Thomas Companies v. United Fire & Casualty Co. (In Re Thomas Companies)

166 B.R. 677, 1994 Bankr. LEXIS 647, 1994 WL 176326
CourtUnited States Bankruptcy Court, C.D. Illinois
DecidedMay 4, 1994
Docket19-80008
StatusPublished

This text of 166 B.R. 677 (Thomas Companies v. United Fire & Casualty Co. (In Re Thomas Companies)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, C.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thomas Companies v. United Fire & Casualty Co. (In Re Thomas Companies), 166 B.R. 677, 1994 Bankr. LEXIS 647, 1994 WL 176326 (Ill. 1994).

Opinion

OPINION

WILLIAM V. ALTENBERGER, Chief Judge.

The Debtor entered into a construction contract with the State of Illinois Capitol Development Board for heating and air conditioning and ventilating work for the Health Sciences Building at Sangamon State University (PROJECT). The Defendant issued a performance, labor and materialmen’s bond, as surety for the Debtor, on the PROJECT. Prior to the PROJECT being completed, the Debtor filed a Chapter 11 proceeding in bankruptcy. The Debtor continued to work on the PROJECT while it negotiated with the Defendant concerning the terms of its continuing to work on the PROJECT. Because the Debtor did not have sufficient funds to finance the continuing work and no payments were forthcoming, the Debtor was forced to stop all work on the PROJECT. The Debtor then filed a motion to reject the contract, which this Court approved. The Defendant took over and completed the PROJECT.

*678 On January 31, 1992, the Debtor filed its plan of reorganization which provided in ¶ 11.06(1) as follows:

11.06. Executory Contracts; Stale Liens.
1. Executory Contracts and Unexpired Leases. All executory contracts and unexpired leases of the debtor which have not previously been assumed, including but not limited to any obligation to provide Golf Course memberships, except as set forth herein shall be deemed rejected on confirmation. Notwithstanding the foregoing, the debtor reserves the right to apply to the court for approval of its election to assume a particular executory contract or unexpired lease prior to confirmation. Each person or entity who is a party to an executory contract or unexpired lease that is deemed rejected on confirmation and not prior thereto, shall be entitled to file a claim of the type described in § 502(g) of the Code within seven days after confirmation; provided, duplicate copies of any such claim are concurrently received by the debtor through its attorneys.

On March 4, 1992, the Debtor filed this adversary proceeding. On August 10,1992, the Defendant filed a proof of claim for $360,-412.47. On October 3, 1992, the Debtor’s plan of reorganization was confirmed.

The Debtor filed this adversary proceeding against the Illinois Capital Development Board and the Defendant, seeking both a retainage for pre-petition work and payment for post-petition work. Both Defendants filed a motion to dismiss the proceeding. By agreement of the parties, the Debtor’s claim against the Illinois Capital Development Board was dismissed without prejudice. The Debtor also agreed that it had no right to the pre-petition retainage because UNITED’s costs to complete the project exceeded the retainage plus the balance due on the contract, leaving only the issue of the Debtor’s right to payment for post-petition work.

In an opinion and order filed August 26, 1992, this Court ruled that a trial was necessary:

It is the Debtor’s position that it is entitled to payment of its post-petition claim for labor and materials based upon either a post-petition contractual relationship or a post-petition quasi-eontractual relationship. In response, UNITED FIRE denies that there was a post-petition agreement and contends that there cannot be relief in quantum meruit under an implied contract where there is an express contract.
This Court finds that UNITED FIRE’s motion to dismiss must be denied. If the Debtor can prove that it had an oral contract with UNITED FIRE, separate and apart from the original contract with CDB, for the work performed post-petition, it will prevail on its claim. See In re Jandous Electric Construction Corp. [1989 WL 81139], 1989 Bankr. LEXIS 402 (Bkrtcy.S.D.N.Y.1989). While UNITED FIRE disputes such an agreement, that is an issue to be decided at trial.
In addition, this Court notes that while some courts have permitted a debtor to recover on a quasi-contract theory under a suspended unassumed executory contract which was later rejected by the debtor, (In re Docktor Pet Centers, Inc. [1992 WTL 189634], 1992 Bankr. LEXIS 1151 (Bkrtcy.D.Mass.1992); In re Auto Dealer Services, Inc. [110 B.R. 68], 1990 Bankr. LEXIS 39 (Bkrtey.M.D.Fla.1990)), other courts have not. As the court in In re Jandous Electric Construction Corp., supra, noted:
There is no question that the debtor’s commencement of its Chapter 11 ease on December 1,1988 did not signify a repudiation or breach of its subcontract with Slattery. However, the debtor’s failure, after December 7, 1988, to perform any work at the Transit Authority project pursuant to the payment terms of the contract, except for the emergency interim work outside the contract on a time and materials basis, sufficiently evidenced the debtor’s breach of its subcontract with Slattery. The debtor’s abandonment of the project after December 23, 1988 conclusively established the debtor’s breach of its subcontract. Having inexcusably defaulted under the subcontract, the debtor may not recover any progress payments for the work it performed in October and November of *679 1988. It is well settled that a party who inexcusably defaults may not recover, even on a quantum meruit basis, notwithstanding that the defendant did receive some benefit. (Citations omitted.) There can be no partial recovery by a breaching contractor for the reasonable value of its work unless it amounts to substantial performance of the entire contract. (Citation omitted.)
In view of this Court’s ruling that a trial is necessary, and given that the law is unsettled and that quantum meruit relief is an equitable theory of recovery, this Court will not decide the issue until the facts have been fully developed at trial.

In answering the complaint, the Defendant asserted a counterclaim, alleging that the Debtor had assumed the contract and then defaulted and that the Defendant was entitled to a post-petition claim and expense of administration in the amount of $500,000.00, as costs incurred in completing performance under the contract, and attorney’s fees and costs. The Defendant filed a demand for a jury trial and moved to withdraw the reference from the bankruptcy court. The district court ruled that the Defendant, by filing a proof of claim in the bankruptcy proceedings, had subjected itself to the bankruptcy court’s equitable jurisdiction and waived its rights to a trial by jury.

The Debtor filed a motion for summary judgment on the counterclaim asserted by the Defendant. The Defendant filed a motion for summary judgment on both its counterclaim and the complaint filed by the Debt- or. A hearing was held and the motions were taken under advisement. The Debtor contends that there remains the factual issue of whether the parties entered into a new contract post-petition, and that it did not assume the pre-petition contract, but rejected it with this Court’s approval. The Defendant asserts that by continuing to perform, the Debtor assumed the contract as a matter of law. The Defendant also argues that there is no factual support for the Debtor’s position that a new contract was entered into between the Defendant and the Debtor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
166 B.R. 677, 1994 Bankr. LEXIS 647, 1994 WL 176326, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thomas-companies-v-united-fire-casualty-co-in-re-thomas-companies-ilcb-1994.