Tom Wright Construction, LLC D/B/A Built Wright Construction v. Bolton Steel Erectors

CourtCourt of Appeals of Texas
DecidedJune 23, 2022
Docket14-20-00649-CV
StatusPublished

This text of Tom Wright Construction, LLC D/B/A Built Wright Construction v. Bolton Steel Erectors (Tom Wright Construction, LLC D/B/A Built Wright Construction v. Bolton Steel Erectors) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tom Wright Construction, LLC D/B/A Built Wright Construction v. Bolton Steel Erectors, (Tex. Ct. App. 2022).

Opinion

Affirmed and Memorandum Opinion filed June 23, 2022.

In The

Fourteenth Court of Appeals

NO. 14-20-00649-CV

TOM WRIGHT CONSTRUCTION, LLC D/B/A BUILT WRIGHT CONSTRUCTION, Appellant V.

BOLTON STEEL ERECTORS, Appellee

On Appeal from the 506th Judicial District Court Waller County, Texas Trial Court Cause No. 17-02-24157

MEMORANDUM OPINION

Appellant Tom Wright Construction, LLC d/b/a Built Wright Construction (“BWC”) appeals a judgment entered in favor of appellee Bolton Steel Erectors (“Bolton Steel”). By two issues, BWC argues the trial court erred in entering judgment in favor of Bolton Steel because (1) the arbitrator’s award was untimely and not briefly reasoned, and (2) the parties’ agreement did not authorize the recovery of attorney’s fees. We affirm. I. BACKGROUND

In 2016, Texas Prairie View A&M University contracted Skanska USA Building, Inc. (“Skanska”) to perform work at the University’s football stadium. Skanska hired BWC as its subcontractor, and BWC subcontracted all of its work and obligations to Bolton Steel by executing a written contract on June 17, 2015. The subcontract between BWC and Bolton Steel contained an arbitration agreement that, in the event of a dispute, gave BWC the sole right to invoke binding arbitration and provided that the issues arbitrated “shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect, unless the parties mutually agree otherwise.”

In February 2017, Bolton Steel filed suit against BWC, among others, asserting claims for breach of contract, to collect on BWC’s payment bonds, and recovery of attorney’s fees under section 38.001 of the Civil Practice and Remedies Code and Texas Government Code Chapter 2253. See Tex. Civ. Prac. & Rem. Code Ann. § 38.001; Tex. Gov’t Code Ann. § 2253.073. BWC filed an answer, moved to compel arbitration, and requested attorney’s fees pursuant to Texas Government Code § 2253.075 and chapter 38 of the Civil Practice and Remedies Code. See Tex. Civ. Prac. & Rem. Code Ann. § 38.001; Tex. Gov’t Code Ann. § 2253.075.1 Pursuant to the parties’ agreement, the trial court entered an order compelling arbitration.

On July 1, 2019, the arbitrator entered a scheduling order, which provided in relevant part:

1 Section 2253.075 of the Government Code provides “A third party to whom a claim is assigned is in the same position as a payment bond beneficiary if notice is given as required by this chapter.” Tex. Gov’t Code Ann. § 2253.075.

2 Award: Within thirty (30) days following the final hearing and post- hearing briefing, if any, the Arbitrator shall prepare a briefly reasoned award. Except as indicated otherwise above, these deadlines and dates are final unless the parties specifically agree otherwise, or unless the Arbitrator modifies them in his discretion after good cause is shown.

The final arbitration hearing before the arbitrator occurred between November 18– 22, 2019, and post-hearing briefing was complete on February 13, 2020. On June 16, 2020, the arbitrator issued his final award. The arbitrator granted Bolton Steel’s breach-of-contract claim against BWC and determined that the adjusted contract amount was $937,137.00; that BWC was entitled to $386,392.65 in back charges; and that the remainder that BWC owed Bolton Steel under the contract was $359,791.35. The arbitrator also granted Bolton Steel $216,621.12 in attorney’s fees, with an additional $10,000 to be awarded in the event of any challenge to the award. Finally, the arbitrator denied BWC’s claims for breach of contract, fraud, tortious interference with a contract, and attorney’s fees.

On June 26, 2020, BWC filed a motion asserting that the award was insufficiently reasoned, requesting from the arbitrator further reasoning for the award. On June 29, the arbitrator requested input from the parties, and on July 22, the arbitrator informed the parties that he would “revisit the Award and provide additional reasoning.” On July 31, BWC filed an objection to the length of time the arbitrator was spending on the award, asserting that the arbitrator failed to timely deliver a briefly reasoned award. BWC avers the delay caused BWC to incur additional costs associated with payment of an additional bond premium and litigation “on two fronts.” On August 3, 2022, the arbitrator issued an amended award and a second amended final arbitration award, which provided for the same relief but included additional reasoning for the award.

3 Bolton Steel then filed a motion with the trial court to confirm the second amended arbitration award; BWC filed a motion to vacate the award. On August 19, 2020, the trial court confirmed the arbitrator’s second amended final arbitration award, entered a judgment in favor of Bolton Steel, and denied BWC’s request for vacatur. This appeal followed.

II. STANDARD OF REVIEW

We review de novo the trial court’s decision to confirm or vacate an arbitration award. D.R. Horton-Tex., Ltd v. Bernhard, 423 S.W.3d 532, 534–35 (Tex. App.—Houston [14th Dist.] 2014, pet. denied). Texas law clearly favors arbitration, and as a result, judicial review is extraordinarily narrow. Broemer v. Hous. Lawyer Referral Serv., 407 S.W.3d 477, 480 (Tex. App.—Houston [14th Dist.] 2013, no pet.).

III. TIMELINESS & REASONING OF AWARD

In its first issue, BWC argues the trial court erred by refusing to vacate the arbitration award. BWC asserts that the arbitrator’s award failed to provide the reasoning required and was untimely.

A. APPLICABLE LAW

The parties agree that the Texas Arbitration Act applies. The TAA provides that an arbitrator shall make the award (1) within the time established by the agreement to arbitrate; or (2) if a time is not established by the agreement, then within the time ordered by the court on application of a party. Tex. Civ. Prac. & Rem. Code Ann. § 171.053(c). The TAA further provides that “[a] party waives the objection that an award was not made within the time required unless the party notifies the arbitrators of the objection before the delivery of the award to that party.” Id. § 171.053(e).

4 An arbitrator may modify or correct an award based on the grounds listed in § 171.091 or to clarify an award.2 Id. § 171.054(a); see id. § 171.091(a). As relevant to this case, a modification may be made only on application of a party. See id. §§ 171.054(b)(1), 171.091(b). A party seeking to have the arbitrator modify the award under § 171.091 must make such a request no later than twenty days after the date the award is delivered. Id. § 171.054(c); see Teleometrics Int’l v. Hall, 922 S.W.2d 189, 192 (Tex. App.—Houston [1st Dist.] 1995, writ denied).

1. Timeliness

Here, BWC objected to the timeliness of the award after the arbitrator issued its award but before the arbitrator issued its amended awards; we therefore conclude that BWC waived its complaint regarding the timeliness of the arbitrator’s original award. See Tex. Civ. Prac. & Rem. Code Ann.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Tom Wright Construction, LLC D/B/A Built Wright Construction v. Bolton Steel Erectors, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tom-wright-construction-llc-dba-built-wright-construction-v-bolton-texapp-2022.