Thill v. Modern Erecting Company

136 N.W.2d 677, 272 Minn. 217, 1965 Minn. LEXIS 653
Supreme Court of Minnesota·Decided September 3, 1965·No. 39448, 39449·Published·Cited by 41 cases

Opinion

Rogosheske, Justice.

Defendants Johnson, Drake & Piper, Inc.,(J. D. & P.) and Modem Erecting Company (Modem) appeal from denials of separate motions for judgment upon amended findings of fact or for a new trial.

The accident from which this case arose occurred on June 23, 1960, during the building of a hangar and one-story office and shop building for Western Airlines at Minneapolis-St. Paul International Airport-Wold-Chamberlain Field. J. D. & P. was the general contractor for the job. Jesco, Inc., was a subcontractor for pouring certain concrete work including the roof slab; J. L. Shiely Company supplied the concrete for the job; Modern Erecting Company furnished a truck crane and two of its employees, Harlan Stowe and Wesley Janshen, at an hourly rental to J. D. & P. to accomplish pouring the roof slab. Ashbach Construction Company, plaintiff’s employer, was the subcontractor for certain earth-moving work around the building.

On the day of the accident Ashbach sent plaintiff, Edward Thill, and two other employees to backfill around a fuel off tank located on the southeast corner of the building under construction. On the same day J. D. & P. scheduled pouring the roof slab. The crane furnished by Modern was set up about midway along the 51-foot east wall of the building for the purpose of elevating bucketfuls of concrete to the roof where they would be poured by Jesco workmen. After 15 or 20 loads had been lifted, the crane, midway in swinging a load to the roof, tipped on its side. The boom fell directly on the plaintiff as he sat on his tractor seat, causing injuries from which he became a paraplegic.

Plaintiff brought action based on negligence against J. D. & P., Modern, Shiely, and Jesco. Ashbach was brought into the action by the third-party complaint filed by Modern, as were Modern’s employees, Stowe *221 and Janshen. Various cross-claims were made among the defendants, none of which are significant on this appeal except J. D. & P.’s claim against Modern for common-law indemnity and its claim against Jesco for contractual indemnity.

By special verdict the jury found causal negligence by J. D. & P., Modem, and Janshen, and that Shiely, Ashbach, and Jesco were not negligent. The court found negligence on the part of Stowe, who had answered but had appeared only as a witness. The court also found as a matter of law that the parties were not engaged in a common enterprise, and it denied J. D. & P.’s claims for indemnity. The court thus absolved Shiely, Jesco, and Ashbach and placed liability equally on J. D. & P. and Modem as joint tortfeasors. Modern was granted indemnity against its two negligent employees, Stowe and Janshen. Although the jury awarded damages of $642,400, the court found any amount above $375,000 excessive and granted J. D. & P.’s and Modem’s motions for new trial unless plaintiff accepted a reduction of the verdict to $375,000. Plaintiff filed a written acceptance but he seeks on appeal to have the verdict reinstated.

Because the issues presented concern placing ultimate liability among the several defendants it is necessary to set out in considerable detail the evidence relevant to their relationships and each one’s part in the mishap.

The voluminous record contains few conflicts in the testimony. Determining the cause of the crane’s tipping and which participants are to be held liable for negligence is essentially a problem of choosing between divergent inferences from undisputed testimony and facts. We, of course, are committed to those inferences which tend to support the decision below.

On the day of the accident plaintiff and two fellow employees of Ash-bach arrived at the construction site about 7:30 a. m. Their employer had instructed them to backfill around a large fuel tank which had been placed in a hole at the southeast corner of the partially constructed building. The dirt from the excavation was piled in two heaps close to the hole. Plaintiff commenced to move this dirt into the hole with a small back-hoe tractor while the other two employees tamped. Two or three days previously, J. D. & P., the general contractor, had notified Ashbach that the hole could be filled.

*222 The seven or eight man crew of Jesco arrived on the job at about 8 a. m. Their plan was to pour the concrete roof slab in “passes” along the width of the budding’s roof. The budding ran 252 feet east and west, and 51 feet on its north-south side. Its height was 18 feet. The Jesco men planned to pour passes 10 to 12 feet wide in strips running the width of the budding, starting at the north side.

Free access — add to your briefcase to read the full text and ask questions with AI

Thill v. Modern Erecting Company, 136 N.W.2d 677, 272 Minn. 217, 1965 Minn. LEXIS 653 (Mich. 1965).

136 N.W.2d 677 (Thill v. Modern Erecting Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

David Finazzo v. Fire Equipment Company
918 N.W.2d 200 (Michigan Court of Appeals, 2018)
Zosel v. Minn-Dak Farmers' Cooperative, Inc.
463 F. Supp. 2d 960 (D. Minnesota, 2006)
Robert Reimer v. City of Crookston
326 F.3d 957 (Eighth Circuit, 2003)
Reimer v. City Of Crookston
326 F.3d 957 (Eighth Circuit, 2003)
Larimore v. Carolina Power & Light
531 S.E.2d 535 (Court of Appeals of South Carolina, 2000)
Sutherland v. Barton
570 N.W.2d 1 (Supreme Court of Minnesota, 1997)
Zimmer v. Carlton County Co-Op Power Ass'n
483 N.W.2d 511 (Court of Appeals of Minnesota, 1992)
Crown Holding Corp. v. Larson
410 N.W.2d 373 (Court of Appeals of Minnesota, 1987)
Conover v. Northern States Power Co.
313 N.W.2d 397 (Supreme Court of Minnesota, 1981)
Lemmer v. IDS Properties, Inc.
304 N.W.2d 864 (Supreme Court of Minnesota, 1980)
Ahrenholz v. Hennepin County
295 N.W.2d 645 (Supreme Court of Minnesota, 1980)
Sorenson v. Kruse
293 N.W.2d 56 (Supreme Court of Minnesota, 1980)
Keith Vagle v. Pickands Mather & Company
611 F.2d 1212 (Eighth Circuit, 1980)
Tolbert v. Gerber Industries, Inc.
255 N.W.2d 362 (Supreme Court of Minnesota, 1977)
Johnson v. Serra
521 F.2d 1289 (Eighth Circuit, 1975)
Sorenson v. Safety Flate, Inc.
216 N.W.2d 859 (Supreme Court of Minnesota, 1974)
Caspersen v. Webber
213 N.W.2d 327 (Supreme Court of Minnesota, 1973)
Keefer v. Al Johnson Construction Co.
193 N.W.2d 305 (Supreme Court of Minnesota, 1971)
Thill v. Modern Erecting Company
193 N.W.2d 298 (Supreme Court of Minnesota, 1971)