Tommy L. Griffin Plumbing & Heating Co. v. Jordan, Jones & Goulding, Inc.

570 S.E.2d 197, 351 S.C. 459, 2002 S.C. App. LEXIS 114
CourtCourt of Appeals of South Carolina
DecidedJune 27, 2002
Docket3527
StatusPublished
Cited by6 cases

This text of 570 S.E.2d 197 (Tommy L. Griffin Plumbing & Heating Co. v. Jordan, Jones & Goulding, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tommy L. Griffin Plumbing & Heating Co. v. Jordan, Jones & Goulding, Inc., 570 S.E.2d 197, 351 S.C. 459, 2002 S.C. App. LEXIS 114 (S.C. Ct. App. 2002).

Opinion

CURETON, J.:

Tommy L. Griffin Plumbing and Heating Co. (Griffin) brought this action seeking to recover money damages from Jordan, Jones & Goulding, Inc. (JJ & G) for professional negligence and breach of implied warranty. The circuit court granted JJ & G’s motion for summary judgment. Griffin appeals. We affirm.

FACTS AND PROCEDURAL HISTORY

This case has a long and involved procedural history. In the spring of 1987, Griffin entered into a contract with the Commissioners of Public Works for the City of Charleston (CPW) to construct the second phase of the Peninsula Water Trunk Main project (PEN II). CPW hired JJ & G to serve as the design engineer for the project and to administer and supervise the PEN II contract between Griffin and CPW. In *464 1992, Griffin filed a complaint alleging it was damaged by JJ & G’s actions relating to its administration of the contract and sought to recover damages from JJ & G under several different causes of action. JJ & G moved for summary judgment on all of Griffin’s causes of action. The circuit court granted JJ & G’s summary judgment motion and Griffin appealed to the supreme court which reinstated two of Griffin’s causes of actions: malpractice based on professional negligence, and breach of implied warranty. Griffin Plumbing & Heating Co. v. Jordan, Jones & Goulding, 320 S.C. 49, 57, 463 S.E.2d 85, 89 (1995).

Griffin filed its second amended complaint on June 20, 1996, and a third amended complaint on April 21, 1998. Griffin’s third amended complaint alleged it was entitled to recover damages based upon JJ & G’s negligence in the supervision, design, and administration of the contract and/or from a breach of implied warranty to provide suitable design plans. Griffin stated nine instances where JJ & G harmed it. JJ & G moved for summary judgment on seven of the nine claims. The circuit court granted JJ & G’s motion for partial summary judgment on August 17,1999.

Griffin’s seven claims, dismissed pursuant to JJ & G’s summary judgment motion, are as follows: (1) damages based on JJ & G’s interference with Griffin’s ability to bid on future projects resulting from a derogatory letter JJ & G mailed to Griffin’s bonding company, which allegedly resulted in a restriction of Griffin’s bonding capability; (2) costs incurred due to a negligent design that failed to show a conflict with an existing sewer line at the McMillan Avenue Tunnel, which caused a delay in redesigning plans, resulting in additional dewatering costs; (3) damages due to the delayed awarding of the contract to Griffin, because of JJ & G’s failure to become aware of an asbestos fill in the water tunnels at the Fiddler Creek crossing; (4) costs incurred by Griffin because JJ & G took one year to redesign around the asbestos fill area at Fiddler Creek Crossing; (5) costs incurred when JJ & G required incremental pipe testing, instead of testing the entire pipeline at one time; (6) costs incurred when JJ & G stopped Griffin from working for thirty-four days due to safety concerns at the St. Johns Avenue site; and (7) damages incurred in consultant costs because Griffin was required to get assis *465 tance in the collection of funds from CPW because of delays caused, and unsuitable design plans submitted, by JJ & G.

The circuit court denied Griffin’s motion for reconsideration on March 28, 2000. The two parties entered into a consent order disposing of the two remaining claims on May 30, 2000. Griffin appeals the circuit court’s grant of partial summary judgment.

LAW/ANALYSIS

I. Timeliness of Appeal

JJ & G contends Griffin’s appeal should be dismissed because the notice of appeal was untimely served. We disagree.

Griffin’s complaint alleged nine causes of actions against JJ & G. JJ & G moved for summary judgment on seven of the nine claims. After a hearing, the trial court granted JJ & G’s motion for partial summary judgment. The order states, in part:

THEREFORE, the Motion for Partial Summary Judgment of Defendant Jordan, Jones & Goulding, Inc. as to the seven enumerated claims is hereby GRANTED. The Court finds that there is no just reason for delay, and directs entry of judgment as to Plaintiffs seven claims, identified above.

Griffin’s motion for reconsideration was denied and Griffin did not immediately appeal. Several months later, after the remaining two claims were dismissed without prejudice, Griffin served a notice of appeal challenging the partial summary judgment order.

JJ & G argues the appeal should be dismissed because the trial court essentially certified the order pursuant to Rule 54(b), SCRCP, and Griffin did not timely serve a notice of appeal pursuant to Rule 203(b)(1), SCACR. JJ & G cites federal law interpreting the federal counterpart to Rule 54, and Link v. School District of Pickens County, 302 S.C. 1, 393 S.E.2d 176 (1990) in support of its position.

Griffin argues JJ & G did not move for certification under Rule 54(b), and the trial court’s order does not cite the rule. Griffin also contends even if the language in the order consti *466 tutes certification under Rule 54(b), the appeal is timely pursuant to S.C.Code Ann. § 14-3-330 (1976).

Rule 54(b), SCRCP, provides:

When more than one claim for relief is presented in an action, ... the court may direct the entry of a final judgment as to one or more but fewer than all of the claims ... only upon an express determination that there is no just reason for delay and upon an express direction for the entry of judgment. In the absence of such determination and direction, any order ... however designated, which adjudicates fewer than all the claims ... shall not terminate the action as to any of the claims or parties, and the order ... is subject to revision at any time before the entry of judgment adjudicating all the claims and the rights and liabilities of all the parties.

An appeal following a Rule 54(b) certification is the exception rather than the rule. 10 Charles Alan Wright, Arthur R. Miller & Mary Kay Kane, Federal Practice and Procedure 2654 (3d ed.1998). The rule does not require certification and if the trial court chooses to certify the judgment, it must do so in a definite, unmistakable manner. Id.

A certification under the federal rule, Rule 54(b), FRCP, which is virtually identical to our rule, must satisfy three prerequisites for the appellate court to obtain jurisdiction prior to adjudication of all claims in the action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kevin Hollinshead, Sr. v. Thomas Bell
Court of Appeals of South Carolina, 2025
Bank of North Carolina v. Bouscaren
72 F. Supp. 3d 621 (D. South Carolina, 2014)
Ashenfelder v. City of Georgetown
698 S.E.2d 856 (Court of Appeals of South Carolina, 2010)
Rashford v. Christopher
Court of Appeals of South Carolina, 2009
Spires v. ACCELERATION NATIONAL INSURANCE COMPANY
417 F. Supp. 2d 750 (D. South Carolina, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
570 S.E.2d 197, 351 S.C. 459, 2002 S.C. App. LEXIS 114, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tommy-l-griffin-plumbing-heating-co-v-jordan-jones-goulding-inc-scctapp-2002.