The Senate Engineering Co. v. KU Resources

CourtSuperior Court of Pennsylvania
DecidedNovember 19, 2019
Docket267 WDA 2019
StatusUnpublished

This text of The Senate Engineering Co. v. KU Resources (The Senate Engineering Co. v. KU Resources) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Senate Engineering Co. v. KU Resources, (Pa. Ct. App. 2019).

Opinion

J-A18043-19

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

THE SENATE ENGINEERING CO., : IN THE SUPERIOR COURT OF : PENNSYLVANIA Appellant : : : v. : : : KU RESOURCES, INC. : No. 267 WDA 2019

Appeal from the Order Entered January 17, 2019 in the Court of Common Pleas of Armstrong County Civil Division at No(s): 2017-1319

BEFORE: BOWES, J., NICHOLS, J., and MUSMANNO, J.

MEMORANDUM BY MUSMANNO, J.: FILED NOVEMBER 19, 2019

The Senate Engineering Co. (“Senate”), appeals from the Order

dismissing its Complaint (the “2018 Complaint”), and granting the Preliminary

Objections filed by KU Resources, Inc. (“KU”). We affirm.

Senate provides engineering design, project management, and related

engineering services to clients. KU is a geotechnical engineering firm. In July

2012, Senate entered into a contract with the Armstrong County Industrial

Development Authority (“ACIDA”). Senate agreed to provide engineering

services and designs for the construction of four new “pad sites” (hereinafter,

“the Project”), in an industrial park in Armstrong County, owned by ACIDA.

Prior to entering into this contract, Senate retained KU to provide

geotechnical investigation and consultation services concerning the Project J-A18043-19

(hereinafter referred to as the “Senate/KU Contract”).1 After KU submitted a

geotechnical report (“the KU Report”) to Senate in September 2012, Senate

provided ACIDA with plans and designs for the Project.2 ACIDA then publicly

sought bids from construction companies that could complete the Project. The

chosen bidder was Hoffman Construction Services, LLC (“Hoffman”).

Hoffman began work on the Project in 2013, which included earthwork,

grading, and grass seeding. Hoffman completed construction in September

2014. However, it eventually became apparent that the seed was not growing

well, which caused damage to the slopes. Senate alleged in its 2018

Complaint that if these problems do exist, they were attributable to the

Project’s slopes being constructed too steep, per KU’s recommendation.

Importantly to this appeal, Senate’s instant action was preceded by an

action that Hoffman brought against Senate and ACIDA concerning the Project

(hereinafter, the “2014 action”).3 In sum, Hoffman pled that it had suffered

damages due to negligent engineering designs concerning the overly-steep

grade of the Project’s slopes.

____________________________________________

1 Specifically, Senate asked KU to investigate any limitations to the Project site development due to any subsurface issues that may be present, and provide a geotechnical report of the site conditions to allow for proper project design by Senate.

2Senate averred that these plans/designs were based, in part, upon the KU Report.

3 Hoffman did not name KU as a defendant in the 2014 action. -2- J-A18043-19

In response to the 2014 action, in August 2015, ACIDA filed an Answer,

New Matter, and a Cross-Claim against Senate. In the Cross-Claim, ACIDA

asserted professional negligence, breach of contract, and indemnification from

Hoffman’s claims.

Notably to this appeal, in November 2016, Senate filed a “Complaint to

Join Additional Defendant, KU []” (the “Complaint to Join”), in the 2014 action.

Therein, Senate asserted against KU claims of (1) negligence; and (2)

indemnification, and asked the court to join KU with respect to the 2014

action. Concerning the indemnification cause of action, Senate averred that,

in the Senate/KU Contract, KU expressly agreed to indemnify Senate

concerning any losses/liabilities that Senate might incur, which arose out of

any negligence or misconduct on the part of KU in performing its contracted

services. In response, KU filed an Answer and New Matter in February 2017.

On March 14, 2018, Senate filed the 2018 Complaint against KU.

Therein, Senate alleged the following causes of action: (1) professional

negligence; (2) breach of contract; (3) common law indemnification; (4)

contractual indemnification; and (5) contribution.

On October 22, 2018, KU filed Preliminary Objections to the 2018

Complaint. KU asserted, inter alia, that Senate’s claims in the 2018 Complaint

were duplicative of the claims that Senate had previously alleged against KU

in the Complaint to Join, and must therefore be dismissed. Concerning

Senate’s claims in the 2018 Complaint for indemnification and contribution

from KU, KU pointed out that the 2014 action is still pending, and no judgment

-3- J-A18043-19

has been entered against Senate or any party.4 Therefore, KU asserted, any

claim for indemnification or contribution is premature.

After a hearing, the trial court granted KU’s Preliminary Objections and

dismissed the 2018 Complaint, by a Memorandum and Order entered on

January 17, 2019. Therein, the trial court held that Senate’s claims for

indemnification and contribution from KU, in the 2018 Complaint, were

premature and duplicative of the claims raised in the Complaint to Join. See

Memorandum and Order, 1/17/19, at 3-4 (unnumbered). Additionally, the

court held that Senate’s claims of breach of contract and professional

negligence constituted “nothing more than [] claim[s] for indemnity or

contribution.” Id. at 3 (unnumbered).

Senate filed a Notice of Appeal, which was entered on the docket on

February 19, 2019.5 Senate thereafter timely filed a court-ordered Pa.R.A.P.

1925(b) Concise Statement of errors complained of on appeal.

Senate presents the following issues for our review:

1. Whether the trial court erred in failing to apply/strictly apply the pendency of the action test to Senate’s claims for contractual indemnification, common law indemnification, and

4The trial court later confirmed this fact in its Memorandum and Order ruling upon the Preliminary Objections.

5 We note that the thirtieth day upon which Senate had to file its appeal, i.e., February 17, 2019, fell on a Sunday. See 1 Pa.C.S.A. § 1908 (extending the thirty-day deadline to first non-holiday weekday if the final date falls on a weekend or holiday); see also Pa.R.A.P. 903. Moreover, Monday, February 18, 2019, was a state and federal holiday. Therefore, Senate’s Notice of Appeal, filed on February 19, 2019, is timely. See 1 Pa.C.S.A. § 1908. -4- J-A18043-19

professional negligence[,] or in otherwise determining [that] said claims are improper?

2. Whether Senate properly asserted a claim for contribution that is neither premature nor duplicative?

3. Whether Senate’s causes of action for breach of contract and professional negligence are duplicative of indemnity and contribution claims?

Brief for Appellant at 4 (capitalization omitted).

We review a trial court’s decision sustaining or overruling preliminary objections for an error of law. In so doing, we employ the same standard as the trial court, to wit, all material facts set forth in the [] Complaint and inferences reasonably drawn therefrom are admitted as true. Preliminary objections which seek the dismissal of a cause of action should be sustained only in cases in which it is clear and free from doubt that the pleader will be unable to prove facts legally sufficient to establish the right to relief.

Knight v. Springfield Hyundai, 81 A.3d 940, 947 (Pa. Super. 2013)

(citations and quotation marks omitted).

As Senate’s issues are related, we will address them together. Senate

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Swartz v. Sunderland
169 A.2d 289 (Supreme Court of Pennsylvania, 1961)
Virginia Mansions Condominium Ass'n v. Lampl
552 A.2d 275 (Supreme Court of Pennsylvania, 1988)
Mattia v. Sears, Roebuck & Co.
531 A.2d 789 (Supreme Court of Pennsylvania, 1987)
Crutchfield v. Eaton Corp.
806 A.2d 1259 (Superior Court of Pennsylvania, 2002)
MIIX Insurance Co. v. Epstein
937 A.2d 469 (Superior Court of Pennsylvania, 2007)
Knight v. Springfield Hyundai
81 A.3d 940 (Superior Court of Pennsylvania, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
The Senate Engineering Co. v. KU Resources, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-senate-engineering-co-v-ku-resources-pasuperct-2019.