Thunderstruck Signs

CourtArmed Services Board of Contract Appeals
DecidedAugust 16, 2017
DocketASBCA No. 61027
StatusPublished

This text of Thunderstruck Signs (Thunderstruck Signs) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thunderstruck Signs, (asbca 2017).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Thunderstruck Signs ) ASBCA No. 61027 ) Under Contract No. FA4855-15-P-0136 )

APPEARANCE FOR THE APPELLANT: Mr. Jason Mock President

APPEARANCES FOR THE GOVERNMENT: Jeffrey P. Hildebrant, Esq. Air Force Deputy Chief Trial Attorney Lt Col Nathaniel H. Sears, USAF Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE WOODROW

This appeal arises from a contracting officer's termination for cause for a contract between appellant Thunderstruck Signs and the government to manufacture and deliver facility signs to Cannon Air Force Base, New Mexico. The parties have elected to proceed under the Board's Rule 12.3 Accelerated Procedures and also to waive a hearing and submit its case upon the record pursuant to Board Rule 11. The only matter before the Board is whether the Air Force's termination of the contract for cause was proper.

SUMMARY FINDINGS OF FACT

I. The Contract

1. The United States Air Force (Air Force or government) awarded a firm-fixed- price, commercial item contract, No. FA4855-15-P-0136, to Thunderstruck Signs (appellant or Thunderstruck) on 16 September 2015 for $47,791.16. The contract required Thunderstruck to supply six facility signs to Cannon Air Force Base (AFB). (R4, tab 3 at 3) The contract specified a delivery date of 16 October 2015 (id. at 6). According to its proposal, Thunderstruck would remove and dispose of the existing signs and supply and install the new signs (id. at 3).

2. The contract incorporated by reference the standard commercial item contract clause, Federal Acquisition Regulation (FAR) 52.212-4, CONTRACT TERMS AND CONDITIONS-COMMERCIAL ITEMS (MA y 2015) (R4, tab 3 at 8).

3. Paragraph (f) of the clause, entitled Excusable delays, states in relevant part that the contractor: [S]hall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers.

4. Paragraph (m) of the clause addresses termination for cause, and permits the government to "terminate [the] contract, or any part hereof, for cause in the event of any default by the Contractor, or ifthe Contractor fails to comply with any contract terms and conditions." Paragraph (m) also provides that if it is "determined that the Government improperly terminated [the] contract for default, such termination shall be deemed a termination for convenience."

II. Performance Period

5. On 8 October 2015, eight days prior to the contract delivery date, Thunderstruck emailed the Air Force stating that "[w]e will need artwork for all signs to be sent at your leisure. These signs generally take 5-7 [sic] to manufacture and install." (R4, tab 4 at 1) The Air Force did not provide the artwork by 16 October 2015, nor did Thunderstruck deliver the signs by that date.

6. On 26 October 2015, Thunderstruck again requested the Air Force to "send us the artwork for the signs as construction is progressing nicely" (R4, tab 5 at 1).

7. On 5 November 2015, the Air Force provided the artwork to Thunderstruck (R4, tab 7 at 1-2).

8. On 12 January 2016, the Air Force contacted Thunderstruck and requested an "update on the timeline for the outdoor signs," and asked, "When will we expect an installation date?" Thunderstruck responded the same day that "the third of six cans" was completed and the fourth "almost complete." (R4, tab 8 at 1-3)

III. Initial Show Cause Notice

9. On 28 January 2016, the Air Force issued a Show Cause Notice informing Thunderstruck that the Air Force was considering terminating the contract for cause. Additionally, the Show Cause Notice requested that Thunderstruck submit a "detailed timeline for installation" and stated that "[t]he Contractor should install the signs that are currently available within two weeks from today." (R4, tab 9 at 1-2)

2 10. On 4 February 2016, Thunderstruck responded to the Show Cause Notice stating that the "response to the RFQ on the quotation from our business clearly stated each can takes 4 to 6 weeks to construct" (R4, tab 13 ). Attachment 1 to the Show Cause response is Thunderstruck's response to the RFQ, titled: "Quotation & Purchase Contract," dated 12 September 2015. The final sentence in the section titled "Description" states that "Each can takes 4 to 6 weeks." (R4, tab 12 at 1)

11. Thunderstruck further indicated the signs would be "finished within the timeframe originally bid (24 weeks)" and that all the work would be "complete[d] by April 13 2016" (R4, tab 13 at 1).

12. On 17 February 2016, the Air Force again requested Thunderstruck to provide a detailed timeline for the installation of the signs and to install all signs "currently available" by 24 March 2016 (R4, tab 14 at 1).

13. On 29 March 2016, Thunderstruck told the Air Force that "Four signs are complete" and the remaining two signs would be complete in "5 to 6 week turns each," or "between June 7-15th" (R4, tab 17 at 6-7).

IV. Bilateral Modification of Completion Date

14. On 4 April 2016, the parties executed a bilateral modification to the contract, which extended the completion date from 16 October 2015 to 15 June 2016 (R4, tab 18 at 2).

15. By 15 June 2016, Thunderstruck had not delivered the signs to Cannon AFB.

16. On 17 June 2016, Thunderstruck wrote to the Air Force requesting specific information on the pole size for one of the two signs that was still under construction (app. supp. R4 at 1-2; R4, tab 24 at 1).

17 .. The manufacturer of the signs, located in Birmingham, Alabama, informed Thunderstruck that the signs would be complete and ready for shipment between 10 July and 24 July (R4, tab 24 at 1; app. resp. at 3 ).

18. On 22 June 2016, Thunderstruck informed the Air Force that it would take approximately another two weeks to deliver the signs and that the signs would be delivered on 11 July 2016, "[g]ive or take 3 days or so" (R4, tab 20 at 3).

19. On 12 July and on 14 July 2016, the Air Force asked about the status of the signs. Thunderstruck responded on 14 July 2016 that it was "waiting on the manufacturer" to provide a shipping date and that "the hold up was due to not getting the Pole size and paint color from your side until June 2l5t." (R4, tab 20 at 1)

3 20. On 21 July 2016, the manufacturer informed Thunderstruck that delivery would be delayed until the week of 25 July 2016 (app. resp. at 3).

21. On 21 July 2016, the Air Force requested the tracking information for the signs. Thunderstruck responded that "the truck is not available until next week sometime." (R4, tab 21 at 1)

22. On 25 July 2016, the contracting officer (CO) contacted Thunderstruck to determine when the signs would be delivered and installed. The CO informed Thunderstruck that either Thunderstruck or its subcontractor would need to be at Cannon AFB, because it was Thunderstruck's responsibility to provide the necessary labor to offload and install the signs. (R4, tab 24 at 2) Mr. Mock, from Thunderstruck, stated that because he would be unavailable to meet the delivery truck at Cannon AFB that Friday, 29 July 2016, he would contact his subcontractor to reschedule delivery and send the CO an updated delivery and installation schedule by the end of the day on 25 July (id. at 3).

23. On 26 July 2016, the CO asked Thunderstruck for an updated delivery schedule. Mr. Mock responded that he would update the CO as soon as he had the revised schedule. (R4, tab 24 at 3)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Thunderstruck Signs, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thunderstruck-signs-asbca-2017.