Thermo Tech, Inc. v. Goodyear Tire and Rubber Co., Inc., National Surety Corporation, Sam Pace, D/B/A Pimco Insulation Contractors & Manufacturers

643 F.2d 1173, 1981 U.S. App. LEXIS 13690
CourtCourt of Appeals for the Fifth Circuit
DecidedMay 1, 1981
Docket79-2876
StatusPublished
Cited by6 cases

This text of 643 F.2d 1173 (Thermo Tech, Inc. v. Goodyear Tire and Rubber Co., Inc., National Surety Corporation, Sam Pace, D/B/A Pimco Insulation Contractors & Manufacturers) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thermo Tech, Inc. v. Goodyear Tire and Rubber Co., Inc., National Surety Corporation, Sam Pace, D/B/A Pimco Insulation Contractors & Manufacturers, 643 F.2d 1173, 1981 U.S. App. LEXIS 13690 (5th Cir. 1981).

Opinion

RANDALL, Circuit Judge:

In this suit two subcontractors (ThermoTech, Inc. and Sam Pace, d/b/a Pimco Insulation Contractors & Manufacturers) seek recovery from the owner of an industrial construction project (Goodyear Tire and Rubber Co.), and from a corporate surety of the project (National Surety Corp.), after the default of the contractor (Harold L. Brussard, d/b/a B & H Insulation Co.) on invoices due the subcontractors. Goodyear placed funds representing unpaid invoice amounts and retainages in the registry of the court, and National Surety seeks its attorneys fees and court costs from this fund. The district court granted a final judgment in favor of the subcontractors in the full amounts owed them; the judgment was based both on a mechanics’ and materialmen’s lien purportedly held by ThermoTech and on a bond issued by National Surety. We find both theories to be in error, and we reverse the judgment of the district court.

I. THE FACTS

In July of 1976 Goodyear solicited bids for the insulation of two large towers in a chemical plant near Beaumont, Texas; Brussard was awarded the contract on his bid of $54,235. Goodyear thereupon submitted a purchase order to Brussard. The order briefly described the requirements of the job and the terms of payment, and included the following sentence: “You are to provide a performance & payment bond at 1% of price, we to pay for cost of bond.” 1 On August 11, 1976, a bond was in fact executed by Brussard and National Surety. The bond did not, however, insure the payment of all subcontractors; it was solely a performance bond. As such it provided for the payment of subcontractors only in the *1176 event that they procured a valid lien on Goodyear’s property.

Brussard hired Pace to procure certain insulation materials and to perform certain fabrication work on the materials before delivering them to Brussard for use on the Goodyear project. Pace in turn purchased the insulation materials from Thermo-Tech. Goodyear did not deal either with Pace or with Thermo-Tech, and made no direct representations to either of these subcontractors. However, the district court found that Goodyear had by its requirement of a “payment & performance bond” on its purchase order to Brussard implicitly represented to Thermo-Tech and Pace that Goodyear would in fact purchase a payment bond. This conclusion was based on the district court’s findings that Brussard used the purchase order to obtain credit from Pace; that both Pace and Thermo-Tech knew of the provision for a payment and performance bond in that purchase order; that both of these subcontractors relied upon that provision in extending credit to Brussard; and that it is “customary in the industry to use such purchase orders to obtain credit from suppliers.”

In late August or early September of 1976, Thermo-Tech delivered the insulation materials to Pace. In September of 1976, Pace completed its fabrication of the materials and delivered them to Brussard at the Goodyear plant construction site. Brussard then commenced the installation of the insulation materials; the job was completed on December 14,1976. At the conclusion of this project, Goodyear owed Brussard $4,746.23 on unpaid invoices, and held unpaid retainages in the amount of $5,581.56.

At this point Brussard still owed ThermoTech $17,811.78 for the materials it had provided to Pace. On December 7, Brussard and Thermo-Tech entered into a written agreement pursuant to which all unpaid invoice amounts owed by Goodyear would be paid by Goodyear directly to ThermoTech to offset this debt. This agreement was presented to Goodyear on December 7; nevertheless Goodyear paid $3,600 to Brussard on December 14. On January 19,1977, Thermo-Tech filed in the office of the county clerk an affidavit of lien with respect to the insulation materials. On February 9, Pace also filed an affidavit of lien with respect to those materials, and on February 10 Pace notified Goodyear of his claim against Brussard; at this time Brussard owed Pace a total of $11,964.03 for its procurement and fabrication work.

In June of 1977, Thermo-Tech brought this suit in a district court of the State of Texas to recover the full amount owed Thermo-Tech by Brussard; the suit named as defendants Goodyear, National Surety, Pace and Brussard. Goodyear then brought a cross-claim in the nature of interpleader and deposited in the registry of the court $4,746.23 as funds due on unpaid invoices and $5,581.56 as contract retainages. Goodyear named the United States as a third-party defendant in this action because of a tax claim the government allegedly held against Brussard. The United States thereupon removed this case to the United States District Court for the Eastern District of Texas, where the suit was tried to the court on September 7, 1978. The United States was not awarded any portion of the inter-pleaded funds and does not appeal this determination against it. Pace responded to Termo-Tech’s suit by itself seeking to recover from Goodyear. Finally, National Surety seeks its attorneys fees and court costs for this action on the basis of an attorneys fee provision in the bond executed by Brussard.

The district court found in favor of Thermo-Tech and Pace, and awarded each of them a judgment against Goodyear and National Surety in the full amount of Brussard’s debts to them. The decision of the district court seems to rest on two separate theories. In the first place, the court found that Thermo-Tech had a valid lien on the insulation materials. More precisely, the court found as follows:

Thermo-Tech, Inc. has a valid lien by reason of Article 5463 and Article 5469 V.A.T.S. pursuant to the notice and assignment of December 7, 1976, in the amount of $3,600 paid to Brussard in *1177 violation of Article 5463(2), and $5,581.56 in retainages, and $4,746.23 in funds yet due on purchase orders.

This lien does not cover the full amount owed Thermo-Tech, but instead seems limited to unpaid invoice amounts, contract retainages, and the amount paid to Brussard in disregard of the agreement between Brussard and Thermo-Tech. The district court did not find any lien in favor of Pace.

In the second place, the district court found that Goodyear and National Surety had contracted for a payment and performance bond and not merely for a performance bond. Because of the subcontractors’ reliance on the description in the purchase order, the district court held that Goodyear and National Surety were estopped from denying that the phrase “payment & performance bond” in Goodyear’s purchase order to Brussard was incorporated by reference in the bond issued by National Surety. The court further held that since the bond insured the payment of subcontractors it was a third-party beneficiary contract enforceable by subcontractors, and therefore the court allowed Thermo-Tech and Pace to recover directly on the bond.

We find that both of these theories are in error as a matter of law, and we therefore reverse the judgment of the district court.

II. THE PURPORTED MECHANICS’ AND MATERIALMEN’S LIENS

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
643 F.2d 1173, 1981 U.S. App. LEXIS 13690, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thermo-tech-inc-v-goodyear-tire-and-rubber-co-inc-national-surety-ca5-1981.