Thorn v. Barringer

81 S.E. 846, 73 W. Va. 618, 1914 W. Va. LEXIS 27
CourtWest Virginia Supreme Court
DecidedFebruary 3, 1914
StatusPublished
Cited by7 cases

This text of 81 S.E. 846 (Thorn v. Barringer) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thorn v. Barringer, 81 S.E. 846, 73 W. Va. 618, 1914 W. Va. LEXIS 27 (W. Va. 1914).

Opinion

Robinson, Judge :

The decree complained of is one enforcing a mechanic’s lien. Barringer, himself a contractor and builder, began the erection of a house on a lot owned by him. Some time thereafter, he contracted1 in a general way with Thorn, a material man, to be furnished with all materials necessary to be used in the building. Barringer under the contract ordered from Thorn many shipments of materials which went into the building. When the main part of the house was nearly done, and after a cessation of work thereon for several weeks, [620]*620Barringer conveyed the property to Heatwole. Under a contract with the grantee, Barringer went on with the work of completing the main part of the house and erecting a wing to it, still ordering the materials from Thorn. The deed from Barringer to Heatwole was recorded, but Thorn had no actual notice of the change of ownership, even if notice in that regard is material. Barringer did not pay for the materials which he ordered under the contract and used in the erection of the house. Thorn proceeded to protect himself by taking out a mechanic’s lien, treating Barringer as the owner, since the contract under which the materials were furnished was made with him as such. The mechanic’s lien was perfected under Code 1906, ch. 75, sec. 2, and not under sec. 3 of that chapter. In other words, Thorn perfected his lien as if Barringer was still the owner.

. Heatwole, on the day that the property was conveyed to him, executed a deed of trust thereon to secure a loan from "Williams, and the same was at once duly recorded. SO' we have observed that during the process of the execution of Thorn’s contract with the owner for furnishing the materials necessary to be used in the house, the property was conveyed away by the owner and was incumbered by the grantee.

In this suit by Thom to enforce the lien, the purchaser, the deed of trust holder, and the trustee in the deed of trust were of course joined with Barringer as parties. The circuit court decreed that Thorn’s lien was a valid one against the property for the amount due him for all materials furnished under the contract and used in the building, notwithstanding some of them were furnished after the time of the conveyance and incumbrance. The lien was given priority over the conveyance and the deed of trust. Prom the decree, Heatwole, the purchaser, has appealed.

Appellant maintains that the materials were not furnished under one continuous contract; that the materials furnished Barringer while he was actually the owner constituted a claim for a distinct lien under Code 1906, ch. 75, sec. 2, the statutory time for the filing of which had expired at the time of the conveyance; and that the materials furnished Barringer after he became a contractor under the vendee constituted a claim [621]*621for a separate lien under Code 1906, eh. 75, see. 3, requiring notice to appellant as owner within thirty-five days after Thom’s ceasing to furnish the materials, which was not given. Thus appellant maintains that there is no valid' lien against the property.

The court below evidently viewed the contract between Thom and Barringer as a continuous one upon which a valid lien could be claimed for all the materials furnished thereunder, as an entirety. The evidence justified such a view. Though the contract did not define just what materials should be furnished or the exact price of the same, yet it contemplated one settlement for all materials that Barringer should order from Thorn and use in the building under process of erection at the time. It was not limited to any particular part of the building. It was broad enough to embrace the furnishing of any materials that might be necessary in making ever so large a house of the ineompleted building. As long as Barringer continued to order materials from Thorn for use in the build-ins’. the contract continued, forming in the end an entire one. “When work or material is done or furnished, all going to the same general purpose, as the building of a house or any of its parts, though such work be done or ordered at different times, yet if the several parts form an entire whole, or are so connected together as to show that the parties had it in contemplation that the whole should form but one, and not distinct matters of settlement, the whole account must be treated as a unit, or as being but a single contract. ’ ’ Phillips on Mechanics’ Liens, see. 229. The contract between Thorn and Barringer being a continuous one, the lapsing of the statutory period for filing a lien, between items of materials furnished thereunder, can not make separate contracts out of it; nor can the same defeat right to a lien based on the contract as an entirety, if filed in time at the end. D. L. Billings Co. v. Brand. 187 Mass. 417; O’Niel v. Taylor, 59 W. Va. 370.

Under our law Thorn’s lien attached to the oroperty, for all materials furnished by him under ibe contract and used in the building, as of the time that his furnishing the materials and the use of them began. Cushwa v. Improvement &c. As [622]*622sociation, 45 W. Va. 490. The lien as a whole relates to and dates from that time. When execution under a contract begins, the right to lien for the whole of the completed contract attaches at the beginning of performance and takes priority as of that time.

One purchasing premises on which buildings are in process of erection must táke notice of any mechanic’s lien right that has attached prior to his purchase. He must inquire what contracts are in course of execution on a property he is about to buy. He must further inquire what has been done and may. be done under any such contracts that he finds. “A party purchasing premises on which buildings are in the process of erection, having knowledge of the same, is bound to make inquiry as to t'he rights of parties furnishing materials or performing work thereon, and is • charged with constructive, if not actual notice of their lien.” Phillips on Mechanics’ Liens, sec. 227. “The fact that the work is in progress, is a notice to all of the rights of the mechanic, and all conveyances made during that time are made subject to the mechanic’s rights.” Rockel on Mechanics’ Liens, sec. 150. Appellant therefore when he purchased from Barringer was charged with notice of Thorn’s right to a lien for all done and to be done under the contract, and took the property subject to the same. The house was an incompleted one. He was bound to inquire into the rights of those who had done work thereon or furnished the materials therefor, and to view those rights under the law. It is said that as no work had been done on the building for more than sixty days prior to his purchase, he could assume that all incipient or unfiled claims to liens had ended. But he was obliged to go further and inquire .for such continuous contracts as' the one with Thorn, as to which a cessation of work meant nothing if the contract was afterwards carried out. The incompleted state of the house gave appellant notice that partially performed continuous contracts for work or materials were likely to exist as to it. In reason he was bound to know that Barringer, who had begun the building and whom he retained to complete it, could have such contracts and could continue to get materials under them.

Where mechanic’s liens attach as of the time when perform-[623]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carolina Lumber Company v. Cunningham
192 S.E.2d 722 (West Virginia Supreme Court, 1972)
Rural Plumbing & Heating, Inc. v. Hope Dale Realty, Inc.
140 S.E.2d 330 (Supreme Court of North Carolina, 1965)
Hadrup v. Sale
111 S.E.2d 405 (Supreme Court of Virginia, 1959)
Wallace v. Brumback
12 S.E.2d 801 (Supreme Court of Virginia, 1941)
Oglethorpe Savings & Trust Co. v. Morgan
102 S.E. 528 (Supreme Court of Georgia, 1920)
W. Bateson & Co. v. Baldwin Forging & Tool Co.
84 S.E. 887 (West Virginia Supreme Court, 1915)
Huntington Plumbing & Supply Co. v. McGuffin
83 S.E. 194 (West Virginia Supreme Court, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
81 S.E. 846, 73 W. Va. 618, 1914 W. Va. LEXIS 27, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thorn-v-barringer-wva-1914.