Tierney & Black, Inc. v. Siemens Power Corp.

79 F. App'x 740
CourtCourt of Appeals for the Sixth Circuit
DecidedSeptember 12, 2003
DocketNo. 01-6518
StatusPublished
Cited by2 cases

This text of 79 F. App'x 740 (Tierney & Black, Inc. v. Siemens Power Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tierney & Black, Inc. v. Siemens Power Corp., 79 F. App'x 740 (6th Cir. 2003).

Opinion

NELSON, Circuit Judge.

The central issue in this appeal is whether the district court erred in granting summary judgment for the defense on a claim of conversion asserted under Tennessee law. Unlike the district court, we are not persuaded that the conversion claim is barred by a release that the plaintiff executed before the claim had accrued. We are persuaded, however, that the plaintiff has failed to demonstrate the existence of a triable issue as to whether the alleged conversion in fact occurred. The challenged judgment will be affirmed on that basis.

I

In 1995, Tierney & Black, Inc.1 contracted with Siemens Power Corporation to [741]*741construct and operate a “Mobile Extraction/Recovery Facility,” or “MERF,” at Siemens’ site in Richland, Washington. The purpose of the MERF is to recover uranium residue from “wet waste” generated during the manufacture of uranium fuel for commercial power reactors.

The parties’ contract—styled a “Services Agreement”—provided that “[Tierney & Black] shall procure, install, fabricate, deliver and set-up the MERF at the [Siemens] site,” but that the MERF “shall be owned by [Tierney & Black].”2 “Delivery of the MERF,” the contract further provided, “shall be the responsibility of [Tierney & Black].”

Siemens agreed to pay capital equipment and related subcontractor and freight costs in addition to paying Tierney & Black for engineering and installation services provided on a time and materials basis. Tierney & Black was also to be compensated on a time and materials basis for operating the facility. A change order executed in 1997 provided that Siemens’ total expenditure on the project should not exceed $2,112,663, of which $401,552 represented projected operating costs.

Tierney & Black agreed that Siemens would have the right to terminate the Services Agreement, by written notice, either for default by Tierney & Black or simply for Siemens’ “own convenience.” If Siemens availed itself of the termination right, it would receive title to the MERF (including materials that were not yet incorporated into the facility) and could either complete Tierney & Black’s work itself or procure the services of another contractor. Tierney & Black, in such circumstances, was to receive a part of the contract price proportionate to the amount of work it had completed.

In February of 1998, with construction of the MERF not yet finished, Tierney & Black and Siemens decided that the Services Agreement was “no longer an adequate expression of the rights and obligations of either party.” They therefore executed an “Interim Agreement,” the key provisions of which were (1) a release of all claims that either party might have against the other “under the Contract” and (2) a promise to negotiate, in good faith, “a change order to the Contract.” Siemens did not exercise its contractual right to terminate the agreement.

Also in February, Tierney & Black entered into a “Release and Settlement Agreement” with Mobile International, Inc., the subcontractor that was constructing the MERF at a location in Oklahoma. The agreement provided that Mobile would release the MERF to Tierney & Black and Siemens upon receipt of a final payment, and that Tierney & Black would be “fully responsible for the loading, offloading, erection and shipping” of the MERF to Siemens’ Richland site by March 30,1998.

Siemens made the final payment to Mobile in March of 1998, bringing Siemens’ total expenditures on the MERF to approximately $1.9 million. Siemens then informed Tierney & Black that it would like to make its own arrangements for shipment of the MERF from Oklahoma to Washington. Tierney & Black responded that negotiation of the change order contemplated by the Interim Agreement must precede shipment of the MERF, and that removal of the facility by Siemens, without Tierney & Black’s permission, would constitute a breach of contract. Siemens proceeded nevertheless to arrange the shipment, and the MERF arrived at Siemens’ [742]*742site in April of 1998. The facility was not functional when it arrived, but Siemens was able to make it work by the middle of 1999. The change order contemplated by the Interim Agreement was never negotiated, and Tierney & Black has had nothing to do with the operation of the facility.

In December of 1998, Tierney & Black sued Siemens for breach of the Services Agreement, breach of the Interim Agreement, and inducement of Mobile to breach the Release and Settlement Agreement. After learning during discovery that the MERF was in operation at Siemens’ site, Tierney & Black filed a supplemental complaint alleging conversion of the MERF.

Siemens then filed a series of three summary judgment motions. First, Siemens moved for summary judgment on the claims in which breach of the Services Agreement was alleged. Citing Tierney & Black’s release of all claims arising under the contract, the district court granted the motion. Second, Siemens moved for summary judgment on the conversion claim. Holding that the release covered that claim as well, the district court again granted Siemens’ motion. The court denied a motion for reconsideration filed by Tierney & Black.

In its third motion, Siemens sought summary judgment on the remaining claims of breach of the Interim Agreement and inducement of breach by Mobile. The district court granted the motion as to the claim for inducement of breach, leaving the claim for breach of the Interim Agreement as the only surviving claim. The court ordered Tierney & Black to file a specification of the damages resulting from the alleged failure to conduct negotiations on a change order, along with a list of exhibits supporting its damages calculations.

After receiving Tierney & Black’s statement of damages, Siemens moved for an order excluding all evidence of damages on the grounds that the claimed damages were impermissibly vague and speculative. The district court granted the motion. Tierney & Black then moved for a voluntary dismissal, without prejudice, and the district court granted that motion as well. Final judgment having been entered as to all claims that were not dismissed, Tierney & Black filed a timely appeal from (1) the summary judgment on the conversion claim, (2) the denial of reconsideration of that summary judgment, (3) the summary judgment on the inducement-to-breach claim, (4) the order requiring Tierney & Black to file a list of damages, and (5) the order excluding evidence of damages.

II

We review the summary judgment on Tierney & Black’s conversion claim de novo. See, e.g., Chao v. Hall Holding Co., 285 F.3d 415, 440 (6th Cir.2002), cert. denied, 537 U.S. 1168, 123 S.Ct. 966, 154 L.Ed.2d 908 (2003). We may affirm the judgment on any ground that is supported by the record. See id.

A

As we have seen, the district court held that Tierney & Black released its conversion claim when it executed the Interim Agreement. In this, we believe, the district court erred. Assuming, for purposes of analysis, that the conversion claim falls within the substantive scope of the release - i.e., that it arises “under the contract” - we think that the claim is plainly outside of the release’s temporal bounds.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rebecca Woody v. A.W. Chesterton Company
Court of Appeals of Tennessee, 2008

Cite This Page — Counsel Stack

Bluebook (online)
79 F. App'x 740, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tierney-black-inc-v-siemens-power-corp-ca6-2003.