This text of 149 N.W. 300 (Thompson-McDonald Lumber Co. v. Morawetz) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thompson-McDonald Lumber Co. v. Morawetz, 149 N.W. 300, 127 Minn. 277, 1914 Minn. LEXIS 878 (Mich. 1914).

Opinion

Brown, 0. J.

Defendant Morawetz entered into a contract with defendant Offrell for tbe construction of a building upon premises owned by [278]*278•him, Offrell agreeing to furnish all labor and material. On February 27, 1912, Offrell, the contractor, purchased from plaintiff certain material to be used in the construction of the building, of the value of $288.24, and the same was used for that purpose. On March 30, 1912, the contractor purchased other and additional material for the same use and purpose of the value of $9.71. The material so furnished was not paid for, and within 90 days from the date of the second item just mentioned, but not within 90 days from the date of the first item, plaintiff duly perfected a lien against the premises and thereafter brought this action to foreclose the same. Plaintiff had judgment and defendant Morawetz appealed.

The cause comes to this court upon the findings, the evidence not being returned, and the question presented is whether the findings of fact support the conclusions of law. Whether the conclusions of law are so supported depends upon the question, with reference to which the facts are not in dispute, whether the second item of material above mentioned was lienable under the statutes. If it was not, the lien statement was not fixed in time and the lien fails. If it was the judgment must be affirmed. The facts are in brief as follows:

The building under construction was located in Liberty Heights, in Dakota county, and plaintiff’s place of business, dealer in lumber and building material, was at Minneapolis. In substance and effect the trial court found, in respect to the item of material in question, that on March 30, 1912, the contractor purchased of plaintiff and plaintiff sold and delivered to him for use in the construction of the building certain material of the value of $9.71; that the contractor ordered the material shipped to him from Minneapolis, and that in pursuance thereof plaintiff delivered the same to a common carrier consigned and to be shipped to the contractor at the place where the building was under construction; that no part of the material was delivered upon the premises or taken there by the contractor or any other person, and no part thereof was ever used in the construction of the building. What became of the material does not appear.

The contention of defendant is that as no part of the material was [279]*279used in tbe building, or ever delivered upon tbe premises where tbe same was being constructed, tbe value thereof was not a lienable item, and, further, since tbe lien was not perfected within 90 days from tbe date of tbe first item of material, that tbe court was in error in ordering judgment for plaintiff.

Our statute, section 7020, G. S. 1913, provides that whoever contributes to tbe improvement of any real estate by furnishing labor or material for tbe construction of a building thereon, whether under contract with tbe owner, contractor or subcontractor, shall have a lien upon tbe premises for tbe value of tbe labor or material so furnished. Tbe statute, being remedial in character, has always received a liberal construction and application. Johnson v. Starrett, supra, p. 138, 149 N. W. 6; 2 Dunnell, Minn. Dig. § 6033. Similar statutes in other states have been construed strictly and tbe rule announced that there can be no lien for material furnished, unless it be actually incorporated in the building so as to form a part of the structure. Some of the authorities so holding are referred to by Mr. Justice Brown in the Johnson case, supra, and others, including those holding to the contrary, will be found in a note to Pittsburg Plate Glass Co. v. Leary (S. D.) 31 L.R.A.(N.S.) 746. But that rule of strict construction has never been applied in this state. On the contrary we have held that actual incorporation of the material into the building is not essential to the right of lien. Burns v. Sewell, 48 Minn. 425, 51 N. W. 224; Hickey v. Collom, 47 Minn. 565, 50 N. W. 918; Combination Steel & Iron Co. v. St. Paul City Ry. Co. 52 Minn. 203, 53 N. W. 1144. We have consistently followed this rule, and it is supported by the courts of other states having similar statutes. Whether a delivery of material upon the premises where the building is being constructed is essential to the right of lien has not heretofore been presented in a case between the owner of the property and the lien claimant. While such a delivery has been said in some of the opinions to be necessary, the question was not involved in the particular case, and the question is an open one in this state. The case of Wentworth v. Tubbs, 53 Minn. 388, 55 N. W. 543, presented a controversy between a lien claimant and a mortgagee, and involved the question whether the [280]*280lien there before tbe court was prior to a mortgage upon tbe premises, wbicb was executed and recorded before tbe improvements thereon were commenced. It was held that as against tbe mortgagee the material must be delivered upon tbe premises, or tbe improvement be actually under way, in order that tbe lien may take priority-over a mortgage executed before tbe commencement of tbe work. Tbe case is not here in point. We have also held that a delivery of material upon tbe premises is not necessary to give life to the lien in those cases where a delivery is prevented by tbe owner. This includes instances where tbe material is specially prepared in conformity with special orders. John Paul Lumber Co. v. Hormel, 61 Minn. 303, 63 N. W. 718; Berger v. Turnblad, 98 Minn. 163, 107 N. W. 543, 116 Am. St. 353. And notwithstanding expressions found in tbe opinions that delivery upon tbe premises is usually necessary, tbe logical result of our decisions leads to tbe conclusion that, as against tbe owner, material sold and in good faith delivered to the contractor for use in the building entitles the materialman to a lien, whether the material be in fact delivered upon the premises or not. If it be delivered to the contractor for use in the construction work, it would seem a strain to hold, and clearly a departure from the logic of prior decisions, that the materialman is bound to follow the contractor to the premises and see to it that the material is taken to and deposited thereon. Our decisions are to the effect that if the material be in fact delivered upon the premises the subsequent act of the contractor, even though fraudulent, in removing the same and converting it to his own personal use does not defeat the lien. If such removal does not defeat the lien, it is a little difficult to understand why the failure of the contractor, to whom possession has been given, to take tbe material to tbe premises at all should defeat the lien. If in fact delivered upon the premises the contractor could, under the decisions referred to, within an hour thereafter cart it away without prejudicing tbe rights of tbe lien claimant. In view of this situation no benefit can accrue to the owner by an actual delivery upon the premises, and his possession would in no legal respect be protected thereby. If the material in a given case be delivered into the physical possession of the owner, it seems clear that [281]*281no court would bold that his failure to deliver the same upon the premises would affect the rights of the materialman. We can conceive of no valid reason for applying a different rule where the delivery is to the contractor, the agent and representative of the owner, and for whose acts the owner is responsible to the extent at least that the premises are liable under the statutes for the value of the material so furnished.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Koza v. RYAN DEVELOPMENT, INC.
384 N.W.2d 233 (Court of Appeals of Minnesota, 1986)
Tabet v. Davenport
260 P.2d 722 (New Mexico Supreme Court, 1953)
Lake Street Sash & Door Co. v. D. H. Evans Co.
243 N.W. 110 (Supreme Court of Minnesota, 1932)
Moorhead Lumber Co. v. Remington Packing Co.
206 N.W. 653 (Supreme Court of Minnesota, 1925)
Whitfield v. Kentucky Sales Corporation
278 S.W. 105 (Court of Appeals of Kentucky (pre-1976), 1925)
Henry Simons Lumber Co. v. Schnobrich
198 N.W. 406 (Supreme Court of Minnesota, 1924)
Lampert Lumber Co. v. Thanning
197 N.W. 269 (Supreme Court of Minnesota, 1924)
Northland Pine Co. v. Northern Insulating Co.
177 N.W. 635 (Supreme Court of Minnesota, 1920)
State Loan Co. v. White Earth Coal Mining Brick & Tile Co.
157 N.W. 834 (North Dakota Supreme Court, 1916)
Minneapolis Sash & Door Co. v. Hedden
154 N.W. 511 (Supreme Court of Minnesota, 1915)
Lamoreaux v. Andersch
150 N.W. 908 (Supreme Court of Minnesota, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
149 N.W. 300, 127 Minn. 277, 1914 Minn. LEXIS 878, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thompson-mcdonald-lumber-co-v-morawetz-minn-1914.