Thill v. Modern Erecting Company

136 N.W.2d 677, 272 Minn. 217, 1965 Minn. LEXIS 653
CourtSupreme Court of Minnesota
DecidedSeptember 3, 1965
Docket39448, 39449
StatusPublished
Cited by41 cases

This text of 136 N.W.2d 677 (Thill v. Modern Erecting Company) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thill v. Modern Erecting Company, 136 N.W.2d 677, 272 Minn. 217, 1965 Minn. LEXIS 653 (Mich. 1965).

Opinion

Rogosheske, Justice.

Defendants Johnson, Drake & Piper, Inc.,(J. D. & P.) and Modem Erecting Company (Modem) appeal from denials of separate motions for judgment upon amended findings of fact or for a new trial.

The accident from which this case arose occurred on June 23, 1960, during the building of a hangar and one-story office and shop building for Western Airlines at Minneapolis-St. Paul International Airport-Wold-Chamberlain Field. J. D. & P. was the general contractor for the job. Jesco, Inc., was a subcontractor for pouring certain concrete work including the roof slab; J. L. Shiely Company supplied the concrete for the job; Modern Erecting Company furnished a truck crane and two of its employees, Harlan Stowe and Wesley Janshen, at an hourly rental to J. D. & P. to accomplish pouring the roof slab. Ashbach Construction Company, plaintiff’s employer, was the subcontractor for certain earth-moving work around the building.

On the day of the accident Ashbach sent plaintiff, Edward Thill, and two other employees to backfill around a fuel off tank located on the southeast corner of the building under construction. On the same day J. D. & P. scheduled pouring the roof slab. The crane furnished by Modern was set up about midway along the 51-foot east wall of the building for the purpose of elevating bucketfuls of concrete to the roof where they would be poured by Jesco workmen. After 15 or 20 loads had been lifted, the crane, midway in swinging a load to the roof, tipped on its side. The boom fell directly on the plaintiff as he sat on his tractor seat, causing injuries from which he became a paraplegic.

Plaintiff brought action based on negligence against J. D. & P., Modern, Shiely, and Jesco. Ashbach was brought into the action by the third-party complaint filed by Modern, as were Modern’s employees, Stowe *221 and Janshen. Various cross-claims were made among the defendants, none of which are significant on this appeal except J. D. & P.’s claim against Modern for common-law indemnity and its claim against Jesco for contractual indemnity.

By special verdict the jury found causal negligence by J. D. & P., Modem, and Janshen, and that Shiely, Ashbach, and Jesco were not negligent. The court found negligence on the part of Stowe, who had answered but had appeared only as a witness. The court also found as a matter of law that the parties were not engaged in a common enterprise, and it denied J. D. & P.’s claims for indemnity. The court thus absolved Shiely, Jesco, and Ashbach and placed liability equally on J. D. & P. and Modem as joint tortfeasors. Modern was granted indemnity against its two negligent employees, Stowe and Janshen. Although the jury awarded damages of $642,400, the court found any amount above $375,000 excessive and granted J. D. & P.’s and Modem’s motions for new trial unless plaintiff accepted a reduction of the verdict to $375,000. Plaintiff filed a written acceptance but he seeks on appeal to have the verdict reinstated.

Because the issues presented concern placing ultimate liability among the several defendants it is necessary to set out in considerable detail the evidence relevant to their relationships and each one’s part in the mishap.

The voluminous record contains few conflicts in the testimony. Determining the cause of the crane’s tipping and which participants are to be held liable for negligence is essentially a problem of choosing between divergent inferences from undisputed testimony and facts. We, of course, are committed to those inferences which tend to support the decision below.

On the day of the accident plaintiff and two fellow employees of Ash-bach arrived at the construction site about 7:30 a. m. Their employer had instructed them to backfill around a large fuel tank which had been placed in a hole at the southeast corner of the partially constructed building. The dirt from the excavation was piled in two heaps close to the hole. Plaintiff commenced to move this dirt into the hole with a small back-hoe tractor while the other two employees tamped. Two or three days previously, J. D. & P., the general contractor, had notified Ashbach that the hole could be filled.

*222 The seven or eight man crew of Jesco arrived on the job at about 8 a. m. Their plan was to pour the concrete roof slab in “passes” along the width of the budding’s roof. The budding ran 252 feet east and west, and 51 feet on its north-south side. Its height was 18 feet. The Jesco men planned to pour passes 10 to 12 feet wide in strips running the width of the budding, starting at the north side.

The truck crane from Modern together with Stowe, the operator, and Janshen, the oder, arrived around 8 a. m. The crane was an American crane, weighing 25 tons, consisting of a cab and truck chassis permitting its operation over the road on rubber tires. From controls in the cab the operator manipulated the boom and a bucket attached to cables. The crane was first located in a parking lot where Stowe and Janshen rigged the cables, fitted on a boom of 60 feet and extended it to 90 feet by attaching a 30-foot jib, and attached the bucket furnished by J. D. & P. After this preparation, the crane was ready to be set in place. Alvin G. Olson, the J. D. & P. foreman, suggested that it be placed along the south wall of the building in order to avoid a number of moves. Stowe, however, preferred the east side, where he would not have to work “blind” as much and Olson concurred. The crane was then moved into position. There was a slight incline away from the budding, but the rear wheels were spun so that they would sink into the earth, thereby to some extent leveling the crane. The ground in the area was wet, muddy, and spongy. Stowe and Janshen then proceeded to block the crane so that it would be stable during their operation. The crane was equipped with four outrigger steel I-beams, each 8 feet long; two on each side of the bed of the truck and encased in channels so they could be moved outward and could be locked in place with steel pins. Modern’s employees slid these four I-beams out from their channels so that they protruded 2 Vi feet from the sides of the crane at the four corners. They were not locked in place because the locking pins were missing. Under each I-beam upon the ground they placed two 8” x 8” x 4’ softwood timbers worn or rounded at the edges. They then stacked upon them 12” x 12” x 10” hardwood blocks, then some 6”, 4”, and 2” blocks and plywood to shim up to the underside of each outrigger. The blocking was made firm by swinging the boom from side to side and placing pieces of wood shims under the outriggers on the *223 opposite side from the boom as the weight shifted. Although only'hard-wood blocks and sometimes mechanical jacks are used to lift the weight of the truck’ crane off its springs and wheels and stabilize it, the blocking materials used were the only materials available at Modem’s yard. As noted, also absent were the locking pins, designed to prevent the I-beams from slipping in and out of their channels. With the weight of the crane off its wheels and upon the blocked outriggers, the crane was ready to elevate concrete. At about 9 a. m. Olson, who had been around the area while the crane was being set up, inspected it and said, “It looks good” or words to that effect.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

David Finazzo v. Fire Equipment Company
918 N.W.2d 200 (Michigan Court of Appeals, 2018)
Zosel v. Minn-Dak Farmers' Cooperative, Inc.
463 F. Supp. 2d 960 (D. Minnesota, 2006)
Robert Reimer v. City of Crookston
326 F.3d 957 (Eighth Circuit, 2003)
Reimer v. City Of Crookston
326 F.3d 957 (Eighth Circuit, 2003)
Larimore v. Carolina Power & Light
531 S.E.2d 535 (Court of Appeals of South Carolina, 2000)
Sutherland v. Barton
570 N.W.2d 1 (Supreme Court of Minnesota, 1997)
Zimmer v. Carlton County Co-Op Power Ass'n
483 N.W.2d 511 (Court of Appeals of Minnesota, 1992)
Crown Holding Corp. v. Larson
410 N.W.2d 373 (Court of Appeals of Minnesota, 1987)
Conover v. Northern States Power Co.
313 N.W.2d 397 (Supreme Court of Minnesota, 1981)
Lemmer v. IDS Properties, Inc.
304 N.W.2d 864 (Supreme Court of Minnesota, 1980)
Ahrenholz v. Hennepin County
295 N.W.2d 645 (Supreme Court of Minnesota, 1980)
Sorenson v. Kruse
293 N.W.2d 56 (Supreme Court of Minnesota, 1980)
Keith Vagle v. Pickands Mather & Company
611 F.2d 1212 (Eighth Circuit, 1980)
Tolbert v. Gerber Industries, Inc.
255 N.W.2d 362 (Supreme Court of Minnesota, 1977)
Johnson v. Serra
521 F.2d 1289 (Eighth Circuit, 1975)
Sorenson v. Safety Flate, Inc.
216 N.W.2d 859 (Supreme Court of Minnesota, 1974)
Caspersen v. Webber
213 N.W.2d 327 (Supreme Court of Minnesota, 1973)
Keefer v. Al Johnson Construction Co.
193 N.W.2d 305 (Supreme Court of Minnesota, 1971)
Thill v. Modern Erecting Company
193 N.W.2d 298 (Supreme Court of Minnesota, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
136 N.W.2d 677, 272 Minn. 217, 1965 Minn. LEXIS 653, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thill-v-modern-erecting-company-minn-1965.