Ætna Construction Co. v. United States

46 Ct. Cl. 113, 1911 U.S. Ct. Cl. LEXIS 126
CourtUnited States Court of Claims
DecidedFebruary 13, 1911
DocketNo. 27,280
StatusPublished
Cited by4 cases

This text of 46 Ct. Cl. 113 (Ætna Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ætna Construction Co. v. United States, 46 Ct. Cl. 113, 1911 U.S. Ct. Cl. LEXIS 126 (cc 1911).

Opinion

Atkinson, J.,

delivered the opinion of the court:

This is a suit arising under a contract to build a 500-foot dam (No. 4) on the Ohio River, on the unit-price plan, all [124]*124materials to be furnished by the contractor except the cement. The original contract was executed July 6, 1901, and a supplemental agreement changing the size of the cofferdam and fixing new prices for the changed conditions was executed May 3, 1902. On May 5, 1904, a second supplemental agreement was entered into of which the part material to the case before us reads as follows:

“That the contract dated July 6, 1901, and supplemental contract dated May 3, 1902, for constructing chanoine dam at Dam No. 4, Ohio River, after the completion of the first 250-foot section of the dam, including the removal by the contractor, at his own expense, of the cofferdam on or before June 1, 1904, to the satisfaction of the engineer will be and hereby is abrogated by mutual consent without prejudice to either party.”

The original contract provided that the Government engineer in charge of the work should fix the length of the dam to be completed the first year, so as not to obstruct the navigation of the river, and the remainder of the dam was to be left for the next year’s work. Work was to begin within 60 days after the approval of the contract, and the contract work was to be completed by November 30, 1902; but allowances were to be made for freshets in the river, days in which no work could be done, and all the time between December 1 and April 30 of each year on account of possible rises and ice in the river. The first season’s work resulted in the construction of the greater part of the cofferdam inclosure; but when winter came on, rises in the river washed out the cofferdam and practically rendered useless nearly all the work that had been done. The Government engineers in charge of the work, however, believing that they were at least in part responsible for this loss, the contractor was paid therefor.

Owing to a change in the bed of the river, resulting from scouring by high water, it was decided to change the plan of construction, and a supplemental contract was made and entered into, as before stated, on May 3, 1902, by which the contract period was extended 60 working days. Under this supplemental contract the claimant company proceeded with the execution of the work; but owing to many apparent unavoidable delays it failed to complete the first half of the [125]*125permanent work until November 10, 1903, at which time it had all of the first section of the cofferdam yet to remove, and had remaining only about 22 days of the time allowed for the entire completion of its contract. Claimant company, on August 24, 1903, asked for an extension of 120 working days for the completion of its contract. This request was refused by the Government engineers in charge of the work, .and on August 31,1903, claimant was instructed not to begin the cofferdam construction for the remaining half of the dam. The reasons for this action of the Government engineers were (1) the fact that with the cofferdam for the first half section of the work still standing in the river the construction and existence of the cofferdam for the second section of the work would interfere with the navigation of the river by reducing the navigable pass of the same for such vessels as were engaged in commerce on said river, and (2) they were of the opinion that claimant could not complete the remaining half of the necessary work or any material part thereof before the opening of the winter season or during the remainder of the contract period.

No further work was done by claimant under its supplemental contract outside of the completion of the first half section of the dam covered by the original and supplemental contracts; and on May 5, 1904, the second supplemental agreement was entered into, which provided for the abrogation of the two preceding contracts or agreements, the defendants paying claimant for all work done by it, and agreeing to pay and did pay a price agreed upon between them for certain materials belonging to claimant which remained unused at the works. Upon this basis final settlement between the parties was made.

Claimant in its petition asserts two items of claim arising between the order of August 31, 1903, directing that work should not be commenced on the cofferdam for the remaining half of the dam, and abrogating the contract of May 5, 1904, as follows: For loss of profits on work which might have been completed, $30,688.93, and for expenses incurred between December 15, 1903, and June 1, 1904, the order of suspension of all work under the contract and its abrogation, for maintenance of the work and its plant, $7,004.53; [126]*126and averring further that the abrogation stopped the incur-rence of further obligations or the origin of further rights, but that the clause “ without prejudice to either party ” contained in the abrogation agreement, which we have herein quoted, saved the rights of either party then in existence.

On the 13art of the defendants it is contended: First, that it was the intent and understanding of both parties by the supplemental and abrogating contract of May 5, 1904, that it should provide for and constitute a full and final settlement of the whole controversy between the parties, and relieve each from any liability to the other on account of any of said contracts or contract work; and that the said abrogating contract should therefore be reformed to so state, and the claimant’s petition accordingly be dismissed. Second, that even if said contract were not so re-formed there could be no recovery against the Government, for the reasons (1) that the Government acted throughout within its rights in the premises, and (2) that no loss by the claimant properly chargeable to the Government has been established by the evidence to have resulted from the Government’s action in the matter.

.These opposing contentions between the parties herein directly raise the question as to whether there was mutual mistake in framing the supplemental abrogating contract of May 5, 1904. Was it their understanding and agreement that said contract should constitute a full and conclusive settlement of all matters, rights, and liabilities growing out of the several contracts for the construction of the dam in question; and was the phrase “without prejudice to either party ” used with the understanding and belief that its legal effect would be to finally close all transactions between them, without recourse on either party? This the court has found as a fact was the mutual understanding of both of the parties.

The findings reveal conversations and verbal statements, and the passing of several letters between the parties in interest which show the failure of claimant to perform the work within the time provided by the original contract; the extension of time granted by the first supplemental contract, Avith failure of claimant to comply therewith; negotiations [127]*127which enabled the parties to arrive at a definite conclusion and understanding; and finally the signing of the abrogating contract by which the Government released claimant from all responsibility in connection with the work and upon terms apparently satisfactory to both parties to the contract; which lead us to conclude that were it not for the phrase “ without prejudice to either party ” this ' suit, doubtless, would not have been instituted.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Australia Bank v. United States
63 Fed. Cl. 352 (Federal Claims, 2004)
T.L. Roof & Associates Construction Co. v. United States
38 Cont. Cas. Fed. 76,534 (Federal Claims, 1993)
Klamath & Modoc Tribes v. United States
174 Ct. Cl. 483 (Court of Claims, 1966)
Board of Commissioners v. United States
69 Ct. Cl. 52 (Court of Claims, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
46 Ct. Cl. 113, 1911 U.S. Ct. Cl. LEXIS 126, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tna-construction-co-v-united-states-cc-1911.