Times & Seasons LLC Act 250 Reconsideration

CourtVermont Superior Court
DecidedMarch 29, 2010
Docket45-3-09 Vtec
StatusPublished

This text of Times & Seasons LLC Act 250 Reconsideration (Times & Seasons LLC Act 250 Reconsideration) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Times & Seasons LLC Act 250 Reconsideration, (Vt. Ct. App. 2010).

Opinion

STATE OF VERMONT ENVIRONMENTAL COURT

} In re Times & Seasons, LLC } Act 250 Reconsideration } Docket No. 45-3-09 Vtec }

Decision on Multiple Motions Times and Seasons, LLC (“Applicant”) seeks an Act 250 permit authorizing the construction and operation of a gift shop and deli, with related improvements, on a 7.3± acre tract of land located at 1675 Dairy Hill Road in South Royalton, Vermont. Applicant’s initial efforts began in March 2004. After its application was denied, both by the District 3 Environmental Commission (“District Commission”) and the former Vermont Environmental Board (“Environmental Board”) for failing to satisfy Act 250 criteria 8, 9(B), and 10, Applicant appealed to the Vermont Supreme Court. The Supreme Court affirmed the permit denial on the grounds that the project did not comply with criteria 8 and 9(B). The Supreme Court issued its final entry order, addressing Applicant’s motion for re-argument, on March 14, 2008. Applicant thereafter filed with the District Commission an application for reconsideration pursuant to 10 V.S.A. § 6087(c).1 As explained more fully below, § 6087(c) allows an applicant to apply for reconsideration with the District Commission within six months of a final Act 250 permit application denial if the applicant certifies that it has corrected the deficiencies identified during the denial.2 An Act 250 permit may issue if those problems are satisfactorily addressed. The District Commission determined that Applicant’s modified project complied with Act 250 criterion 8, but it denied the application for failing to satisfy criterion 9(B). Applicant timely appealed that decision to this Court; the only issue raised in the appeal is whether the deficiencies regarding criterion 9(B) have been corrected such that the proposal now complies with criterion 9(B). No adjoining landowners have appeared in these proceedings. The only entities to appear in opposition to Applicant’s proposal are the Land Use Panel of the Vermont Natural Resources Board (“NRB”), which is represented by its attorney, Mark L. Lucas, Esq., and the Town of

1 We note here, for clarity, that an application for reconsideration filed pursuant to 10 V.S.A. § 6087(c) is wholly different from a motion to amend under V.R.C.P. 59(e), which is often called a motion for reconsideration. 2 Although Act 250 applicants have long taken advantage of § 6087(c), this case appears to be the first instance in which an Act 250 permit applicant sought reconsideration following a denial by the Vermont Supreme Court.

1 Royalton Planning Commission (“Planning Commission”), which is represented by Geoffrey H. Hand, Esq. Applicant is represented by David L. Grayck, Esq. and Zachary K. Griefen, Esq. The Agency of Natural Resources has informational status through Judith L. Dillon, Esq. Currently pending before the Court are three cross-motions for summary judgment, filed on behalf of Applicant, the NRB, and the Planning Commission. The NRB has also filed two motions that seek to strike from the record certain pleadings filed by Applicant. Because our decision on the motions for summary judgment is reached without considering any of the challenged pleadings, and because the issues discussed herein are dispositive, we need not address the NRB’s motions to strike.

Procedural History & Factual Background For the sole purpose of putting the pending motions into context, we recite the following facts, which we understand to be undisputed unless otherwise noted: 1. In March 2004, Applicant sought approval under Act 250 to construct and operate a gift shop and deli on a 7.3± acre tract of land near the Joseph Smith Birthplace Memorial; Applicant’s property is located at 1675 Dairy Hill Road in South Royalton, Vermont. In addition to constructing a roughly 4,800-square-foot gift shop and a twenty-seat deli, Applicant proposed to improve the parcel with an access drive and parking lot, a pump station, a septic field, and a drilled well. 2. On August 25, 2004, the District Commission denied Applicant’s Act 250 permit application; Applicant appealed that decision to the Environmental Board. 3. The Environmental Board denied Applicant’s application, concluding that the proposed project did not comply with Act 250 criteria 8, 9(B), or 10. Re: Times and Seasons, LLC, No. 3W0839-2-EB, Findings of Fact and Conclusions of Law, and Order (Altered) (Vt. Envtl. Bd. Nov. 4, 2005). 4. The Board determined that Applicant failed to satisfy criterion 8 for two reasons: Applicant did not take adequate mitigation measures to minimize the project’s aesthetic impact, and the project violated a clear, written community standard intended to preserve the scenic beauty of the area. Id. at 42–50. The Board also concluded that the proposal did not comply with criterion 9(B) because the project would significantly reduce the agricultural potential of 1.9± of the 2.8± acres of primary agricultural soil on the project site. Id. at 51–56. Finally, the Board concluded that Applicant did not satisfy criterion 10 because Applicant failed to show that

2 locating the commercial development close to the town center was not feasible, which was a directive stated in the Town of South Royalton Town Plan (“Town Plan”). Id. at 58–67. 5. Applicant appealed the Environmental Board’s decision to the Supreme Court, and on February 1, 2008, the Court affirmed in part and reversed in part the denial of Applicant’s application. In re Times & Seasons, LLC, 2008 VT 7, 183 Vt. 336. 6. The Supreme Court agreed that Applicant’s proposed project did not comply with criterion 8, affirming the Environmental Board’s finding that Applicant took inadequate mitigation measures to minimize the project’s aesthetic impact. Id. at ¶¶ 9–10.3 The Court also agreed that Applicant’s project did not comply with criterion 9(B), finding no error in the Board’s conclusion that 1.9± of 2.8± acres of primary agricultural soils would be impacted by the project. Id. at ¶ 16.4 However, the Court reversed the Board’s determination regarding criterion 10, concluding that the general Town Plan recommendation that commercial developments be located close to the town center “where feasible” was too ambiguous to be enforced against Applicant. Id. at ¶ 23. Accordingly, the Supreme Court’s February 1 decision established that Applicant’s proposed project only exhibited deficiencies in regard to Act 250 criteria 8 and 9(B). 7. Applicant thereafter filed a motion for re-argument with the Supreme Court; the Court denied its motion by entry order of March 14, 2008. 8. Approximately five and one-half months after this denial, on August 29, 2008, Applicant filed a reconsideration request with the District Commission pursuant to 10 V.S.A. § 6087(c). Section 6087(c) allows an applicant who has been denied an Act 250 permit to seek reconsideration of the permit within six months of the final permit denial—so long as the applicant certifies that it has corrected the deficiencies identified in the prior denial of its original application. 10 V.S.A. § 6087(c).5 9. On February 20, 2009, the District Commission determined that the Applicant’s revised project design corrected the problems concerning Act 250 criterion 8, but the project continued 3 As a result of this conclusion, the Court did not reach whether the proposed project violated any clear, written community standard. In re Times & Seasons, LLC, 2008 VT 7, ¶ 10. 4 The Court also agreed with the Environmental Board that Applicant had failed to meet each of the four sub- criteria to criterion 9(B). Id. at ¶ 17–20 (examining 10 V.S.A. § 6086(a)(9)(B)(i)–(iv)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Eustance Act 250 Juris. Opinion (No. 2-231)
2009 VT 16 (Supreme Court of Vermont, 2009)
In Re Appeal of Times & Seasons, LLC
2008 VT 7 (Supreme Court of Vermont, 2008)
Smith v. Winhall Planning Commission
436 A.2d 760 (Supreme Court of Vermont, 1981)
In Re Eastview at Middlebury, Inc.
2009 VT 98 (Supreme Court of Vermont, 2010)
Bacon v. Lascelles
678 A.2d 902 (Supreme Court of Vermont, 1996)
Coty v. Ramsey Associates, Inc.
573 A.2d 694 (Supreme Court of Vermont, 1990)
In Re Sherman Hollow, Inc.
641 A.2d 753 (Supreme Court of Vermont, 1993)
Toys, Inc. v. F.M. Burlington Co.
582 A.2d 123 (Supreme Court of Vermont, 1990)
Chapman v. Sparta
702 A.2d 132 (Supreme Court of Vermont, 1997)
Perkins v. Vermont Hydro-Electric Corp.
177 A. 631 (Supreme Court of Vermont, 1934)
Sanz v. Douglas Collins Construction
2006 VT 102 (Supreme Court of Vermont, 2006)
Madkour v. Zoltak
2007 VT 14 (Supreme Court of Vermont, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
Times & Seasons LLC Act 250 Reconsideration, Counsel Stack Legal Research, https://law.counselstack.com/opinion/times-seasons-llc-act-250-reconsideration-vtsuperct-2010.