Towerridge Inc. v. TAO Inc.

CourtCourt of Appeals for the Tenth Circuit
DecidedApril 15, 1997
Docket96-6015
StatusPublished

This text of Towerridge Inc. v. TAO Inc. (Towerridge Inc. v. TAO Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Towerridge Inc. v. TAO Inc., (10th Cir. 1997).

Opinion

UNITED STATES COURT OF APPEALS Tenth Circuit Byron White United States Courthouse 1823 Stout Street Denver, Colorado 80294 (303) 844-3157 Patrick J. Fisher, Jr. Elisabeth A. Shumaker Clerk Chief Deputy Clerk

April 30, 1997

TO: All recipients of the captioned opinion

RE: 96-6015, Towerridge Inc. v. T.A.O. Inc. April 15, 1997

Please be advised of the following correction to the captioned decision:

The identification of the attorneys for Defendants-Appellants and Cross-Appellees is incorrect. The identification should read as follows:

Charles E. Raley (W. Drew Mallender with him on the briefs) of Watt, Tieder & Hoffar, L.L.P., McLean, Virginia, for Defendants-Appellants and Cross- Appellees.

Please make the appropriate correction.

Very truly yours,

Patrick Fisher, Clerk

Susie Tidwell Deputy Clerk F I L E D United States Court of Appeals Tenth Circuit PUBLISH APR 15 1997 UNITED STATES COURT OF APPEALS PATRICK FISHER Clerk TENTH CIRCUIT

TOWERRIDGE, INC., sued as United States of America for the Benefit of Towerridge, Inc.,

Plaintiff-Appellee and Cross-Appellant, Nos. 96-6015 & v. 96-6107

T.A.O., INC., and MID-CONTINENT CASUALTY CO.,

Defendants-Appellants and Cross-Appellees.

Appeal from the United States District Court for the Western District of Oklahoma (D.C. No. CIV-95-42BL)

Patsy H. Brown (Michael L. Loyd with her on the briefs) of Michael L. Loyd & Associates, Bethany, Oklahoma, for Plaintiff-Appellee and Cross-Appellant.

Charles E. Raley (W. Drew Mallender with him on the briefs) of Watt, Tieder & Hoffar, L.L.P., McLean, Virginia, for Defendants-Appellants and Cross- Appellees.

Before BALDOCK, BRORBY and MURPHY, Circuit Judges.

BRORBY, Circuit Judge.

I. BACKGROUND This action was brought by Towerridge, Inc., a subcontractor on a federal

construction project, against the prime contractor, T.A.O., Inc., and T.A.O.'s

surety on the prime contract, Mid-Continent Casualty Company. Towerridge sued

under the Miller Act, 40 U.S.C. §§ 270a-270d (1994), seeking recovery for sums

allegedly due and owing under its subcontract. The jury awarded Towerridge

$56,963.94 in damages and, in response to a special interrogatory, found T.A.O.

acted in bad faith. The district court entered judgment accordingly, and later

awarded Towerridge prejudgment interest and attorneys' fees. T.A.O. appeals the

award of damages, the award of prejudgment interest, and the award of attorneys'

fees. It also appeals the district court's admission into evidence of references to a

separate action between T.A.O. and the government. Towerridge cross-appeals

the district court's failure to note the jury's finding of bad faith on its entry of

judgment. We reverse the district court's award of attorneys' fees and affirm the

district court on all other issues.

T.A.O. was the prime contractor on a construction project for the Oklahoma

Air National Guard in Oklahoma City. Because the project was federally funded,

T.A.O. was required under the Miller Act to post a payment bond to protect

-2- subcontractors and materialmen. 1 Co-defendant Mid-Continent Casualty Co. was

the surety on the bond.

Under the prime contract, T.A.O. submitted monthly payment applications

to the government. These payment applications stated the scheduled value of

each of sixty-nine line-item tasks which made up T.A.O.'s obligations under the

contract, the sum of which equaled the contract price. The applications also

provided estimated percentages of completion of both the actual line item tasks

and their scheduled values. Upon receipt of the applications, the government paid

T.A.O. the percentage of scheduled values completed, minus a retainage due upon

completion of the project.

Towerridge subcontracted with T.A.O. to perform most of the concrete and

asphalt paving work for the project. The total subcontract price was $448,520.00.

The subcontracted work was broken down into four line items: (1) concrete

paving, dowels and sawing, (2) curb and gutter, (3) sealant, and (4) rock and

1 The Miller Act thus provides an alternative remedy to the mechanics' liens ordinarily available on private construction projects. United States ex rel. C.J.C., Inc. v. Western States Mechanical Contractors, Inc., 834 F.2d 1533, 1537 n.1 (10th Cir. 1987). Because a lien cannot attach to federal property, those supplying labor or materials are instead protected by the payment bond. Id.

-3- asphalt. The subcontract assigned each line item a scheduled value representing

its proportionate value of the whole; thus the sum of the scheduled values equaled

the subcontract price. T.A.O. was to make monthly progress payments to

Towerridge for work satisfactorily completed, minus a ten percent retainage. To

that end, Towerridge submitted monthly payment applications to T.A.O. providing

estimated completion percentages of the line-item tasks, and the appropriate

percentage of each line item's scheduled value to which Towerridge was therefore

entitled. Thus, ideally, upon Towerridge's completion of twenty percent of a line

item, T.A.O. was to pay Towerridge twenty percent of that line item's scheduled

value; when Towerridge had completed ninety percent of a line item it was

entitled to ninety percent of the scheduled value, and so forth. 2

Towerridge started work in June 1993. However, nearly from the

beginning of Towerridge's performance, T.A.O. and Towerridge disagreed over

whether Towerridge was working sufficiently productively and efficiently to

complete its work on schedule. Timely completion of all portions of the project

was of particular importance to T.A.O. because its prime contract contained a

2 Actually, these payments would be less the ten percent retainage due upon Towerridge's completion of performance. However, because T.A.O. does not contest Towerridge's right to the retainage, we do not concern ourselves with this issue. See State Farm Fire & Cas. Co. v. Mhoon, 31 F.3d 979, 984 n.7 (10th Cir. 1994) (issues not raised in opening brief deemed waived).

-4- liquidated damages clause rendering T.A.O. liable to the government for $296.85

for each day completion was delayed beyond the scheduled completion date.

The parties dispute to whom blame for any delays or defects in

Towerridge's performance should be attributed. Both note delays and disruptions

caused by the government hampered completion of the overall project; however,

they disagree on the extent the government's actions impaired Towerridge's ability

to perform. Towerridge asserts it was at all times ready and able to meet its

obligations under the subcontract, and that any delays in its performance were

caused by T.A.O. and the government's failure to satisfy necessary preconditions

to Towerridge's performance, such as clearing, grading and surveying.

Additionally, Towerridge claims T.A.O. failed to properly schedule, supervise,

and coordinate the project, and that any defects in its work were the result of

T.A.O.'s inadequate project management rather than the fault of Towerridge.

T.A.O., on the other hand, contends Towerridge repeatedly left the work site and

failed to use sufficient workers to timely complete its work, even after T.A.O.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Guevara v. Maritime Overseas Corp.
59 F.3d 1496 (Fifth Circuit, 1994)
Guevara v. Maritime Overseas Corp.
59 F.3d 1496 (Fifth Circuit, 1995)
Vaughan v. Atkinson
369 U.S. 527 (Supreme Court, 1962)
Fleischmann Distilling Corp. v. Maier Brewing Co.
386 U.S. 714 (Supreme Court, 1967)
Hall v. Cole
412 U.S. 1 (Supreme Court, 1973)
Alyeska Pipeline Service Co. v. Wilderness Society
421 U.S. 240 (Supreme Court, 1975)
West Virginia v. United States
479 U.S. 305 (Supreme Court, 1987)
Chambers v. Nasco, Inc.
501 U.S. 32 (Supreme Court, 1991)
Haines v. Fisher
82 F.3d 1503 (Tenth Circuit, 1996)
Doan v. Seagate Technology, Inc.
82 F.3d 974 (Tenth Circuit, 1996)
Nemeroff v. Abelson
620 F.2d 339 (Second Circuit, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
Towerridge Inc. v. TAO Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/towerridge-inc-v-tao-inc-ca10-1997.