Towerridge Inc. v. TAO Inc.

Court of Appeals for the Tenth Circuit·Decided April 15, 1997·No. 96-6015·Published

Opinion

UNITED STATES COURT OF APPEALS Tenth Circuit

Byron White United States Courthouse 1823 Stout Street

Denver, Colorado 80294

(303) 844-3157

Patrick J. Fisher, Jr. Elisabeth A. Shumaker Clerk Chief Deputy Clerk

April 30, 1997

TO: All recipients of the captioned opinion

RE: 96-6015, Towerridge Inc. v. T.A.O. Inc.

April 15, 1997

Please be advised of the following correction to the captioned decision:

The identification of the attorneys for Defendants-Appellants and Cross-Appellees is incorrect. The identification should read as follows:

Charles E. Raley (W. Drew Mallender with him on the briefs) of Watt, Tieder & Hoffar, L.L.P., McLean, Virginia, for Defendants-Appellants and Cross-

Appellees.

Please make the appropriate correction.

Very truly yours,

Patrick Fisher, Clerk

Susie Tidwell

Deputy Clerk

F I L E D

United States Court of Appeals Tenth Circuit

PUBLISH

APR 15 1997

UNITED STATES COURT OF APPEALS PATRICK FISHER

Clerk

TENTH CIRCUIT

TOWERRIDGE, INC., sued as United States of America for the Benefit of Towerridge, Inc.,

Plaintiff-Appellee and Cross-Appellant, Nos. 96-6015 &

v. 96-6107

T.A.O., INC., and MID-CONTINENT CASUALTY CO.,

Defendants-Appellants and Cross-Appellees.

Appeal from the United States District Court for the Western District of Oklahoma (D.C. No. CIV-95-42BL)

Patsy H. Brown (Michael L. Loyd with her on the briefs) of Michael L. Loyd & Associates, Bethany, Oklahoma, for Plaintiff-Appellee and Cross-Appellant.

Charles E. Raley (W. Drew Mallender with him on the briefs) of Watt, Tieder & Hoffar, L.L.P., McLean, Virginia, for Defendants-Appellants and Cross- Appellees.

Before BALDOCK, BRORBY and MURPHY, Circuit Judges.

BRORBY, Circuit Judge. I. BACKGROUND

This action was brought by Towerridge, Inc., a subcontractor on a federal construction project, against the prime contractor, T.A.O., Inc., and T.A.O.'s surety on the prime contract, Mid-Continent Casualty Company. Towerridge sued under the Miller Act, 40 U.S.C. §§ 270a-270d (1994), seeking recovery for sums allegedly due and owing under its subcontract. The jury awarded Towerridge $56,963.94 in damages and, in response to a special interrogatory, found T.A.O. acted in bad faith. The district court entered judgment accordingly, and later awarded Towerridge prejudgment interest and attorneys' fees. T.A.O. appeals the award of damages, the award of prejudgment interest, and the award of attorneys' fees. It also appeals the district court's admission into evidence of references to a separate action between T.A.O. and the government. Towerridge cross-appeals the district court's failure to note the jury's finding of bad faith on its entry of judgment. We reverse the district court's award of attorneys' fees and affirm the district court on all other issues.

T.A.O. was the prime contractor on a construction project for the Oklahoma Air National Guard in Oklahoma City. Because the project was federally funded, T.A.O. was required under the Miller Act to post a payment bond to protect

subcontractors and materialmen. 1 Co-defendant Mid-Continent Casualty Co. was the surety on the bond.

Under the prime contract, T.A.O. submitted monthly payment applications to the government. These payment applications stated the scheduled value of each of sixty-nine line-item tasks which made up T.A.O.'s obligations under the contract, the sum of which equaled the contract price. The applications also provided estimated percentages of completion of both the actual line item tasks and their scheduled values. Upon receipt of the applications, the government paid T.A.O. the percentage of scheduled values completed, minus a retainage due upon completion of the project.

Towerridge subcontracted with T.A.O. to perform most of the concrete and asphalt paving work for the project. The total subcontract price was $448,520.00. The subcontracted work was broken down into four line items: (1) concrete paving, dowels and sawing, (2) curb and gutter, (3) sealant, and (4) rock and

1 The Miller Act thus provides an alternative remedy to the mechanics'

liens ordinarily available on private construction projects. United States ex rel. C.J.C., Inc. v. Western States Mechanical Contractors, Inc., 834 F.2d 1533, 1537 n.1 (10th Cir. 1987). Because a lien cannot attach to federal property, those supplying labor or materials are instead protected by the payment bond. Id.

asphalt. The subcontract assigned each line item a scheduled value representing its proportionate value of the whole; thus the sum of the scheduled values equaled the subcontract price. T.A.O. was to make monthly progress payments to Towerridge for work satisfactorily completed, minus a ten percent retainage. To that end, Towerridge submitted monthly payment applications to T.A.O. providing estimated completion percentages of the line-item tasks, and the appropriate percentage of each line item's scheduled value to which Towerridge was therefore entitled. Thus, ideally, upon Towerridge's completion of twenty percent of a line item, T.A.O. was to pay Towerridge twenty percent of that line item's scheduled value; when Towerridge had completed ninety percent of a line item it was entitled to ninety percent of the scheduled value, and so forth. 2

Towerridge started work in June 1993. However, nearly from the beginning of Towerridge's performance, T.A.O. and Towerridge disagreed over whether Towerridge was working sufficiently productively and efficiently to complete its work on schedule. Timely completion of all portions of the project was of particular importance to T.A.O. because its prime contract contained a

2 Actually, these payments would be less the ten percent retainage due upon Towerridge's completion of performance. However, because T.A.O. does not contest Towerridge's right to the retainage, we do not concern ourselves with this issue. See State Farm Fire & Cas. Co. v. Mhoon, 31 F.3d 979, 984 n.7 (10th Cir. 1994) (issues not raised in opening brief deemed waived).

liquidated damages clause rendering T.A.O. liable to the government for $296.85 for each day completion was delayed beyond the scheduled completion date.

The parties dispute to whom blame for any delays or defects in Towerridge's performance should be attributed. Both note delays and disruptions caused by the government hampered completion of the overall project; however, they disagree on the extent the government's actions impaired Towerridge's ability to perform. Towerridge asserts it was at all times ready and able to meet its obligations under the subcontract, and that any delays in its performance were caused by T.A.O. and the government's failure to satisfy necessary preconditions to Towerridge's performance, such as clearing, grading and surveying. Additionally, Towerridge claims T.A.O. failed to properly schedule, supervise, and coordinate the project, and that any defects in its work were the result of T.A.O.'s inadequate project management rather than the fault of Towerridge. T.A.O., on the other hand, contends Towerridge repeatedly left the work site and failed to use sufficient workers to timely complete its work, even after T.A.O. repeatedly warned of the necessity for Towerridge to increase its workforce and speed its performance. T.A.O. also contends Towerridge's work was substandard, containing numerous defects requiring repair or reconstruction, further delaying

completion. Eventually, T.A.O. hired supplemental subcontractors to complete and correct the work Towerridge was to have performed.

Free access — add to your briefcase to read the full text and ask questions with AI

Towerridge Inc. v. TAO Inc., (10th Cir. 1997).

Towerridge Inc. v. TAO Inc. (Towerridge Inc. v. TAO Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Guevara v. Maritime Overseas Corp.
59 F.3d 1496 (Fifth Circuit, 1994)
Guevara v. Maritime Overseas Corp.
59 F.3d 1496 (Fifth Circuit, 1995)
Vaughan v. Atkinson
369 U.S. 527 (Supreme Court, 1962)
Fleischmann Distilling Corp. v. Maier Brewing Co.
386 U.S. 714 (Supreme Court, 1967)
Hall v. Cole
412 U.S. 1 (Supreme Court, 1973)
Alyeska Pipeline Service Co. v. Wilderness Society
421 U.S. 240 (Supreme Court, 1975)
West Virginia v. United States
479 U.S. 305 (Supreme Court, 1987)
Chambers v. Nasco, Inc.
501 U.S. 32 (Supreme Court, 1991)
Haines v. Fisher
82 F.3d 1503 (Tenth Circuit, 1996)
Doan v. Seagate Technology, Inc.
82 F.3d 974 (Tenth Circuit, 1996)
Nemeroff v. Abelson
620 F.2d 339 (Second Circuit, 1980)