Total Recall Technologies v. Palmer Luckey

District Court, N.D. California·Decided October 15, 2021·No. 3:15-cv-02281·Unknown

Opinion

1 2 3 4 5 6 7 UNITED STATES DISTRICT COURT 8 NORTHERN DISTRICT OF CALIFORNIA 9

11 TOTAL RECALL TECHNOLOGIES, 12 Plaintiff, No. C 15–02281 WHA

13 v.

14 PALMER LUCKEY, et al., POST-TRIAL MEMORANDUM OPINION 15 Defendants.

16 17 This memorandum opinion explains various rulings made during the course of trial. 18 1. IMPACT OF CREDIBILITY ON CONTRACT INTERPRETATION. 19 In the spring, at the request of the judge, the parties submitted several rounds of 20 supplemental briefing on the issue of contract interpretation including, specifically, the extent to 21 which the credibility of Seidl or Luckey could affect the construction of the contract. The parties 22 also submitted, by way of exhibits, (1) all of the pre-execution communications between Seidl 23 and Luckey, (2) their post-execution written communications, and (3) the parties’ deposition 24 transcripts. The judge carefully considered the briefing and the exhibits, including the hundreds 25 of emails and Skype chats between Luckey and Seidl. 26 In June, an order issued giving a tentative construction of the meaning of the agreement. 27 The order rejected TRT’s argument that the asserted pattern of lies and deceit by Luckey could, 1 concealment of his work on the Rift from Seidl could support a reasonable inference by the jury 2 that Luckey did so because he believed his work on the Rift was in breach of the contract which, 3 in turn, would be evidence that the contract did, in fact, have that meaning. Therefore, TRT 4 argued, interpretation of the contract should go to the jury which could draw inferences about the 5 meaning based on Luckey’s concealment and other conflicting extrinsic evidence. 6 The contract construction order rejected that argument for two reasons. First, assuming 7 TRT could persuade a jury to make the inference described above, such line of proof would only 8 lead to a contract interpretation foreclosed by Section 16600 of California’s Business and 9 Professions Code. TRT was not obligated to pay Luckey anything for his work and Seidl would 10 have had no use for Luckey’s HMD designs unsuitable for Seidl’s stated purpose. Interpreting 11 the no-aid restraint to cover all designs in Luckey’s workshop, including the Rift, regardless of 12 whether they were reasonably suitable for Seidl’s purpose, would have been an unreasonable 13 restraint of trade and competition. Thus, TRT’s preferred inference from Luckey’s alleged 14 concealment of his work on the Rift would only lead to a contractual meaning foreclosed by 15 Section 16600. 16 Second, a jury finding that Luckey concealed his work on the Rift because he believed it 17 breached the agreement would only be one of several competing inferences that could be drawn 18 from the extrinsic evidence, introducing further ambiguity into the meaning of the contract 19 language. In such case, the “tie breaker” of California Civil Code Section 1654, which resolves 20 ambiguities against the drafter, would apply in spades here because Seidl was entirely 21 responsible for the ambiguities. Thus, “[g]iven that the alleged pattern of lies and deceit, even if 22 proven, could not possibly matter on the issue of the meaning of the contract, there remains no 23 credibility issue for jury determination,” and, therefore, the meaning of the contract was a matter 24 for judicial construction (Dkt. 418 at 18–19). 25 Despite the numerous rounds of briefing on the subject, the tentative contract construction 26 order invited the parties to file briefs critiquing the Court’s construction. The Court then issued a 27 final contract construction order adopting the construction given in the tentative order in all 1 parties “an opportunity to adjust their expert reports to conform to the Court’s construction” (id. 2 at 23). In addition, the final construction order stated (id. at 23–24): 3 The Court will consider all evidence received in the liability phase of the trial and then evaluate whether any adjustment to the final 4 construction is warranted. The expert reports and trail plans should take this possibility into account. The Court will also 5 consider the possibility, despite the foregoing, of asking the jury to return a special verdict or interrogatory answer with respect to the 6 alleged lies and concealment of Luckey and the reason(s) therefor, and/or possibility with respect to some other supposed credibility 7 issue pertaining to extrinsic evidence. At all events, the judge will instruct the jury on the meaning of the agreement(s) between the 8 parties.

9 . . . [E]ach side must further file a statement setting forth each specific credibility issue for the jury with respect to contract 10 interpretation and extrinsic evidence, setting forth, for each issue, the witnesses whose credibility is implicated and what difference it 11 would make in contract interpretation. 12 In response, TRT repeated its argument that (Dkt. 435 at 6) (emphasis in original): 13 [T]he most telling evidence that supports TRT’s view that the no- 14 aid provision must apply to designs in progress is Luckey’s eventual admission in September 2012—after being accused of 15 breaching his agreement with Seidl by launching a Kickstarter for the Rift—that his commercial pursuit of the Rift would have been 16 precluded by the Exclusivity Agreement had he pursued it before July 1, 2012. 17 18 At a conference outside the presence of the jury after the third day of trial, the Court 19 requested TRT to file a brief showing how any trial testimony given thus far raised a credibility 20 issue which could affect the Court’s contract construction (Trial Tr. 804:20–805:9). 21 TRT responded with two points. First, TRT cited Luckey and Seidl’s testimonies about 22 their subjective understandings of the meaning of Section 9 of the contract. TRT cited the 23 following testimony from Luckey (Trial Tr. 729:24–730:18): 24 Q. And you considered the meaning of head mounted display used 25 in that section prior to signing [the August 1 contract]; right?

26 A. Yes.

27 Q. And you understood the meaning of head mounted display, as used in Section 9, to mean the head displays that you were building A. Yes. 1 Q. And you understood that the exclusivity in Section 9 applied to 2 designs that you build using parts that TRT paid for; right?

3 A. Using — it applied to designs that I was building for Seidl, whether or not I was using parts that they had paid for. Because, 4 remember, some of the prototypes I built for them used parts that I paid for. So it wasn’t about what parts they had paid for. It was 5 about things I was making for — for them.

6 Q. Well, certainly you understood that with respect to parts that they paid for, you were going to use those parts exclusively for 7 TRT?

8 A. That’s right. 9 This exchange tracks closely the actual instruction given to the jury. TRT also pointed to 10 Seidl’s testimony that he did not intend a distinction between the different usages of the term 11 “Head Mounted Display” in Section 9 of the contract (see Trial Tr. 469:19–470:20). 12 The fundamental problem with these snippets is that, once again, even if accepted as per 13 TRT’s spin, they would only lead to meanings foreclosed by Section 16600 and the rule 14 construing ambiguities against the drafter. 15 TRT also pointed to Seidl’s trial testimony in which Seidl read back the parties’ written 16 communications from September and December 2012 in which Seidl accused Luckey of breach 17 and Luckey responded, in part, by lying to Seidl about the timing of his work on the Rift (see 18 Trial Tr. 323:18–324:2, 327:15–24, 383:15–385:10). As noted above, TRT relied on these 19 statements in repeatedly arguing that interpretation of the contract should be left to the jury (Dkt. 20 435 at 6).

Free access — add to your briefcase to read the full text and ask questions with AI

Total Recall Technologies v. Palmer Luckey, (N.D. Cal. 2021).

Total Recall Technologies v. Palmer Luckey (Total Recall Technologies v. Palmer Luckey) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Vai v. Bank of America National Trust & Savings Ass'n
364 P.2d 247 (California Supreme Court, 1961)
Persson v. Smart Inventions, Inc.
23 Cal. Rptr. 3d 335 (California Court of Appeal, 2005)
Richelle L. v. Roman Catholic Archbishop
130 Cal. Rptr. 2d 601 (California Court of Appeal, 2003)
Moreno v. City of King
25 Cal. Rptr. 3d 29 (California Court of Appeal, 2005)
Salahutdin v. Valley of California, Inc.
24 Cal. App. 4th 555 (California Court of Appeal, 1994)
Assilzadeh v. California Federal Bank
98 Cal. Rptr. 2d 176 (California Court of Appeal, 2000)
Brown v. Wells Fargo Bank, N.A.
168 Cal. App. 4th 938 (California Court of Appeal, 2008)
Nasrawi v. Buck Consultants LLC
231 Cal. App. 4th 328 (California Court of Appeal, 2014)
Lomita Land and Water Co. v. Robinson
97 P. 10 (California Supreme Court, 1908)
Engalla v. Permanente Medical Group, Inc.
938 P.2d 903 (California Supreme Court, 1997)
Shawmut Bank, N.A. v. Kress Associates
33 F.3d 1477 (Ninth Circuit, 1994)
Xpertuniverse, Inc. v. Cisco Systems Inc.
868 F. Supp. 2d 376 (D. Delaware, 2012)