Thornton-Tomasetti Engineers v. Indianapolis-Marion County Public Library

851 N.E.2d 1269, 2006 Ind. App. LEXIS 1545, 2006 WL 2323313
CourtIndiana Court of Appeals
DecidedAugust 11, 2006
Docket06A01-0602-CV-75
StatusPublished
Cited by25 cases

This text of 851 N.E.2d 1269 (Thornton-Tomasetti Engineers v. Indianapolis-Marion County Public Library) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thornton-Tomasetti Engineers v. Indianapolis-Marion County Public Library, 851 N.E.2d 1269, 2006 Ind. App. LEXIS 1545, 2006 WL 2323313 (Ind. Ct. App. 2006).

Opinions

OPINION

BAKER, Judge.

This case arises out of the renovation and expansion of the Indianapolis-Marion County Public Library (the Project). Work on the Project commenced in September 2002, and is scheduled to be completed in February 2008. The estimated cost of the Project when work began was approximately $105 million.

Appellant-defendant Thoraton-Tomaset-ti Engineers (Thornton) appeals from the trial court's denial of a preliminary injuncetion that it had sought with regard to work that it had performed for appellee-plaintiff, the Library. In particular, Thornton-the engineer involved in the Project-contends that the trial court erred in dismissing its request for a preliminary injunction because it had offered evidence on all of the elements required to obtain such relief. Thornton also maintains that the trial [1272]*1272court erred in denying its request to enter the Library's premises in order to conduct certain testing on the construction site, and seeks to appeal the trial court's grant of a protective order in favor of the Library with regard to Thornton's request to conduct the further testing.

Concluding that the trial court properly dismissed Thornton's request for a preliminary injunction, we affirm. We also grant the Library's motion to dismiss the portion of Thornton's appeal challenging the denial of its request to enter the premises to conduct further testing, as well as the matters relating to the protective order that was entered in favor of the Library.

FACTS

On February 19, 1998, the Library contracted with Woolen, an architect, for the Project that involved: (1) the renovation of the Library building; (if) the demolition of a multi-story annex building; (iii) the new construction of a six-story tower; (iv) the new construction of an underground parking garage that serves as the structural foundation for the tower; and (v) construction of a 350-seat auditorium. Woolen issued the final architectural plans, and Thornton was engaged to serve as the engineer of record on the Project.

On February 28, 2004, while work was being performed on the parking garage, representatives from the Library discovered a number of alleged defects in the concrete beams on the structure. As a result, the Library retained Construction Technology Laboratories, Inc. (CTL), to investigate and analyze potential problems with the garage. CTL requested design information and calculations from Thornton to assist in its analysis of the garage.

Thereafter, on April 12, 2004, CTL commenced non-destructive testing on the garage to evaluate the extent and significance of the alleged defects. CTL performed this testing in order to identify the location of reinforcing steel and to identify any voids in the concrete. CTL eventually reached the conclusion that the garage contained "major construction and design defects" that required repairs on "al vast majority of the columns and beams." Appellant's App. p. 954.

Following CTL's investigation and testing, the Library suspended construction on the garage on May 6, 2004. At some point, CTL determined that destructive testing was necessary to more thoroughly investigate and analyze the defects. CTL prepared, and Thornton allegedly agreed to, a Repair Plan dated June 16, 2004. The parties also allegedly agreed to a detailed testing and repair protocol on July 13, 2004 (the Repairs Manual), which set forth the process for testing, analyzing, and repairing structural defects in the garage.

In accordance with the Repairs Manual, all defects and repairs to the garage were to be documented, photographed, and/or videotaped as the work progressed. In August 2004, the Library commenced an action against Thornton and others,1 alleging that Thornton was responsible for the damages associated with errors in the design of the garage. Hence, the Library claimed that it sustained damages in excess of $19 million. Thornton denied the allegations that its design was deficient and claimed that CTL's findings regarding the various defects in the structure were erroneous.

For the next several months, CTL continued to investigate and analyze the de[1273]*1273fects. Corrective measures to the garage were to be performed in accordance with the Repairs Manual. Hence, Thornton prepared various repair design documents for the Project subject to CTL's review. The Library claimed that Thornton failed to follow the procedures set forth in the Repairs Manual and became dilatory in issuing repair directives Ultimately, Thornton refused to follow the Repairs Manual whenever a design issue arose. Finally, on May 18, 2005, Thornton formally retracted any agreement to follow the Repairs Manual, and the Project was further delayed. The Library then engaged Beam Longest & Neff and another company to design the repairs to the garage in order to compensate for Thornton's refusal to participate in the repairs process. By June 2005, the Library completed the repairs to a stage that enabled construction to resume.

In the fall of 2005, after approximately sixteen months of delay and several months of new construction following recommencement of work, Thornton suggested to the Library that certain "load tests" were necessary on three of the structural beams in the garage so that Thornton could verify the adequacy of its design and confirm or refute the allegations of the design errors. Load tests are generally designed to test the structural members within a building to the point of failure, and Thornton maintained that the results of such tests would settle the matter.2

On December 12, 2005, Thornton petitioned the trial court for injunctive relief in accordance with Trial Rule 65(A): (M) to prevent the Library from continuing with all physical investigations and repairs to all structural members on the Project that were alleged to be defectively designed; (ii). to require the Library .to provide Thornton with detailed and specific information regarding alleged design defects; and (ifi) to allow Thornton access to the site to perform its proposed load tests over a ninety-day period. Thornton alleged that because it did not have the required calculations and analyses that it had requested at the time of filing its motion, it was not able to specifically identify structural members for load testing at that time.

In support of its motion for a preliminary injunction, Thornton submitted an affidavit, and the testimony of Robert DeS-cenza, Thornton's executive vice president, as well as evidence from Joseph G. Burns, the lead engineer on the project. Hearings were held on January 11, 19, and 20, 2006. It was determined that multiple beams in the garage failed to meet applicable building codes, and Burns admitted that at least one of the beams had "significant faults." Tr. p. 271. Burns further indicated that, although load tests were considered during the lengthy period of relative inactivity on the Project, the idea of such testing never became a particularized demand until late fall 2005 when construction already had resumed. Thornton then rested its case in chief on January 19, and the Library asserted that the request for injunctive relief should be denied in accordance with Indiana Trial Rule 41(B) because Thornton had failed to satisfy the requisite burden of proof to obtain -injune-tive relief.

Prior to the hearing on January 20, representatives from Thornton visited the Library's garage and selected three beams [1274]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Margarita Ruiz v. Pedro J. Tirado (mem. dec.)
Indiana Court of Appeals, 2018
Abdullah Alkhalidi v. Indiana Department of Correction
42 N.E.3d 562 (Indiana Court of Appeals, 2015)
5200 Keystone Ltd. Realty, LLC v. Filmcraft Laboratories, Inc.
30 N.E.3d 5 (Indiana Court of Appeals, 2015)
D.S. v. State of Indiana
Indiana Court of Appeals, 2013
Orndorff v. Indiana Bureau of Motor Vehicles
982 N.E.2d 312 (Indiana Court of Appeals, 2012)
Camm v. State
957 N.E.2d 205 (Indiana Court of Appeals, 2011)
In Re MD
906 N.E.2d 931 (Indiana Court of Appeals, 2009)
Indiana Department of Child Services v. B.D.
906 N.E.2d 931 (Indiana Court of Appeals, 2009)
Reiswerg v. Statom
901 N.E.2d 1164 (Indiana Court of Appeals, 2009)
Todd v. State
900 N.E.2d 776 (Indiana Court of Appeals, 2009)
Gibson v. Indiana Department of Correction
899 N.E.2d 40 (Indiana Court of Appeals, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
851 N.E.2d 1269, 2006 Ind. App. LEXIS 1545, 2006 WL 2323313, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thornton-tomasetti-engineers-v-indianapolis-marion-county-public-library-indctapp-2006.