Thomason v. Keeney

70 S.E. 220, 8 Ga. App. 852, 1911 Ga. App. LEXIS 176
Court of Appeals of Georgia·Decided January 31, 1911·No. 2727; 2728·Published·Cited by 3 cases

Opinion

Hill, C. J.

Keeney brought suit against Thomason as principal and the iEtna Indemnity Company as surety, on a contractor’s bond, seeking to recover for the default of the contractor in building a house. The jury found a verdict for the plaintiff, for the full amount sued for, and the defendants filed separate motions for a new trial, which were overruled, and separate writs of error were sued out. When the case was before this court on a former occasion, it was held that the petition stated a cause of action, and the •judgment of the lower court, overruling a demurrer thereto, was affirmed. Thomason v. Keeney, 4 Ga. App. 131 (63 S. E. 410). The questions involved are practically the same in both cases. Besides the usual general grounds, the motion for new trial contains numerous special assignments of error, some of them applicable only to the surety company. We will decide those which we deem controlling. The general grounds may be disposed of by the statement that a careful consideration of the evidence shows that-every essential allegation in the petition was proved, and the verdict in favor of- the plaintiff should be allowed to stand, unless the trial judge committed some prejudicial error of law in his rulings or charge, or refusal to charge, as assigned in the amended motion for a new trial.

1. The first assignment of error insisted upon is that the court erred in refusing to charge the jury as follows: “ I charge you that if the plaintiff by any act of omission or commission increased the risk of the surety on the bond, or exposed the surety to greater liability, then such act discharged the surety from any liability, and defeats plaintiff’s right to recover against it.” This was one of the defenses relied upon by the surety, and it is insisted that it was supported by the evidence. Unquestionably the request embodied a sound abstract principle of law. The defendant, however, specially pleaded and introduced evidence to prove the specific acts charged against the plaintiff, which it was alleged had increased the surety’s risk and resulted in its discharge. The judge fully charged the jury the law applicable to these special pleas and to the pertinent evidence. In other words, the court, in making a concrete application of the abstract principle stated in the request, gave the defendant the full benefit of the principle, and in a clearer and more satis[854] factory maimer than would have been done if he had simply given the requested instruction .embodying the rule as to the rights of sureties in the abstract. A careful examination of the evidence leads to the conclusion that none of these special pleas alleging acts of the plaintiff or obligee which had increased the risk of the surety were sustained; but on the contrary, the evidence preponderated in favor of the contention of the plaintiff that he had paid oiit no money to the principal in the bond, except in accordance with its express terms, and that all of his acts before and after the default of the contractor were fully authorized.

2. The next error assigned is that the court erred in refusing to charge the jury as follows: “I charge you that the law imposes on the owner the duty to see that such parts of the contract price as he ■ pays to the contractor improving real estate are applied by him first in payment for labor and material employed and used in performance of the contract. If you believe, from the evidence, that the plaintiff in-this case failed to perform his duty which the law imposes, and if you believe, from the evidence, further that contractor Thomason failed'to thus apply all that was paid to him by plaintiff on the contract price, then I charge you that such failure on the part of the plaintiff to perform this duty operated to increase the risk of the surety, the A3tna Indemnity Company, and discharges it from liability on its bond.” We do not think that this request embodied a sound principle of law. True, the owner is bound to see that money paid by him to the contractor is applied to claims for material and labor unpaid at the date of the payment to the contractor, but the owner’s failure to do this does not increase the risk of the surety or discharge him from liability on the bond. It simply results in making the owner liable for such claims to the employees of the contractor and to materialmen who had furnished to the contractor the material to go into the house. It is only a breach of a legal duty which is imposed upon the owner for the protection of both himself and the employees and materialmen. But the risk that a contractor may not make the proper application of the money which is paid to him by the owner is one of the risks, and probably the .chief risk, against which the owner is protected by the contractor’s bond. If the owner of the building were required to see to the proper application by the contractor of all the money paid to him within the limits of the contract price, there would be little rea[855] son or necessity for taking a bond, for in that event there could not' be loss to the owner by any improper application of his money by the contractor. The decision in the case of Green v. Farrar Lumber Co., 119 Ga. 30 (46 S. E. 62), relied upon by the plaintiff in error in support of his request to charge, does not sustain the proposition as contended for by him. That decision is simply an enunciation of the statute that requires the owner of property improved by a contractor to see that money paid by him to the contractor is applied to claims for labor and material not paid for at the date of the payment to the contractor, or else incur liability himself for such claims in the event the contractor fails to pay them. (Civil Code of 1895, § 2801, par. 2, as amended by the act of 1899 (Ácts'1899, p. 33)). There is nothing in this decision that gives color to the contention that it is the duty of the owner of the property to see to the proper application of the money which lie pays to the contractor, under penalty of discharging the surety from liability on the contractor’s bond. As before stated, the proper application of the money paid by the owner to the contractor is" a risk which the surety assumes when he signs the bond as surety, and it is a danger' from which the bond protects the owner.

Free access — add to your briefcase to read the full text and ask questions with AI

Thomason v. Keeney, 70 S.E. 220, 8 Ga. App. 852, 1911 Ga. App. LEXIS 176 (Ga. Ct. App. 1911).

70 S.E. 220 (Thomason v. Keeney) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Standard Accident Insurance v. Bear
184 So. 97 (Supreme Court of Florida, 1938)
Wise v. Thurman
93 S.E. 112 (Court of Appeals of Georgia, 1917)
Massachusetts Bonding & Insurance v. Realty Trust Co.
73 S.E. 1053 (Supreme Court of Georgia, 1912)