Tippetts-Abbett-McCarthy-Stratton v. New York State Thruway Authority

27 Misc. 2d 533, 212 N.Y.S.2d 275, 1961 N.Y. Misc. LEXIS 3240
New York Court of Claims·Decided March 11, 1961·No. Claim No. 34771·Published·Cited by 1 cases

Opinion

Bernard Ryan, P. J.

The contract by which claimant partnership agreed to supervise four certain Thruway construction contracts differs, in its terms, from that which we considered in another suit by this claimant, Claim No. 34769, recently decided. (Tippetts-Abbett-McCarthy-Stratton v. New York State Thruway Auth., 27 Misc 2d 506.)

In Claim No. 34769, the provision was: “ 2. The engineers shall provide to the satisfaction of the chairman or his duly authorized representatives acting through the District Engineer of District No. 8, engineering supervision and inspection services until the completion and final acceptance of the contract ’ \

In this claim, No. 34771, the provision was: “ 2. The engineers shall provide to the satisfaction of the chairman or his duly authorized representatives, engineering supervision and inspection services during the entire term of the contracts as originally established and during such additional periods of time as may be covered by extensions of time granted thereunder, until the completion and final acceptance of the CONTRACTS ’ \

The stipulation that claimant was to provide its services during the additional periods of time, thus expressed, would [534]*534seem, at first hand, to be conclusive herein. There was moreover, in this contract, a further stipulation: 2.1 The engineers are on notice that no additional fee is payable under this agreement for supervision and inspection services performed during additional periods of time covered by extensions of time under the contracts.”

But all contracts must be carried out according to the contemplation of the parties. If performance is delayed through the fault of the one to whom the service is to be rendered, he may be liable to the other for resulting losses incurred by him. This court, upon settled law, has often held that where the State of New York permits a general contractor to fail to progress his operations, and interference with the work of another contractor results, the latter may recover against the State. Without citing cases we recognize that the same principle may be applied to the Thruway Authority. Upon that theory, we directed an award against it in Claim No. 34769. We therein held that inasmuch as the defendant alone had the power to impose sanctions against the general contractor it could not require the claimant to stay on the job" indefinitely without incurring liability for compensation.

Despite the fact that the clauses of the contract between claimant and defendant, above quoted, are, concededly, more restrictive than that which was contained in the contract between the same parties which was in suit in Claim No. 34769, the defendant may be liable herein if any act on its part can be construed as interference with the performance by claimant of this contract.

Claimant was engaged to supervise four projects. The first of the four contracts was known as H. T. 55-4. It was made by the Thruway Authority with the United States Steel Corporation, American Steel and Wire Division, Cyclone Pence Department. It was dated June 17, 1955 and had a completion date of August 1, 1955. But the site of the work was not made available promptly; specifications were changed by the Thruway Authority; work was not commenced until January 25, 1956; then weather conditions were adverse. Extensions were granted to April 1, 1956, to May 15, to June 1, to June 11. Claimant had received a letter of intent dated June 23, 1955. It commenced supervision of the work on January 25, 1956. The work was completed June 8, 1956. It was accepted November 13, 1956.

The second contract was known as H. T. 55-6 and was made with Yonkers Contracting Co., Inc. It was dated September 26, 1955 and had a completion date of July 1, 1956. It provided [535]*535for grading, paving, sodding and seeding in and about a Thruway service area where another contractor, Chiappinelli-Marx, was to build the gasoline station and restaurant. Claimant was engaged to supervise the Yonkers contract but not the Chiappinelli-Marx contract. Yonkers started work on September 25 under claimant’s supervision. When various structural complications developed with respect to building the gasoline station and restaurant which deprived Yonkers of the site of its work, claimant recommended to the Thruway Authority that extensions be granted. In its letter to him claimant requested the Chief Engineer of the Thruway Authority to charge engineering costs against the contractor corporation which caused the delay. Extensions to Yonkers were granted to November 1,1956 and to May 1,1957. The work under the Yonkers contract was completed April 24, 1957. It was accepted May 23, 1957.

The third contract was H. T. 55-7 with Anchor Post Products, Inc. It provided for 12 miles of fencing. It was dated October 13,1955 and had a completion date of January 1, 1956. Claimant received a letter of intent dated October 5, 1955 and accepted the assignment October 19, 1955. It began supervision of the Anchor contract on November 14, 1955. Anchor ran into trouble. Right of way lines were not determined in some instances; there were changes in fence location; changes were ordered in some of the materials originally specified and they were replaced by others. In these circumstances Anchor requested and received extensions to June 15, 1956 and to October 5,1956, on which date its work was completed.

The fourth contract bore two numbers, H. T. 55-9 and S. W. C. 55-1. It was made with D. Alper Co., Inc., and provided for the work of installing guide railing. It was dated November 30,1955 and had a completion date of December 15,1955. Claimant commenced supervision November 29, 1955. In June, 1956 claimant reported that Alper persisted in prosecuting its work at a slow and intermittent pace. In spite of this contractor’s failure to expedite its work, the defendant extended time of completion to April 15,1956, then to August 1,1956. The work was completed August 3, 1956 and accepted September 28, 1956.

Claimant’s contract was dated January 10, 1956 and was signed and acknowledged by the claimant on that day. After approval as to form by the Attorney-General and upon recommendation of the Chief Engineer and of the Director of Finance, both officers of the Thruway Authority, it was signed and acknowledged by the defendant on January 26, 1956. Prior to January 10, 1956, claimant had received a letter of intent covering H. T. 55-4, had begun supervision of H. T. 55-6, of [536]*536H. T. 55-7 and of the contract which bore two numbers, H. T. 55-9 and S. W. C. 55-1. In three of the projects, viz., H. T. 55-4, H. T. 55-7 and H. T. 55-9-S. W. C. 55-1, the completion date for the work prescribed had already passed before claimant signed its contract.

Claimant’s theory of damages is notable. It asserts that it lost money in carrying out the supervision contract anyway but proposes that it should bear all losses incurred up to July 1, 1956. It estimates that its losses to that date were in the net amount of $13,230.66. Its actual costs up to April 24, 1957, when the Yonkers contract was completed, were $40,459.35, according to the testimony. Claimant credits against that sum the gross fee it received under the terms of its contract, its remuneration, on a percentage basis, being $19,391.92, and asserts that it sustained a net estimated loss of $21,067.43. On this basis, claimant asks this court to award it the sum of $7,836.77 ($21,067.43 less $13,230.66).

Free access — add to your briefcase to read the full text and ask questions with AI

Tippetts-Abbett-McCarthy-Stratton v. New York State Thruway Authority, 27 Misc. 2d 533, 212 N.Y.S.2d 275, 1961 N.Y. Misc. LEXIS 3240 (N.Y. Super. Ct. 1961).

27 Misc. 2d 533 (Tippetts-Abbett-McCarthy-Stratton v. New York State Thruway Authority) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

J. A. Jones Construction Co. v. City of Dover
372 A.2d 540 (Superior Court of Delaware, 1977)