TOCCI BUILDING CORPORATION v. IRIV PARTNERS, LLC, & another (and a companion case ).

190 N.E.3d 1077, 101 Mass. App. Ct. 133
CourtMassachusetts Appeals Court
DecidedJune 7, 2022
StatusPublished
Cited by8 cases

This text of 190 N.E.3d 1077 (TOCCI BUILDING CORPORATION v. IRIV PARTNERS, LLC, & another (and a companion case ).) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
TOCCI BUILDING CORPORATION v. IRIV PARTNERS, LLC, & another (and a companion case )., 190 N.E.3d 1077, 101 Mass. App. Ct. 133 (Mass. Ct. App. 2022).

Opinion

TOCCI BUILDING CORPORATION vs. IRIV PARTNERS, LLC, 101 Mass. App. Ct. 133

TOCCI BUILDING CORPORATION vs. IRIV PARTNERS, LLC, & another [Note 1] (and a companion case [Note 2]).

101 Mass. App. Ct. 133

February 1, 2022 - June 7, 2022

Court Below: Superior Court, Suffolk County

Present: Rubin, Kinder, & Ditkoff, JJ.

Amended July 1, 2022.

Nos. 21-P-393 & 21-P-733.

Contract, Construction contract, Performance and breach. Practice, Civil, Summary judgment, Notice of appeal.

A Superior Court judge properly granted summary judgment for the plaintiff construction contractor and against the defendants, a manager and property owner, on the plaintiff's claims that periodic progress payments on each of seven applications it submitted had been in whole or in part withheld wrongfully under a contract subject to the Prompt Payment Act, G. L. c. 149, § 29E (act), where, given the defendants' failure to issue a rejection effective under the act containing a certification that the rejection was made in good faith prior to the date payment was due (i.e., thirty days after submission of the application), the applications were thereby deemed approved by operation of law and were required to be paid [137-142]; further, the judge properly ordered the entry of separate and final judgment, where the point of the act was that such payments may not be withheld, even on valid grounds that they were not due because of a breach of contract, unless a timely rejection was made in compliance with the statute [142-143].


Civil action commenced in the Superior Court Department on February 6, 2019.

A motion for summary judgment was heard by Michael D. Ricciuti, J., and the entry of separate and final judgment was ordered by him.

A motion for enlargement of time to file a notice of appeal was considered in the Appeals Court by Sullivan, J., and a motion for reconsideration was considered by her.

Roger L. Smerage & Bradley L. Croft (Kirk J. McCormick also present) for the plaintiff.

Michael B. Donahue (Adam M. Santeusanio also present) for the defendants.

Page 134

Joel Lewin, Christopher W. Morog, Seth M. Pasakarnis, & Alexandra Gordon, for Construction Industries of Massachusetts, Inc., & another, amici curiae, submitted a brief.

Joseph A. Barra, for Associated Subcontractors of Massachusetts, Inc., amicus curiae, submitted a brief.


RUBIN, J. This case requires us to construe for the first time the provisions of the Prompt Payment Act, G. L. c. 149, § 29E (the act or statute). That statute applies to certain private contracts for construction with respect to projects for the erection, alteration, repair, or removal of buildings or structures, or for other improvement to real property, where the "contract with the project owner has an original contract price of $3,000,000 or more." [Note 3] G. L. c. 149, § 29E (a).

Designed to ensure the prompt payment of, or resolution of disputes about, invoices for periodic payment made by contractors during the course of work on such projects, the act provides, "Every contract for construction shall provide reasonable time periods within which: (i) a person seeking payment under the contract shall submit written applications for periodic progress payments; (ii) the person receiving the application shall approve or reject the application, whether in whole or in part; and (iii) the person approving the application shall pay the amount approved. The time periods for each application for a periodic progress payment shall not exceed: (i) for submission, [thirty] days . . .; (ii) for approval or rejection, [fifteen] days after submission . . .; and (iii) for payment, [forty-five] days after approval." G. L. c. 149, § 29E (c).

If, in response to a proper application for periodic progress payment, the owner does not provide approval or rejection, in whole or in part, within fifteen days (or a shorter period of time if the contract so provides), the statute provides that the application will "be deemed to be approved unless it is rejected before the date payment is due." G. L. c. 149, § 29E (c). The statute specifies that "[a] rejection of an application for a periodic progress payment, whether in whole or in part, shall be made in writing and shall include an explanation of the factual and contractual basis for the rejection and shall be certified as made in good faith." Id. It also provides that any "provision in a contract

Page 135

for construction which purports to waive or limit any provisions of this section shall be void and unenforceable."

As the amicus brief of the Associated Subcontractors of Massachusetts, Inc., explains, "By securing prompt payment from upstream funding sources, [the act] ensures that those who perform the work and pay all costs for labor and materials will be promptly compensated without the need to engage in costly legal battles on every project."

Of course, submission of a proper periodic request for payment does not require its approval. But the statute provides that "[a] rejection of an application for a periodic progress payment shall be subject to the applicable dispute resolution procedure [in the contract]. A provision in the contract which requires a party to delay commencement of the procedure until a date later than [sixty] days after the rejection shall be void and unenforceable." G. L. c. 149, § 29E (c).

Background. This case involves seven applications for periodic progress payments submitted by the plaintiff Tocci Building Corporation (Tocci), to the defendant IRIV Partners, LLC (IRIV), under a contract subject to the act, that were, in whole or in part, not paid on the date payment would have been due under the contract had they been approved, and which remained unpaid after completion of the project. The contract was between "[IRIV] Partners, LLC Manager for Boston Harbor Industrial Development, LLC," denominated the "Owner" in the contract, and "Tocci Building Corporation," denominated "Constructor," for work to be done at a project at 645 Summer Street in the South Boston section of Boston. The first page of the contract states that the "Property Owner" is "Boston Harbor Industrial Development, LLC." The signature page of the contract contains one line for "Manager: [IRIV] Partners, LLC," on which the signature of P. Andrew Pappas appears, followed by a line indicating that his title is "Manager," and one line for "Constructor: Tocci Building Corporation," on which the signature of Anthony Sandonato appears, followed by a line indicating that his title is "Executive Vice President."

Following the completion of the project, the plaintiff, Tocci, sued the defendants, IRIV and Boston Harbor Industrial Development, LLC (BHID), for breach of contract, alleging that they had wrongfully withheld the periodic payments, as well as breach of the implied covenant of good faith and fair dealing, fraud, "unjust enrichment/quantum meruit," violation of G. L. c. 93A, and foreclosure of a mechanic's lien pursuant to G. L. c. 254.

Page 136

The defendants filed counterclaims for breach of contract, breach of the implied covenant of good faith and fair dealing, negligent misrepresentation, fraud, negligence, unfair and deceptive conduct under G. L. c.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
190 N.E.3d 1077, 101 Mass. App. Ct. 133, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tocci-building-corporation-v-iriv-partners-llc-another-and-a-massappct-2022.