Green v. Farrar Lumber Co.

46 S.E. 62, 119 Ga. 30, 1903 Ga. LEXIS 11
Supreme Court of Georgia·Decided November 14, 1903·Published·Cited by 50 cases

Opinion

Cobb, J.

Mrs. Green filed an equitable petition against Jones and others, in which she alleged that she had made a contract with Jones to erect a dwelling-house at a cost of $1,100 ; that the house was completed with the exception, of several small items mentioned in the petition; that, after deducting what she had paid on the contract and the reasonable cost of completing the house, there was still due Jones $183.40, which she asked that she might pay into court, in order that Jones and the other defendants might determine in what proportion they were entitled to the same. The case came on to be tried upon an agreed statement of facts, in which it was set forth that on July 18, 1901, Mrs. Green entered into a written contract with Jones, whereby he was to furnish all material and labor and do all the work necessary to construct a dwelling-house according to the plans and specifications referred to in the contract, the contract price to be paid weekly as the work progressed, Mrs. Green to retain twenty per cent, of the contract price as security for the completion of the house; that as the work progressed she paid to Jones, or to materialmen and laborers at his request, $884.40 in the aggregate, all of this amount having been paid to Jones, except $59.40, which was paid directly to parties who had lawful claims against Jones for material or labor; that during the progress of the work Jones paid to materialmen and laborers $1,013; that when he quit work the house was in such a condition that it would cost $52.71 to complete it according to contract; that none of. the parties to whom either plaintiff or Jones had paid sums of money for work or material had filed liens upon the house and lot; that the actual cost of the house for work done and material furnished [32] was $1,632, or $532 more than the contract price; that certain parties named have claims against Jones, amounting in the aggregate to $510.78, for material furnished and work done, and have filed and recorded their liens in due time and in the manner prescribed by law. The judge held that Mrs. Green “ was liable to all persons doing work on the house in question or furnishing material therefor, for such proportionate part of the claim of each as the contract price, less the amount she was forced to pay to complete the job, bore to the amount which the building actually cost W. T. Jones, the contractor.” In accordance with this holding he entered a decree against Mrs. Green in favor of the different parties who had filed liens, for sums aggregating $277.25. To this decree Mrs. Green excepted on the ground that it required her to pay a sum exceeding the contract price of the house; and those in whose favor the decree was rendered excepted on the ground that the court erred in not decreeing that they should be paid their claims in full.

The determination of this question depends upon what is the proper construction of Civil Code, §2801, as amended by the act of 1899. See Acts 1899, p. 33, Van Epps’ Code Supp. § 6176. Paragraph one of the section just referred to provides that all mechanics of every sort who take no personal security for work done or material furnished in improving real estate, and all contractors, materialmen, and persons furnishing material for the improvement of real estate, shall have special liens on such real estate. Section 2, as amended by the act of 1899, provides: “When work done or material furnished for the improvement of real estate is done or may be furnished upon the employment of a contractor, or some other person than the owner, then, and in that case, the lien given by this section shall attach upon the real estate improved, as against such true owner, for the amount of the work done or material furnished, unless such true owner shows that such lien has been waived in writing, or produces the sworn statement of the contractor, or other person, at whose instance the work was done, or material was furnished, that the agreed price or reasonable value thereof has been paid; provided, that in no event shall the aggregate amount of liens set up hereby exceed the contract price of the improvements made.” It is well settled that laws giving to a creditor a lien upon the property [33] of his debtor, being in derogation of common law, are to be strictly construed against the creditor and liberally in favor of the debtor. If there are degrees of strict construction, certainly an act of the General Assembly which has for its purpose the giving of a lien upon property of one in favor of the creditor of another should be dealt with according to the strictest rules of strict construction. The purpose of this act is to protect materialmen and laborers for work done and material furnished to contractors who fail or refuse to pay. Under it the liability of the contractor to his materialmen and laborers is transferred to the person who employs the contractor. It would seem that if the money due to the contractor by the owner is actually used by the contractor in discharging just and valid claims of materialmen and laborers, the purposes of the law have been accomplished. And in the light of the fact that the act expressly declares that in no event shall the claims of materialmen and laborers against the owner and contractor exceed the contract price of the improvement, if the owner can’ show that all amounts paid by him to the contractor have been appropriated to the payment of valid and just claims of materialmen and laborers, he should not be held liable for any additional sum, notwithstanding the contractor may be indebted to other materialmen and laborers ; that is to say, the owner is bound for the contract price and is bound to see that to the extent of this price the amounts paid to the contractor are appropriated by him to the payment of valid claims of materialmen and laborers; but if the aggregate claims of materialmen and laborers exceed the contract price, the loss should fall upon them rather than upon the owner. If the owner pays to the contractor any sum of money which is not applied to the discharge of claims of materialmen and laborers, then the owner would be liable to the extent of the amount not so applied, in the event any materialmen or- laborer had an unsatisfied claim against the contractor and asserted his lien in due time and in the proper manner.

Free access — add to your briefcase to read the full text and ask questions with AI

Green v. Farrar Lumber Co., 46 S.E. 62, 119 Ga. 30, 1903 Ga. LEXIS 11 (Ga. 1903).

46 S.E. 62 (Green v. Farrar Lumber Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Donna Lang v. Brand-Vaughan Lumber Co., Inc.
Court of Appeals of Georgia, 2016
Lang v. Brand-Vaughan Lumber Co.
792 S.E.2d 461 (Court of Appeals of Georgia, 2016)
Phillips, Inc. v. Historic Properties of America, LLC.
581 S.E.2d 389 (Court of Appeals of Georgia, 2003)
U. S. Filter Distribution Group, Inc. v. Barnett
538 S.E.2d 739 (Supreme Court of Georgia, 2000)
US Filter Distribution Group v. Barnett
538 S.E.2d 739 (Supreme Court of Georgia, 2000)
Browning v. Gaster Lumber Co.
475 S.E.2d 576 (Supreme Court of Georgia, 1996)
Gaster Lumber Co. v. Browning
465 S.E.2d 524 (Court of Appeals of Georgia, 1996)
Palmer v. Duncan Wholesale, Inc.
413 S.E.2d 437 (Supreme Court of Georgia, 1992)
F. S. Associates, Ltd. v. McMichael's Construction Co.
399 S.E.2d 479 (Court of Appeals of Georgia, 1990)
Electrical Distributors, Inc. v. Turner Construction Co.
395 S.E.2d 879 (Court of Appeals of Georgia, 1990)
Mayer Electric Supply Co. v. Federal Insurance
393 S.E.2d 270 (Court of Appeals of Georgia, 1990)
Bishop v. Forsyth Paving Contractors, Inc.
352 S.E.2d 198 (Court of Appeals of Georgia, 1986)
Taverrite v. Lowe's of Franklin, Inc.
304 S.E.2d 78 (Court of Appeals of Georgia, 1983)
Sanford v. Hodges Builders Supply, Inc.
303 S.E.2d 294 (Court of Appeals of Georgia, 1983)
Shuman-Mann Supply Co. v. Weaver
291 S.E.2d 562 (Court of Appeals of Georgia, 1982)
Henderson v. Mitchell Engineering Co.
279 S.E.2d 750 (Court of Appeals of Georgia, 1981)
Pugh v. Norsworthy
274 S.E.2d 106 (Court of Appeals of Georgia, 1980)
JONES MERCANTILE COMPANY v. Lyn-Har, Inc.
267 S.E.2d 251 (Supreme Court of Georgia, 1980)
Rochester v. Dixon's Concrete Products, Inc.
267 S.E.2d 819 (Court of Appeals of Georgia, 1980)
Thompson v. BRANNEN BUILDING SUPPLY
264 S.E.2d 498 (Court of Appeals of Georgia, 1980)