Danville Bridge Co. v. Pomroy & Colony

15 Pa. 151
CourtSupreme Court of Pennsylvania
DecidedJuly 15, 1850
StatusPublished
Cited by14 cases

This text of 15 Pa. 151 (Danville Bridge Co. v. Pomroy & Colony) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Danville Bridge Co. v. Pomroy & Colony, 15 Pa. 151 (Pa. 1850).

Opinion

The opinion of the court was delivered by

Bill, J.

By their agreement of the 26th of June, 1846, the plaintiffs below assumed the liability and undertook the engagements of Kownover and Evans, in respect of the superstructure of the bridge to be rebuilt. The order drawn by the latter in favor of the former, and the acceptance by the company, so refers to the original contract as to show the parties contemplated it as the basis of the transaction, and as the standard by which the relative rights and remedies of the now plaintiffs and defendants were to be measured and determined. It is true, the order and acceptance furnish the immediate foundation of the action, but its sufficiency, as affording means of redress, is influenced and limited by the articles of the 11th of May, to which all the parties unequivocally point as the governing instrument. The cause is, therefore, to be determined precisely as though Pomroy and Colony were the original contractors for building the superstructure of the bridge, upon the terms and under the conditions stipulated between Kownover and Evans and the company. Thus treated, the case may be approached disembarrassed of some of the perplexities a different view tends to engraft upon it.

[158]*158By the terms of the first contract, the bridge was to have been finished on the 1st of January, 1847, under penalty of a stipulated forfeiture. But all the evidence in the cause shows that this stipulation was waived. Indeed, it was not at all insisted on, as furnishing any ground of defence. Had it been, the terms and time of acceptance of the order by the - defendant would have afforded the plaintiffs a triumphant answer: Preston v. Finney, 2 W. & Ser. 55. In pursuance of their agreement with Kownover and Evans, the plaintiffs, with their workmen, commenced to build the superstructure in the year 1846. It progressed, under the immediate supervision and direction of the defendant’s engineer, until November, 1847, when it was practicable for the passage of wagons and other vehicles. Early in that month, the plaintiffs opened it to travellers and others, intending to take the tolls for their own benefit; but their right to do so was disputed by the defendant, and a quarrel ensuing, the bridge was again closed by the contractors. It so continued until the first of December, when, it would seem, the company took forcible possession of the structure; or, at least, the possession was assumed against the will and in spite of the plaintiffs, who were then carrying on the work towards its completion. On the same day, the defendants threw the bridge open for the transit of animals and carriages, taking toll in the usual way, and placed persons, as guards, to prevent the contractors from again assuming the command of it. The possession and collection of tolls has been continued ever since, the plaintiffs, in the'mean time, continuing to labor on the bridge until August, 1848, when, pronouncing it to be completed, they demanded to be paid to them $1566.61, the balance due of the sum called for by the order of June, 1847, as they averred. Payment was refused, because of certain defects and omissions in the work, which, it is insisted, constitute such a violation of the original contract as, in law, bars the action, and wholly defeats the plaintiffs’ right to recover any part of the sum demanded. The Court of Common Pleas denied this, and instructed the jury that the defects and omissions complained of, if proved, did not affect the whole consideration of the contract, and, being capable of compensation in damages, were not, necessarily, an answer to the whole of the plaintiffs’ demand. The defendant’s position is drawn from the general rule, that an entire contract must be performed in all its parts by him who claims a counter performance from the other contracting parties, and if there be a failure in any particular, no recovery can be had, however meritorious may be the claim preferred for services actually performed in furtherance of the engagement. At one time, this rule was rigidly adhered to, though the consequence was to bestow upon one the advantages derived from the labor, time, and money of another; because, it was .supposed, an insuperable technical difficulty forbade a division of the subject of the contract. Mutual [159]*159covenants, like those which exist here, were treated as necessarily entire; and as performance on one side was regarded as a condition precedent to a demand for performance on the other, nothing short of a perfect discharge of every part of the undertaking was accepted as a sufficient fulfilment of the condition. This was peculiarly so when the contract was for the execution of a task, involving skill and labor on one side, to be compensated by payment in money, or other valuable thing, on the other. And it is still the general rule which governs the remedy upon entire contracts, as is shown by Shaw v. The Turnpike Company, 2 Pa. Rep. 454; Alexander v. Hoffman, 5 W.& Ser. 382, and other cases.

Bui; the injustice inflicted in practice, by a liberal application of it in all cases, long since introduced an exception to, or rather modification of a principle, which, however perfect in theory, was found to work harshly in a large variety of instances. That modification was, perhaps, first recognised in Boone v. Eyre, 1 H. Bl. 273, note a: and is thus stated in Ligget v. Smith, 3 Watts 331, where it was approved and applied. A mutual or dependent covenant, which goes but to a. part of the condition on both sides, and whose breach may be compensated in damages, is to b.e treated exactly as if it were separate and independent. Its non-performance will not, necessarily, bar the entire right of the plaintiff. So too, a covenant which is in form entire, but in truth embraces a variety of acts, more or less essential to the whole performance, may be so discharged as to sustain an averment of performance, though a literal compliance cannot be alleged: Wilhelm v. Caul, 2 W. & Ser. 26; Preston v. Finney, id. 53, and Chambers v. Jaynes, 4 Barr 39, are examples of this. Each of them proceeds upon the ground that, where a party, acting honestly, and intending to fulfil his contract, performs it substantially, but fails in some comparatively unimportant particulars, the other party will not be permitted to enjoy the fruits of such imperfect performance, without paying a fair compensation according to the contract, receiving a credit for any loss or inconvenience suffered. And, perhaps, it may be asserted, that where a thing -is so far perfected as to answer the intended purpose, and it is taken possession of and turned to that purpose by the party for whom it is constructed, no mere imperfection or omission, which does not virtually affect its usefulness, can be interposed to prevent a recovery, subject to a deduction for damages, consequent upon the imperfection complained of. Of course, the indulgence is not to be so stretched as to cover fraud, gross negligence, or obstinate and wilful refusal to fulfil the whole engagement, or even a voluntary and causeless abandonment of it. This distinction is pointed out by Mr. Justice Sergeant, in Preston v. Finney, from whence he draws the conclusion, that “ in those .cases where the law allows the party to recover on a quantum meruit or quantum valebat, [160]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Formigli Corporation v. Fox
348 F. Supp. 629 (E.D. Pennsylvania, 1972)
Tortolani v. Diwinsky
152 A.2d 653 (Supreme Court of Rhode Island, 1959)
Mornes Estate
79 Pa. D. & C. 356 (Lawrence County Orphans' Court, 1951)
Mort Co. v. Paul
76 A.2d 445 (Superior Court of Pennsylvania, 1950)
Typhoon Air Conditioning Co. v. Fried
24 A.2d 929 (Superior Court of Pennsylvania, 1941)
O'Hare v. McGee
176 A. 525 (Superior Court of Pennsylvania, 1934)
Louthan v. Carson
63 Colo. 473 (Supreme Court of Colorado, 1917)
Otis Elevator Co. v. Flanders Realty Co.
90 A. 624 (Supreme Court of Pennsylvania, 1914)
Smith v. Cunningham Piano Co.
86 A. 1067 (Supreme Court of Pennsylvania, 1913)
Pressy v. McCornack
84 A. 427 (Supreme Court of Pennsylvania, 1912)
Snedaker v. Torpey
41 Pa. Super. 312 (Superior Court of Pennsylvania, 1909)
Philip Hiss Co. v. Pitcairn
107 F. 425 (U.S. Circuit Court for the District of Western Pennsylvania, 1901)
Langenheim v. Anschutz-Bradberry Co.
2 Pa. Super. 285 (Superior Court of Pennsylvania, 1896)
Holmes v. Chartiers Oil Co.
21 A. 231 (Supreme Court of Pennsylvania, 1891)

Cite This Page — Counsel Stack

Bluebook (online)
15 Pa. 151, Counsel Stack Legal Research, https://law.counselstack.com/opinion/danville-bridge-co-v-pomroy-colony-pa-1850.