3-91-563-CV


TOWN LAKE JOINT VENTURE, RON MULLEN AND JOSEPH E. THOMPSON,


APPELLANTS



vs.


LUMBERMEN'S INVESTMENT CORPORATION,


APPELLEE





FROM THE DISTRICT COURT OF TRAVIS COUNTY, 331ST JUDICIAL DISTRICT


NO. 405,692, HONORABLE PAUL R. DAVIS, JR., JUDGE PRESIDING




Appellant Town Lake Joint Venture ("Town Lake") filed suit against appellee Lumbermen's Investment Corporation ("LIC"), alleging breach of contract and numerous other claims. LIC then filed a claim against appellants Ron Mullen, Joseph E. Thompson, and Town Lake to recover the deficiency on two promissory notes. The trial court directed a verdict in favor of LIC on its claims against appellants and offset the resulting damages with the damages the jury awarded Town Lake on its claims of negligent misrepresentation and promissory estoppel. Town Lake, Mullen, and Thompson appeal this judgment, asserting six points of error. We will affirm.



FACTS

Town Lake, a joint venture involving Robert Keener, Neal Block, Mullen, and Thompson, borrowed $4 million from Anchor Savings in March 1984 in order to purchase a plot of land in downtown Austin. Keener, Block, and Thompson signed the promissory note acknowledging this debt to Anchor. The land and a $1 million certificate of deposit were collateral for the loan. Town Lake and LIC began discussing the possibility of forming a joint venture to construct and lease an office building on the land. In July 1984, LIC loaned Town Lake $4.6 million to refinance the Anchor loan. The new loan contained similar terms as the Anchor loan; the land and certificate of deposit were designated as collateral. In September 1984, LIC loaned Town Lake an additional $100,000 to cover architectural fees. The parties produced a draft of a contract detailing the planned joint venture in early October. However, on December 11, 1984, LIC informed Town Lake that it no longer wished to enter into the venture.

Town Lake defaulted on both notes it owed LIC. On November 4, 1985, the parties signed an agreement. Town Lake stipulated that the amount due on the two original notes was $4,586,811.21. (1) In return, LIC agreed not to foreclose upon the land until January 5, 1986. It had foreclosed upon the certificate of deposit on August 5, 1985, but loaned Town Lake $78,000 from these funds; this loan was due January 5th. LIC also agreed to release Keener and Block from any liability upon two conditions: that they convey their interest in Town Lake to Thompson or Mullen, and that they release all claims against LIC by signing a form satisfactory to LIC. LIC never released Keener or Block and foreclosed upon the land owned by Town Lake on December 2, 1986.

Town Lake filed suit, claiming LIC had (1) negligently misrepresented its intentions about forming a joint venture with Town Lake; (2) broken its promise to form a joint venture, and Town Lake had relied on this promise to its detriment; (3) breached an enforceable contract to form a joint venture and to construct the office building; (4) committed deceptive trade practices; and (5) broken its promise in the November 4, 1985, agreement to release Keener and Block. LIC's claims in this case involve the deficiency for the amount due on the three notes for $4.6 million, $100,000, and $78,000 after foreclosure upon the certificate of deposit and the land. The trial court submitted questions to the jury on Town Lake's negligent misrepresentation and promissory estoppel claims, refused to submit questions to the jury on Town Lake's claims regarding deceptive trade practices and breach of the November 4th agreement, and directed a verdict against Town Lake's claim that LIC had breached an agreement to form a joint venture. The court also directed a verdict in favor of LIC on its claims for the deficiency on the notes and refused to submit Town Lake's proffered jury questions on its affirmative defense that LIC had fraudulently induced Town Lake to sign the notes. The jury found in favor of Town Lake on the submitted questions and awarded $235,000 in damages. The court offset this amount against the damages it found LIC should recover for its claims and rendered judgment accordingly.



THE NOVEMBER 4, 1985, AGREEMENT

Appellants' first point of error asserts that the trial court erred when it failed to ask the jury whether LIC had breached the November 4th agreement by not releasing Keener and Block from liability. The court's action was proper if no evidence supported the requested jury question. Kindred v. Con/Chem., Inc., 650 S.W.2d 61, 63 (Tex. 1983).

LIC contends that it did not breach the agreement as a matter of law because Town Lake presented no evidence that the conditions precedent for LIC's promise to release Keener and Block from liability ever occurred. Appellants first raise a procedural argument that this Court cannot consider such a contention in support of the trial court's judgment because LIC failed to plead specifically which conditions precedent did not occur.

Town Lake's petition generally alleged that all conditions precedent had been performed. This pleading was procedurally sufficient. Tex. R. Civ. P. 54. LIC's answer denied that all such conditions precedent had been performed without specifically identifying any single condition. This lack of specificity would prevent LIC from complaining on appeal about Town Lake's failure to prove the performance of conditions precedent if Town Lake had recovered on its claim at trial. Id.; Sunbelt Constr. Corp. v. S & D Mechanical Contractors, Inc., 668 S.W.2d 415, 417-18 (Tex. App.--Corpus Christi 1983, writ ref'd n.r.e.); Dealers Nat'l Ins. Co. v. Simmons, 421 S.W.2d 669, 674 (Tex. Civ. App.--Houston [14th Dist.] 1967, writ ref'd n.r.e.). A plaintiff's compliance with Rule 54, however, merely shifts the burden of pleading to the defendant, not the burden of proof at trial. Trevino v. Allstate Ins. Co., 651 S.W.2d 8, 11 (Tex. App.--Dallas 1983, writ ref'd n.r.e.). Because appellants did not prevail at trial, the relevant issue is their complaint about the trial court's failure to submit Town Lake's requested jury question. We conclude that LIC's general denial that all conditions precedent had been performed was procedurally sufficient to support the trial court's action. We therefore review the merits of LIC's assertion that Town Lake presented no evidence of the occurrence of conditions precedent to LIC's promise to release Keener and Block from liability.

Appellants presented evidence that Keener and Block had signed documents transferring their interests in Town Lake to the other venturers and releasing LIC from liability.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kindred v. Con/Chem, Inc.
650 S.W.2d 61 (Texas Supreme Court, 1983)
Matthews v. General Accident Fire & Life Assurance Corp.
343 S.W.2d 251 (Texas Supreme Court, 1961)
Dealers National Insurance Company v. Simmons
421 S.W.2d 669 (Court of Appeals of Texas, 1967)
Collora v. Navarro
574 S.W.2d 65 (Texas Supreme Court, 1978)
Magcobar N. Amer v. Grasso Oilfield S.
736 S.W.2d 787 (Court of Appeals of Texas, 1987)
Riverside National Bank v. Lewis
603 S.W.2d 169 (Texas Supreme Court, 1980)
Wilgus v. Bond
730 S.W.2d 670 (Texas Supreme Court, 1987)
Hirsch v. Hirsch
770 S.W.2d 924 (Court of Appeals of Texas, 1989)
Melody Home Manufacturing Co. v. Barnes
741 S.W.2d 349 (Texas Supreme Court, 1987)
Black Lake Pipe Line Co. v. Union Construction Co.
538 S.W.2d 80 (Texas Supreme Court, 1976)
Trevino v. Allstate Insurance Co.
651 S.W.2d 8 (Court of Appeals of Texas, 1983)
" MOORE" BURGER, INC. v. Phillips Petroleum Company
492 S.W.2d 934 (Texas Supreme Court, 1972)
Adams v. Petrade International, Inc.
754 S.W.2d 696 (Court of Appeals of Texas, 1988)
Flenniken v. Longview Bank and Trust Co.
661 S.W.2d 705 (Texas Supreme Court, 1983)
Allstate Insurance Co. v. Perez
783 S.W.2d 779 (Court of Appeals of Texas, 1990)
HOW Insurance Co. v. Patriot Financial Services of Texas, Inc.
786 S.W.2d 533 (Court of Appeals of Texas, 1990)
Bachynski v. Fox and Co.
662 S.W.2d 771 (Court of Appeals of Texas, 1983)
Fretz Construction Co. v. Southern National Bank of Houston
626 S.W.2d 478 (Texas Supreme Court, 1982)
Sunbelt Construction Corp. v. S & D Mechanical Contractors, Inc.
668 S.W.2d 415 (Court of Appeals of Texas, 1983)
Federal Land Bank Ass'n of Tyler v. Sloane
825 S.W.2d 439 (Texas Supreme Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Town Lake Joint Venture, Ron Mullen and Joseph E. Thompson v. Lumbermen's Investment Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-lake-joint-venture-ron-mullen-and-joseph-e-th-texapp-1993.