Timmins v. Tishman Construction Corp.

9 A.D.3d 62, 777 N.Y.S.2d 458, 2004 N.Y. App. Div. LEXIS 7321
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMay 27, 2004
StatusPublished
Cited by20 cases

This text of 9 A.D.3d 62 (Timmins v. Tishman Construction Corp.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Timmins v. Tishman Construction Corp., 9 A.D.3d 62, 777 N.Y.S.2d 458, 2004 N.Y. App. Div. LEXIS 7321 (N.Y. Ct. App. 2004).

Opinion

OPINION OF THE COURT

Sullivan, J.

This appeal presents the issue of whether a contractor has a duty of care arising out of its contractual obligations so as to impose liability to an injured noncontracting party.

Plaintiff, employed by the New York City Department of Transportation (DOT) as a deckhand assisting passengers entering and exiting the ferry at the Whitehall Ferry Terminal, owned by the City of New York and operated by DOT, sues for personal injuries allegedly sustained while he was pushing open a rolling gate. His wife also seeks damages for her alleged loss of consortium. At the time of the accident, the Terminal, which has an upper and lower level and three slips for docking, was undergoing a substantial renovation.

Defendants Tishman Construction Corp. and Frederick R. Harris, Inc., both doing business as Tishman Harris Whitehall (Tishman/Harris), constituted a joint venture that was the construction manager for the renovation project under a contract with the New York City Economic Development Corporation (EDC). Pursuant to a separate contract with the EDC, defendant Seasons Contracting Corp. was the general contractor for the demolition work.

Since the rebuilding of the Terminal was an extensive and long-term project involving distinct phases of demolition and construction, the work was arranged to avoid any interruption of ferry service between Manhattan and Staten Island. As the contract between Tishman/Harris and the EDC specifically acknowledged: “The provision of uninterrupted 24-hour-a-day ferry service for the 60,000 daily passengers to and from two of the three existing ferry slips is a critical requirement during construction of the Project. A construction phasing plan that [64]*64satisfies this requirement and provides continuity of all major operational and passenger services throughout the construction period will be implemented.”

In July 2000, as part of the phased construction activities arranged to accommodate the demolition of slip No. 3, changes had to be implemented in the flow of passengers to and from the ferries. This included the installation in the summer of 2000 of eight-feet-high rolling chain-link gates to enclose the walkway between slip No. 2 and the passenger waiting room on the upper level of the ferry terminal. Tishman/Harris subcontracted the installation of these gates to defendant Seasons, which, in turn, subcontracted the job to defendant Regional Scaffolding & Hoisting Co., Inc. Regional then subcontracted the fabrication and installation of the gates to defendant Bay-side Fencing, Inc.

According to Bayside’s vice-president, this type of gate, known as a cantilever gate, standard at a construction site, hung from an overhead roller track and was designed to slide open and closed between vertical posts. In order for the gate to be balanced so that it would slide without dragging on the ground, the distance between the vertical posts should be approximately one foot less than one half of the width that the gate is designed to enclose. If, for instance, a cantilever gate is designed to cordon off an area 20 feet wide, the distance between the vertical posts should be approximately nine feet. Shortly after the installation of the gate involved herein, DOT informed Tishman/Harris that it needed to be modified so as to provide a wider opening for passenger traffic. Thereafter, one of the vertical posts was moved four to five feet to widen the opening. A few days after the modification was made, DOT informed Tishman/Harris that the end of the gate was dragging on the ground for a few feet before reaching its fully closed position, a condition that was apparently the result of the relocation of the vertical post, which caused the gate to become unbalanced. The problem was promptly rectified by the addition of footage to the tail end of the gate, which balanced its front end when the gate was in a fully closed position, and a six-inch standard rubber wheel at the front end of the gate. Tishman/Harris and Seasons inspected the gate after the modification, finding it be in good working order, and approved payment to Regional.

Plaintiff claims that he was injured while moving the gate on November 3, 2000. At his deposition, he testified that he was unable to move the gate because it “was broken, dragging on [65]*65the ground,” adding, “There was no wheel at the bottom of the gate where there was supposed to be a wheel.” He testified further that there had been a wheel on the gate when it was installed but that it had been subsequently replaced when it had broken off. Plaintiff claimed there had been no wheel on the gate for approximately two weeks before the accident.

It is uncontroverted that ferry service was provided on an uninterrupted basis from slip No. 2 from the summer of 2000 through the date of the accident and that DOT was in operational control of the upper level of the Terminal, where the gate was located, during this period of time. It is also undisputed that the daily activity reports at the job site, as produced during discovery, confirm that no ongoing demolition or construction work was conducted on the upper level of the Terminal between the installation of the gate during the summer of 2000 and the date of the accident. The Ferry Terminal project contracts of Tishman/Harris and Seasons with EDC do not contain any provision obligating either Tishman/Harris or Seasons to maintain the upper level of the Terminal or to inspect it for any defective conditions during the period between the time of the installation and modification of the gate and the date of the accident.

After joinder of issue and discovery, Tishman/Harris, Seasons and Regional, collectively the Tishman defendants, moved for summary judgment dismissing the complaint, arguing that they did not have control of the Ferry Terminal during the relevant time period and that none of them had any contractual obligation to inspect or maintain the premises where plaintiff was injured. Thus, as argued, they did not owe a duty of care to plaintiff. Supreme Court denied the motion, holding that a triable issue of fact existed as to whether any of the defendants had continuing access to the area or a continuing obligation to maintain the gate. The court also found a factual issue as to whether the gate was improperly designed or installed in the first instance. In our view, whether defendants had continued access to the area is irrelevant to the issue presented, i.e., whether defendants owed a duty to plaintiff to maintain the gate. Since none of the reasons propounded to deny the motion withstand scrutiny, we reverse and grant summary judgment.

The threshold issue is the extent, if any, of the duty of care that the Tishman defendants, as contractors, owed to plaintiff, a noncontracting party to their contractual arrangements with EDC and each other. In a recent decision (Church v Callanan Indus., 99 NY2d 104 [2002]), the Court of Appeals again had oc[66]*66casion to set forth the general rule that a contractor does not owe a duty of care to a noncontracting third party. A duty of care to noncontracting third parties, however, may arise out of a contractual obligation or the performance thereof in three sets of excepted circumstances, in which case the promisor is subject to tort liability for failing to exercise due care in the execution of the contract (id. see also Espinal v Melville Snow Contrs., 98 NY2d 136, 139-141 [2002]; H.R. Moch Co. v Rensselaer Water Co., 247 NY 160 [1928]; Eaves Brooks Costume Co. v Y.B.H. Realty Corp., 76 NY2d 220 [1990]; and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Donaldson v. Port Auth. of N.Y. & N.J.
2025 NY Slip Op 02719 (Appellate Division of the Supreme Court of New York, 2025)
Scaccia v. Brookfield Props. One WFC Co., LLC
2024 NY Slip Op 02677 (Appellate Division of the Supreme Court of New York, 2024)
Beadell v. Eros Mgt. Reality, LLC
2024 NY Slip Op 02496 (Appellate Division of the Supreme Court of New York, 2024)
Hyland v. MFM Contr. Corp.
2024 NY Slip Op 01252 (Appellate Division of the Supreme Court of New York, 2024)
Hodzic v. M. Cary, Inc.
159 N.Y.S.3d 882 (Appellate Division of the Supreme Court of New York, 2022)
Farrugia v. 1440 Broadway Assoc.
2018 NY Slip Op 347 (Appellate Division of the Supreme Court of New York, 2018)
Kenny v. Turner Construction Co.
2017 NY Slip Op 8090 (Appellate Division of the Supreme Court of New York, 2017)
Federico v. Defoe Corp.
138 A.D.3d 682 (Appellate Division of the Supreme Court of New York, 2016)
Board of Managers of the a Building Condominium v. 13th & 14th Street Realty, LLC
121 A.D.3d 432 (Appellate Division of the Supreme Court of New York, 2014)
PARO, CAMERON E. v. PIEDMONT LAND AND CATTLE, LLC
Appellate Division of the Supreme Court of New York, 2013
Paro v. Piedmont Land & Cattle
111 A.D.3d 1425 (Appellate Division of the Supreme Court of New York, 2013)
Asante v. JPMorgan Chase & Co.
93 A.D.3d 429 (Appellate Division of the Supreme Court of New York, 2012)
Powell v. HIS Contractors, Inc.
75 A.D.3d 463 (Appellate Division of the Supreme Court of New York, 2010)
Golisano v. Keeler Construction Co.
74 A.D.3d 1915 (Appellate Division of the Supreme Court of New York, 2010)
H & H Acquisition Corp. v. Financial Intranet Holdings
669 F. Supp. 2d 351 (S.D. New York, 2009)
Oefelein v. CFI Construction Inc.
45 A.D.3d 1002 (Appellate Division of the Supreme Court of New York, 2007)
Wyant v. Professional Furnishing & Equipment, Inc.
31 A.D.3d 952 (Appellate Division of the Supreme Court of New York, 2006)
Marden v. Maurice Villency, Inc.
29 A.D.3d 402 (Appellate Division of the Supreme Court of New York, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
9 A.D.3d 62, 777 N.Y.S.2d 458, 2004 N.Y. App. Div. LEXIS 7321, Counsel Stack Legal Research, https://law.counselstack.com/opinion/timmins-v-tishman-construction-corp-nyappdiv-2004.