Timberton Golf, L.P. v. McCumber Construction, Inc.

788 F. Supp. 919, 1992 U.S. Dist. LEXIS 5291, 1992 WL 72081
CourtDistrict Court, S.D. Mississippi
DecidedApril 3, 1992
DocketCiv. A. H92-0035(R)
StatusPublished
Cited by2 cases

This text of 788 F. Supp. 919 (Timberton Golf, L.P. v. McCumber Construction, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Timberton Golf, L.P. v. McCumber Construction, Inc., 788 F. Supp. 919, 1992 U.S. Dist. LEXIS 5291, 1992 WL 72081 (S.D. Miss. 1992).

Opinion

MEMORANDUM ORDER

DAN M. RUSSELL, Jr., District Judge.

This cause is before this Court on Motion of Timberton Golf, L.P. (hereinafter “Tim-berton”) for Preliminary Injunction, for Consolidation, and for Abstention, and on the Cross-Motion of McCumber Construction, Inc. and McCumber Golf, Inc. (hereinafter “McCumber”) to compel arbitration and dismiss Timberton’s cause of action.

Facts and Proceedings

Timberton is a Mississippi limited partnership having its principal place of business in Forrest County, Mississippi. McCumber consists of McCumber Construction, Inc. and McCumber Golf, Inc., d/b/a Mark McCumber and Associates (hereinafter “McCumber and Associates”). Both McCumber Construction and McCum-ber and Associates are Florida corporations with their principal place of business in Orange Park, Florida.

Timberton is the owner/developer of Timberton Golf Club in Hattiesburg, Mississippi, which involved the development of a residential community containing residential lots and a golf course.

In furtherance of the development of the golf club, Timberton, and/or its predecessor in interest, entered into discussions with McCumber for the purpose of contracting with McCumber and Associates for design and consulting services and with McCumber Construction to implement the design.

Notwithstanding Timberton’s argument that the alleged contracts are void, purported agreements were entered into:

1) between McCumber and Associates and Timberton’s predecessor in interest, Timber Realty Corp., evidenced by correspondence of September 2, 1988 and March 6, 1989; and

2) between McCumber Construction and Timberton on or about September 12, 1989.

Of the two alleged agreements, only the September 12,1989 instrument provides for arbitration.

The parties appear to have treated the purported agreements and subsequent amendments as valid for the better part of two years.

On October 8, 1991, based upon allegations of Timberton’s failure to pay for work performed under the contract, as well as additional work arising therefrom, McCum-ber Construction, relying upon provision 10.8 of the main contract, filed a demand for arbitration.

Initially, Timberton treated the alleged contracts as valid even to the extent of, in addition to its response and counterclaim against McCumber Construction, filing a claim against McCumber and Associates. By McCumber Construction’s amendment to its demand and response to counterclaim of November 22, 1991, which, in part, added the claim of McCumber and Associates, said associates agreed to arbitration notwithstanding its understanding that no pre *921 vious agreement to arbitrate existed between that party and Timberton.

Upon discovery, Timberton ascertained that neither McCumber and Associates, nor J. Christopher Commins, McCumber and Associates’ principal in charge of the Tim-berton project, were licensed to practice landscape architecture in the State of Mississippi. It was also discovered that McCumber Construction had not obtained a certificate of responsibility in the State of Mississippi as required by Miss.Code Ann. Sections 31-3-15 and 31-3-21 (1972, as amended).

On or about January 22, 1992, based upon the foregoing discovery, Timberton filed its objection to the demand for arbitration, amended response to demand, and amended counterclaim in the arbitration proceedings.

Also, on or about January 23, 1992, Tim-berton filed its complaint in the Circuit Court of Forrest County, Mississippi, seeking declaratory and injunctive relief and assessment óf statutory penalty.

After removal of the proceedings to this Court, McCumber, on or about February 18, 1992, filed their answer, defenses and counterclaim against Timberton.

While proceedings were being initiated, which led to removal to this Court on or about January 22,1992, the American Arbitration Association advised the parties that it had set the matter for a hearing on March 16, 1992.

The motions at bar were filed by Timber-ton and McCumber on February 27 and 28 of 1992, respectively, and a hearing was had on the motions on March 5, 1992. The parties at that hearing related to this Court that the March 16, 1992 arbitration hearing had been postponed. The hearing has been subsequently rescheduled for May 26,1992.

Discussion

The primary issue before this Court is the effect, if any, of the failure of McCumber Construction to obtain a certificate of responsibility upon the enforceability of the arbitration clause; assuming, ar-guendo, that the violation of the statute potentially renders the underlying contract void ab initio.

Also at issue is the broader question of whether the construction of the particular statutes pose such a problem of inconsistent and inconclusive interpretation that this Court should abstain until such time as the State court addresses the issues.

I.

Miss.Code Ann. Section 31-3-15 (1972) sets out:

No contract for public or private projects shall be issued or awarded to any contractor who did not have a current certificate of responsibility issued by said board at the time of the submission of the bid, or a similar certificate issued by a similar board of another state which recognizes certificates issued by said board. Any contract issued or awarded in violation of this section shall be null and void.

It is further set out in Section 31-3-21, in pertinent part:

It shall be unlawful for any person who does not hold a certificate of responsibility issued under this chapter, or a similar certificate issued by another state recognizing such certificate issued by the State of Mississippi, to submit a bid, enter into a contract, or otherwise engage in or continue in this state in the business of a contractor, as defined by this chapter.

The argument of Timberton concedes the premise that otherwise arguably valid and comprehensive arbitration clauses are separable from the underlying contract, and thus effective, if said contract is merely potentially voidable. If however, argues Timberton, the contract is subject to being found to be void ab initio, then likewise the arbitration agreement is subject to being found to be void since it is a part of the contract.

The argument of Timberton on this issue is characterized as bordering on the frivolous by McCumber, and while this Court would not so characterize it, it nevertheless does find McCumber’s argument persuasive.

*922 Notwithstanding McCumber’s citation to Robert Lawrence Company v. Devonshire Fabrics, Inc., 271 F.2d 402 (2nd Cir.1959), as authority, in part, for the principle that federal courts have consistently treated arbitration clauses as separate and independent of the underlying contract, this Court deems the proper point of beginning to be Prima Paint Corp. v. Flood & Conklin Mfg. Co.,

Related

Cite This Page — Counsel Stack

Bluebook (online)
788 F. Supp. 919, 1992 U.S. Dist. LEXIS 5291, 1992 WL 72081, Counsel Stack Legal Research, https://law.counselstack.com/opinion/timberton-golf-lp-v-mccumber-construction-inc-mssd-1992.