Toomey Bros. v. United States

49 Ct. Cl. 172, 1914 U.S. Ct. Cl. LEXIS 302, 1914 WL 1399
CourtUnited States Court of Claims
DecidedJanuary 5, 1914
DocketNo. 28562
StatusPublished
Cited by1 cases

This text of 49 Ct. Cl. 172 (Toomey Bros. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Toomey Bros. v. United States, 49 Ct. Cl. 172, 1914 U.S. Ct. Cl. LEXIS 302, 1914 WL 1399 (cc 1914).

Opinion

ÁTKINSON, Judge,

delivered tbe opinion of the court:

The plaintiff company sues the United States to recover the sum of $39,938.54 growing out of the construction of a Government lighthouse at Point No Point, on the Patuxent Biver near its junction with the Chesapeake Bay in the State of Maryland.

On January 2, 1902, claimant company entered into a written contract with the United States, through Lieut. Col. W. A. Jones, engineer of the fifth lighthouse district, to furnish all the materials, labor, etc., necessary to completely construct the above-mentioned lighthouse within the period of one year for the sum of $38,880.

The specifications required the lower part of the structure to consist of a square wooden caisson, provided with a working chamber and air shaft. On the roof of this caisson was to rest a cast-iron foundation cylinder, trumpet-shaped on top, which, after being sunk to the proper depth below the bottom of the bay, was to be filled as follows: The working chamber of the caisson and a part of the air shaft with concrete, the four segmental parts of the foundation cylinder with sand and large stones, and the rest of the cylinder with concrete, except the spaces for cisterns and cellar. The caisson, after being moored over the correct place, the one staked out by the Lighthouse Board, was to be lowered by gradually extending the cylinder and the air shaft in the height and filling in with concrete, in manner and in detail described at length in the specifications.

The plaintiff company constructed a pier on piles extending out a considerable distance into the Patuxent River, where the lighthouse was to be erected, and early in April, 1903, the caisson was towed from Solomons Island, 18 miles distant, to the place of permanent location on the Patuxent River. When the caisson reached said pier, April 3, the water was very rough, which caused the caisson to tip and turn over, thereby crushing the pier and sending it to the bottom of the river with all the machinery, material, and other appliances thereon belonging to the plaintiff company, causing a loss to it of about $11,108.82, as shown by Finding Y. The caisson drifted down the river and into the Cheaspeake Bay, and [184]*184after an effort extending over two days and one night, by means of a tugboat chartered by plaintiff, it was recovered in a damaged condition and returned to Solomons Island near the point from which it had drifted. On October 22, 1903, after it had been repaired, it was towed back to the lighthouse site and an effort was again made to place it in position. The work of filling the concrete in the caisson was stopped on November 16 by the Government superintendent, because, as he claimed, the concrete was not up to the standard required by the specifications, and a delay of 55 days in the work was occasioned thereby, viz, from November 16, 1903, to January 11, 1904. On said latter date Lieut. Col. W. A. Jones, engineer in charge, visited the site of the work, approved the concrete, although he stated that it was not fully up to the required standard, and accordingly allowed the work to proceed.

It was for a time believed by the contractors, that the caisson could be put in place without the aid of a pier, but during the 55 days’ delay occasioned by the rejection of the cement referred to above, a new and stronger pier was constructed; and, unfortunately for the contractors, it was, on February 14, 1904, carried away by a flood of water and ice in the Patuxent River, occasioning an additional loss to the plaintiff company of about $4,550, as set forth in Finding VII. It is contended by plaintiff that the refusal of the Government inspector to allow the use of concrete, which it maintains was in accordance with the specifications, causing the delay of 55 days in the prosecution of the work, as herein-before stated, resulted in an actual loss to it of $9,800.

The contract required the completion of the work in 12 months, and it is apparent that under ordinary circumstances and conditions that period of time would have been sufficient. The following provisions, however, were inserted in the contract to provide for the unforseen:

“Provided, however, that if the party (or parties) of the first part shall by freshets, ice, or other force or violence of the elements, and by no fault of their own, be prevented either from commencing or completing the work or delivering the materials at the time agreed upon in this contract, [185]*185such additional time may, in writing, be allowed him or them for such commencement or completion as, in the judgment of the party of the second part, or his successors, shall be just and reasonable, any additional expense incurred by the United States on account of inspection or otherwise during the extension to be deducted from the contract price of the work.
“It is further understood and agreed that in case of failure on the part of the party of the first part to complete this contract as specified and agreed upon, that the said United States shall have the right to recover any or all damages incurred by reason of said failure by the party of the first part, and shall also have the right to recover whatever sums may be expended by the party of the second part in completing the said contract in excess of the price herein stipulated to be paid to the party of the first part for completing the same.”

It is further shown by the findings that after the brealdng down of the first pier, plaintiff company saw the impossibility of completing the contract within the contract period of one year, and it thereupon made a request in writing, followed by additional verbal requests, for an extension; but these requests were denied by the defendants and the completion of the contract under its terms was peremptorily demanded by the engineer in charge. The work, however, went on, and it was finished one year and four months after the period for its completion fixed by the contract. It is, therefore, contended by plaintiff’s counsel that inasmuch as the Government did not extend the time provided by the contract, it did not possess the lawful right to charge against plaintiff inspection charges during the delay in completing the work. This, it contends, would follow, because there are no provisions in the contract or specifications giving the right to deduct such costs upon failure to complete the contract within the time required by its terms. On the other hand, counsel for the United States insists that inasmuch as plaintiff was allowed to go on and complete its contract, although not authorized in writing so to do, yet under the provision of the contract that any additional expense incurred by the United States on account of inspection or otherwise shall be deducted from the contract price of the work,” it was thereby authorized to charge to plaintiff the services of the inspector during the [186]*186one year and four months overtime period in completing the lighthouse.

This case, in its most important feature, is identical with the, case of United States v. Gleason, 175 U. S., 588. That case contained the same provision as to granting an extension of time on account of ice, floods, etc., as we find in the contract involved in the case at bar.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re the Appeal of Lord
25 Haw. 76 (Hawaii Supreme Court, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
49 Ct. Cl. 172, 1914 U.S. Ct. Cl. LEXIS 302, 1914 WL 1399, Counsel Stack Legal Research, https://law.counselstack.com/opinion/toomey-bros-v-united-states-cc-1914.