Tortolani v. Diwinsky

152 A.2d 653, 89 R.I. 283, 1959 R.I. LEXIS 87
Supreme Court of Rhode Island·Decided June 23, 1959·No. Ex. No. 9776·Published

Opinion

*284 Powers, J.

This is an action in assumpsit to recover a balance allegedly due on a contract and for moneys due and owing for services, goods and supplies. The instant case and a companion case, Diwinsky v. Tortolani, 89 R. I. 290, were tried together before a justice of the superior court sitting with a jury, and resulted in a verdict for the plaintiff. It is here on the defendant’s bill of exceptions to the denial of her motions for a directed verdict and for a new trial.

Although the cases were heard together before us, we have treated them separately. See our opinion filed this day in Diwinsky v. Tortolani, supra.

It appears from the evidence that the parties entered into a contract on June 27, 1953 wherein plaintiff agreed to construct a dwelling house for defendant and her husband and defendant agreed to pay $18,300 in consideration thereof. The contract consisted of the agreement and, by incorporation, the plans and specifications. The plaintiff was to receive payments in four equal installments of $4,575. The first payment was to be made when the foundation was *285 completed, the second and third at specified stages of construction, and the fourth when the work was completed.'

The plaintiff testified he advised defendant that if any changes were to be made he must know before the work was started; otherwise changes would constitute' extras for which he would be entitled to additional compensation. The first three payments were made on schedule.

The plaintiff further testified that payments were made after inspection by a representative of the bank. It appears that the work went smoothly until after the third payment was received. The evidence shows that the work was started after June 27 and defendant’s husband, who died Augúst 23, was present at the first two payments. Shortly after his death the work was suspended until the fall when the plastering was completed and plaintiff worked on and off through the winter on the interior of the house. He further testified that by this time “the inside of the house was pretty near completed * *

The plaintiff received an additional $1,500 on March 30, 1954 after requesting more funds from defendant to assist him in completing the work. This made a total of $15,225 that plaintiff had received from defendant. The plaintiff admitted that he left the work unfinished and estimated it would cost defendant $1,045 to complete it. He testified that he did not complete the work for the reason that defendant refused to pay for the extra work as agreed, but he acknowledged that on the original contract defendant was entitled to recoup the cost of the unfinished work.

The record discloses that for a time during the construction of the house defendant considered selling it and a sign was placed thereon bearing the names of plaintiff and the attorney for defendant. Later she changed her mind and moved into the house in the latter part of April 1954 at which time as she testified: “The place was almost completed when I had to move in.” It was shortly thereafter *286 that plaintiff removed his tools from the premises and did not return.

The plaintiff testified that during the time the house was ■being constructed the defendant or her husband in her presence ordered numerous changes for which she agreed to pay additional compensation. The plaintiff testified that such changes included removing asphalt shingles from the peaks and replacing them with red cedar panels, a change from “American Standard” to “Crane” plumbing fixtures, which was substantially more costly, and a change from copper to wooden gutters resulting in further additional cost.

Other changes included one long window in the kitchen rather than two small ones, another cabinet in the kitchen as well as a longer counter and snack bar. The plaintiff testified that these changes were also requested by defendant who agreed to pay extra for them. Further, according to plaintiff’s testimony, after some of the interior painting had been completed the defendant changed her mind about the color and agreed to additional payments for repainting.

The plaintiff’s testimony on the requested changes for which defendant agreed to pay also included added floor joists to comply with the building laws of the city of Cranston, panel windows on the sides of the front door, hood over the front door and a closed-in rear porch rather than a patio as specified in the original plan. His estimate of the value of extra work for which he was entitled to be paid was $3,784. He admitted that prior to the bringing of his suit he had never presented defendant with an itemized bill for the extra work.

His testimony as to requested changes and defendant’s agreement to pay for them was substantiated in part by Charles Giblin, an electrician employed by defendant, and by Silvio DeMarco, a mutual friend of the parties. Both witnesses testified to overhearing defendant requesting changes, and DeMarco added that at defendant’s request a wall partition was moved back to enlarge one of the bed *287 rooms. Although plaintiff did not mention this particular change, DeMarco stated that the request was made in his presence and that defendant’s husband in her presence said: “Don’t worry. We will pay for it.”

The defendant admitted requesting an additional fireplace in the basement for which plaintiff testified he had been paid $300. She further admitted agreeing to pay an additional $100 for the change from a picture window to a bow window in the front of the house and to pay extra for changes regarding an ironing' board. Other than these, however, she flatly denied requesting any changes or promising to pay therefor and contradicted plaintiff and his witnesses Giblin and DeMarco by specific questions and answers.

She testified that after plaintiff refused to do any further work she engaged J. Baccala & Sons, Inc., who together with Allie Campopiano entered into a joint venture to complete the unfinished work and correct defective work performed by plaintiff. The plaintiff denied that any of his work was defective. The contractor Campopiano testified as to the work necessary to be done and stated that the cost thereof amounted to $4,200 for which he and his associate Baccala were paid by defendant.

During the trial of the two cases the jury took a view of the premises in dispute, at which time they were instructed by the trial justice to observe those matters which attorneys for the parties would call to their attention.

The defendant’s first exception is to the denial of her motion for a directed verdict. It is her contention that as a matter of law plaintiff could not recover the balance of the contract price since by his own admission the contract was never completed; nor could plaintiff recover any part of it on the theory of substantial compliance since he wilfully abandoned the work. She calls our attention to the case of Carpenter v. Gay, 12 R. I. 306, in support of her contention.

*288 .

Free access — add to your briefcase to read the full text and ask questions with AI

Tortolani v. Diwinsky, 152 A.2d 653, 89 R.I. 283, 1959 R.I. LEXIS 87 (R.I. 1959).

152 A.2d 653 (Tortolani v. Diwinsky) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Desmond-Dunne Co. v. . Friedman-Doscher Co.
56 N.E. 996 (New York Court of Appeals, 1900)
Danville Bridge Co. v. Pomroy & Colony
15 Pa. 151 (Supreme Court of Pennsylvania, 1850)
Gillespie Tool Co. v. Wilson
16 A. 36 (Supreme Court of Pennsylvania, 1888)