Thompson Transport Co. v. Middlestates Construction Co.

397 P.2d 368, 194 Kan. 52, 1964 Kan. LEXIS 448
CourtSupreme Court of Kansas
DecidedDecember 12, 1964
Docket43,822 and 43,860
StatusPublished
Cited by6 cases

This text of 397 P.2d 368 (Thompson Transport Co. v. Middlestates Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thompson Transport Co. v. Middlestates Construction Co., 397 P.2d 368, 194 Kan. 52, 1964 Kan. LEXIS 448 (kan 1964).

Opinion

The opinion of the court was delivered by

Schroeder, J.:

This is an action by Thompson Transport Company, Inc. (appellant) to recover freight charges for transporting bituminous base (road mix) materials for Middlestates Construction Company. Middlestates had a road construction contract with the State Highway Commission of Kansas. The appellant sued Middle-states and also Trinity Universal Insurance Company (appellee), claiming such transportation charges were covered by the G. S. 1949, 68-410 bond signed by Trinity as surety. The trial court *53 entered judgment for Trinity, and appeal has been duly perfected by Thompson Transport Company, Inc.

The question is whether charges for transporting such road materials are covered by the bond given pursuant to G. S. 1949, 68-410.

The preliminary facts and procedural steps necessary to focus the foregoing issue on appeal are conceded by the parties, and we shall not dwell upon them. The facts necessary for a determination of this appeal have been stipulated by the parties. In pertinent part they provide:

“5. That defendant Middlestates Construction Co. on or about July 6, 1961, entered into a contract with the State Highway Commission of Kansas for the construction of 6.007 miles of roadway with a bituminous base (road mix) in Barton County, Kansas, and identified as Project 4-5 K 5097 ( 2); that a copy of said contract is attached hereto as Stipulation Exhibit No. I, and is incorporated herein as if set out in full; that said contract incorporated and included by reference the 1960 Kansas Standard Specifications, a copy of which is attached hereto as Stipulation Exhibit No. 11 and incorporated herein as if set out in full, . . .
“6. That on the 6th day of July, 1961, defendant Middlestates Construction Co., as principal, and defendant Trinity Universal Insurance Co., as surety, executed a G. S. 1949, 68-410, statutory contract bond, which was approved by and filed with the State Highway Commission of Kansas; and that a copy of said bond is attached hereto as Stipulation Exhibit No. Ill and is incorporated herein as if fully set out.
“7. That defendant Middlestates Construction Co., in the performance of said contract, contracted with the Mobil Oil Company for the purchase of bituminous base (road mix) from the latter’s Augusta, Kansas, refinery, which purchase was F. O. B. the refinery.
“8. Pursuant to request by defendant Middlestates Construction Co., on August 9, 1961, plaintiff began transporting said bituminous base (road mix) from the Mobil Oil Company refinery at Augusta, Kansas, to Barton County, Kansas, where it was stored in tanks at the project site and thereafter used and consumed in the construction of said public highway; and that plaintiff continued transporting said materials until November 27, 1961.
“9. Defendant Middlestates Construction Co. is indebted to plaintiff for transporting said materials in the sum of $9,617.13, for which amount plaintiff has made demand, but defendant Middlestates Construction Co. has failed and neglected to pay the same.
‘TO. That defendant Middlestates Construction Co. was given authority for temporary suspension of work on February 2, 1962, ending on or about March 17, 1962; that thereafter the Highway Commission for the State of Kansas made written demands upon said defendant on March 19 and 30, 1962, to begin work; that the Kansas Highway Commission served demand and notice upon defendant Middlestates Construction Co., under Section A 8-8, of 1960 Standard Specifications; that said defendant refused to resume work; *54 and that the project was assumed by Mr. Charles Hulme on April 7, 1962, who completed the project on April 20,1962.
“11. That subsequent to the defendant Middlestates Construction Company’s refusal to pay plaintiff’s account, plaintiff made demand for payment of the same upon Trinity Universal Insurance Co. as surety under said statutory contract bond; that defendant Trinity Universal Insurance Co. informed plaintiff of its contention that its freight bill toas not covered by said statutory contract bond and refused to pay the same or any part thereof and still refuses to do so.
“12. That on or about the 9th day of April, 1962, plaintiff filed an itemized statement under oath with the State Highway Commission, a copy of which is attached hereto as Exhibit No. IV, and is incorporated herein as if set out in full; that said itemized statement is true and correct.
“13. That in transporting said materials, plaintiff used and consumed labor of its employees, its trucks and gasoline, lubricating oils, fuel oils, greases and similar items necessary to transport bituminous base (road mix) from Augusta, Kansas, to the storage tanks at the project site in Barton County, Kansas; that said account is composed entirely of plaintiff’s charges for transporting said materials to the construction site as hereinbefore alleged whereby they were used in and consumed in the construction and completion of this project.” (Emphasis added.)

Pursuant to stipulation No. 9, wherein Middlestates stipulated to the amount of its indebtedness to the appellant, the trial court entered judgment against Middlestates, and it did not appeal. In its contract with the State Highway Commission Middlestates agreed at its “own proper cost and expense to do all the work, furnish all materials and labor necessary to do the work in accordance with the plans and specifications herein described, and in full compliance with all the terms of this agreement and the requirements of the engineer under it.” (Emphasis added.)

The contract further provided:

“It is also understood and agreed that the advertisement, proposal bond,, specifications and plans hereto attached, or hereinbefore referred to are all essential documents of this contract and are a part thereof(Emphasis added.)

The statutory contract bond entered into by Middlestates, as principal, and Trinity Universal Insurance Company, as surety, firmly bound Middlestates and Trinity unto the State of Kansas in the penal sum of $182,983.82 (the full amount of the road construction contract) to be paid the State Highway Commission of Kansas on the conditions set forth in the bond.

The condition of the bond provides:

“. . . If the Principal shall fully and faithfully perform such contract in every respect and properly and promptly complete the work in accordance with the provisions of said contract, plans and specifications, and any additions *55 to or changes in said contract, . . . and shall pay all indebtedness incurred, whether by said Principal,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frickey Ex Rel. Frickey v. Equity Mutual Insurance
576 P.2d 702 (Court of Appeals of Kansas, 1978)
State Ex Rel. Grassie v. Masterson
561 P.2d 796 (Supreme Court of Kansas, 1977)
Tracy v. T & B CONSTRUCTION COMPANY
182 N.W.2d 320 (South Dakota Supreme Court, 1970)
State v. Bob Eldridge Construction Co.
397 S.W.2d 7 (Missouri Court of Appeals, 1965)
Thompson Transport Co. v. Middlestates Construction Co.
403 P.2d 999 (Supreme Court of Kansas, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
397 P.2d 368, 194 Kan. 52, 1964 Kan. LEXIS 448, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thompson-transport-co-v-middlestates-construction-co-kan-1964.