J.C. Cannistraro, LLC v. Columbia Construction Co.

CourtMassachusetts Supreme Judicial Court
DecidedJune 26, 2026
DocketSJC 13819
StatusPublished

This text of J.C. Cannistraro, LLC v. Columbia Construction Co. (J.C. Cannistraro, LLC v. Columbia Construction Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.C. Cannistraro, LLC v. Columbia Construction Co., (Mass. 2026).

Opinion

NOTICE: All slip opinions and orders are subject to formal revision and are superseded by the advance sheets and bound volumes of the Official Reports. If you find a typographical error or other formal error, please notify the Reporter of Decisions, Supreme Judicial Court, John Adams Courthouse, 1 Pemberton Square, Suite 2500, Boston, MA, 02108-1750; (617) 557- 1030; SJCReporter@sjc.state.ma.us

SJC-13819

J.C. CANNISTRARO, LLC vs. COLUMBIA CONSTRUCTION CO. & another.1

Norfolk. February 2, 2026. – June 26, 2026.

Present: Budd, C.J., Gaziano, Kafker, Wendlandt, Georges, Dewar, & Wolohojian, JJ.

Arbitration, Authority of arbitrator, Confirmation of award. Massachusetts Arbitration Act. Public Policy. Contract, Construction contract, Subcontract. Payment.

Civil action commenced in the Superior Court Department on August 3, 2020.

Motions to vacate and to confirm an arbitration award were heard by Keren E. Goldenberg, J.

The Supreme Judicial Court granted an application for direct appellate review.

Jeff D. Bernarducci (Seth M. Pasakarnis & Lindsey K.P. Black also present) for Columbia Construction Co. J. Nathan Cole (Ross C. Wecker also present) for the plaintiff. The following submitted briefs for amici curiae: Robert W. Stetson for Real Estate Bar Association for Massachusetts, Inc., & another.

1 Travelers Casualty & Surety Company of America. 2

David E. Wilson for Associated Subcontractors of Massachusetts, Inc. Kenneth E. Rubinstein, Nicholas A. Dube, & Michael J. Amato for Associated General Contractors of Massachusetts & others. Joseph A. Barra for Electrical Contractors Association of Greater Boston, Inc., & others.

WOLOHOJIAN, J. The question is whether an arbitrator

exceeded his authority by awarding recoupment of payments to a

general contractor, Columbia Construction Co. (Columbia), that

(a) did not timely certify its rejection of invoices submitted

by a subcontractor, J.C. Cannistraro, LLC (Cannistraro), and (b)

asserted defenses to payment before paying the invoices. See

Business Interiors Floor Covering Business Trust v. Graycor

Constr. Co., 494 Mass. 216, 225 (2024) (Graycor) (establishing

payment prerequisite where contractor does not reject invoices

in conformity with requirements of prompt pay act, G. L. c. 149,

§ 29E). We conclude that the arbitrator's award was within his

authority, and accordingly reverse the judgment of a Superior

Court judge vacating the arbitration award.2

2 We acknowledge the amicus briefs submitted by Real Estate Bar Association for Massachusetts, Inc., and the Abstract Club; Electrical Contractors Association of Greater Boston, Inc., Boston Roofing Contractors Association, Inc., Painting & Finishing Employers Association of New England, Inc., and Glass Employers Association of New England, Inc.; Associated Subcontractors of Massachusetts, Inc.; and Associated General Contractors of Massachusetts, Construction Industries of Massachusetts, Inc., and Utility Contractors' Association of New England, Inc. 3

Background.3 On February 3, 2017, Columbia entered into a

contract for the construction and renovation of an office and

manufacturing facility located in Walpole (prime contract). The

prime contract was a "contract for construction" as defined in

G. L. c. 149, § 29E (a), and was therefore subject to the

provisions of the prompt pay act.

Columbia then entered into two subcontracts with

Cannistraro, both of which contained the following arbitration

provision:

"At the sole election of [Columbia], any disputes shall be resolved by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association."

Cannistraro thereafter proceeded to perform work under both

subcontracts and submitted regular monthly requisitions for

payment.

In addition, in January 2020, Cannistraro submitted change

order requests under each subcontract. Columbia timely rejected

those requests and conveyed its reasons for doing so.

Approximately two months later, Cannistraro submitted

applications and certificates for payment for the change orders

3 We draw the facts, which are undisputed, from the arbitrator's findings. The arbitrator's findings were contained in his interim order on the parties' cross motions for summary judgment, his ruling on Columbia's motion for leave to amend its response to the arbitration demand, his ruling on Cannistraro's second motion for summary judgment, and his final award. 4

(collectively, invoices). Although Columbia timely rejected the

invoices, it failed to include the certification required by the

prompt pay act that its rejections were made in good faith.4 See

G. L. c. 149, § 29E (d).5 Columbia did not pay the amounts

invoiced.

Procedural history. Cannistraro filed suit in the Superior

Court seeking damages in the amount of the invoices. Among

other things, Cannistraro's amended complaint asserted a claim

for violation of the prompt pay act, alleging that Columbia

failed to make payments in accordance with the requirements of

the statute.6

4 Several months later, on September 22, 2020, Columbia provided certification that its rejections of the invoices were made in good faith. But those certifications were not made within the time allowed by the prompt pay act. See G. L. c. 149, § 29E (d).

5 The prompt pay act has two provisions concerning certification of good faith rejection: one for progress payments, see G. L. c. 149, § 29E (c), and one for change orders, see G. L. c. 149, § 29E (d). Because this case concerns invoices for change orders, it falls under the latter, but both provisions contain the same requirement that a rejection of a request for payment "shall be made in writing," "shall include an explanation of the factual and contractual basis for the rejection and shall be certified as made in good faith." G. L. c. 149, §§ 29E (c), (d).

6 The amended complaint also asserted claims for breach of contract, unjust enrichment, promissory estoppel, enforcement of mechanic's lien bonds under G. L. c. 254, § 14, and violation of G. L. c. 93A, § 11. 5

Columbia answered, denied liability, and asserted various

affirmative defenses.7 In addition, Columbia moved to compel

arbitration. That motion was allowed, and the case thereafter

proceeded to arbitration under the American Arbitration

Association's Construction Industry Arbitration Rules (AAA

Construction Rules), as required by the subcontracts.8

Once in arbitration, and after discovery, the parties

cross-moved for summary judgment. Those cross motions raised,

among other things, the question of what, if any, legal

consequences were to flow from the fact that Columbia had not

timely certified that its rejections of the invoices were made

in good faith. The arbitrator, knowing that this legal issue

was then pending before the Appeals Court in Tocci Bldg. Corp.

v. IRIV Partners, LLC, 101 Mass. App. Ct. 133 (2022) (Tocci),

deferred ruling on the cross motions until the Appeals Court

issued its decision in that case.

The Appeals Court in Tocci concluded that the good faith

certification requirement was "an essential component of the

7 Columbia's affirmative defenses included that Cannistraro had committed a breach of the terms of the subcontract, that it had willfully and knowingly inflated the amount of its mechanic's lien, and that its claims were barred by fraud.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Lawrence v. Falzarano
402 N.E.2d 1017 (Massachusetts Supreme Judicial Court, 1980)
CONCERNED MIN. EDUCATORS v. Sch. Comm. of Worcester
466 N.E.2d 114 (Massachusetts Supreme Judicial Court, 1984)
City of Marlborough v. Cybulski, Ohnemus & Associates, Inc.
346 N.E.2d 716 (Massachusetts Supreme Judicial Court, 1976)
Beacon Towers Condominium Trust v. Alex
42 N.E.3d 1144 (Massachusetts Supreme Judicial Court, 2016)
Katz, Nannis & Solomon, P.C. v. Levine
46 N.E.3d 541 (Massachusetts Supreme Judicial Court, 2016)
City of Pittsfield v. Local 447 International Brotherhood of Police Officers
107 N.E.3d 1137 (Massachusetts Supreme Judicial Court, 2018)
Massachusetts Bay Transportation Authority v. Local 589, Amalgamated Transit Union
546 N.E.2d 135 (Massachusetts Supreme Judicial Court, 1989)
Plymouth-Carver Regional School District v. J. Farmer & Co.
553 N.E.2d 1284 (Massachusetts Supreme Judicial Court, 1990)
Commonwealth v. Massachusetts Organization of State Engineers & Scientists
671 N.E.2d 1222 (Massachusetts Supreme Judicial Court, 1996)
Bureau of Special Investigations v. Coalition of Public Safety
722 N.E.2d 441 (Massachusetts Supreme Judicial Court, 2000)
City of Lynn v. Thompson
754 N.E.2d 54 (Massachusetts Supreme Judicial Court, 2001)
School District of Beverly v. Geller
755 N.E.2d 1241 (Massachusetts Supreme Judicial Court, 2001)
City of Boston v. Boston Police Patrolmen's Ass'n
824 N.E.2d 855 (Massachusetts Supreme Judicial Court, 2005)
Superadio Ltd. Partnership v. Winstar Radio Productions, LLC
844 N.E.2d 246 (Massachusetts Supreme Judicial Court, 2006)
City of Boston v. Boston Police Patrolmen's Ass'n
907 N.E.2d 241 (Massachusetts Appeals Court, 2009)
Massachusetts Board of Higher Education v. Massachusetts Teachers Ass'n
943 N.E.2d 485 (Massachusetts Appeals Court, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
J.C. Cannistraro, LLC v. Columbia Construction Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/jc-cannistraro-llc-v-columbia-construction-co-mass-2026.