The Sappho

89 F. 366, 1898 U.S. Dist. LEXIS 184
CourtDistrict Court, D. South Carolina
DecidedAugust 30, 1898
StatusPublished
Cited by3 cases

This text of 89 F. 366 (The Sappho) is published on Counsel Stack Legal Research, covering District Court, D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Sappho, 89 F. 366, 1898 U.S. Dist. LEXIS 184 (D.S.C. 1898).

Opinion

BBAWLEY, District Judge.

These cases were heard together, and the controversy arises out of a contract for repairs of the steamer [367]*367Sappho, owned by the respondent company, a corporation duly chartered by the state of South Carolina for conducting a ferry between the city of Charleston and Mt. Pleasant and Sullivan’s Island; the Sappho being employed in such service. The libelant In the case first entitled is a shipwright, and the libel claims a balance due for work done and materials furnished in sucli repairs. The libelants in the second case are merchants, and I heir claim is for materials furnished to the first named libelant, and used by Mm in the repairs. Air. C. O. Witte is chairman of the board of directors of the respondent company, and as the case has given rise to unfortunate differences of opinion, and an apparent conflict of testimony between Mr. Pregnall and himself, it may be as well to say that both are men of the highest character, and neither would knowingly stale what was untrue. A. contract in writing and under seal was entered into February 25, 1897, between the libelant. Pregnall and the company. Tins contract is not referred to in the libel, but is set up in, and made a part of, the answer; and a proper understanding of the questions raised requires its consideration. Ah inspection of it shows that at the time it was entered into ttie precise extent of the repairs needed was not entirely known. The first clause provides for such as were specifically known, and embraces 1.1 items in all. The second clause' provides for the payment of the sum of .$2,000 for the work and material (unbraced in the first clause, upon certificate that there are no liens of any kind on account thereof. The third clause provides for such additional repairs as it was supposed would be found necessary, but, as the exact amount thereof was not known, the three items embraced therein were to be paid for as follows: (1) The taking out of defective and substituting of new timber, "such ns floors, futtoeks, and top,” at $1 for the running foot; (2) replacing of ceiling, at: 30 cents for the running foot; (3) (he taking out of defective planking, and renewing same, at 60 cents for the running foot. The fourth clause provides for the payment of amounts found to be dae under The third clause, upon certificate of no liens. The fifth clause provides that all the material furnished and work done under the first and third clauses shall be of the best quality, and subject to the superintendence and approval of the company, and also of the United Hiatus inspector of hulls. Having thus provided for the known and for the probable needs of the vessel, provision was made for the unknown and possible needs in the sixth clause, which is as follows:

“Sixth. No new work of any description done on the said steamer, or any work of any kind whatever, shall he considered as extra, unless a. separate estimate in writing for the same, before its commencement, slia.ll have been submitted by the, contractor to the proprietor, and tlie signature ol’ the chairman of its board of directors obtained thereto; and the contractor shall demand payment for such work immediately after it is done. In case of day’s work, statement of the same must be delivered to the proprietor, at latest, during the week following that in which the work ma.y have been done; and only- such day’s work and extra work will be paid for, as such, as agreed on and authorized in writing.”

The controversy comes from an alleged agreement subsequent to the written contract, which it is claimed was made between S. J. Preg[368]*368nail, the contractor, and C. O. Witte, the chairman of the ferry company, — an agreement positively asserted on the one side, and as positively denied on the other. It occurred in this wise: After the Sappho was put on the marine railway of the contractor, and stripped, as appears from the testimony of Cherry, the master, she was found to be in worse condition than he expected. He discussed the matter with Mr. Bird, one of the directors, and told him that he thought it would be cheaper to cancel the contract with Pregnall, and get him to build a new hull, which he thought would cost about $10,000. Bird advised him to see the president. He went down to see him, and informed him of the condition of the boat; and his reply was that he was sorry he had not known it sooner, and that they would have to do the best they could. After informing Pregnall of this conversation, they went down together the next day to Mr. Witte’s office, and Mr. Pregnall gives this account of the interview: After saying that the vessel would have to be rebuilt, in reply to the question, “Did you describe this condition of affairs?” he answers:

“I did, and so did Captain Cherry. After consulting a time, he wanted to know if I could do that work in time to save tlie season; he then considered the cost of a new boat against rebuilding that one. T suggested that by taking out the machinery I could save $4,000 or $5,000. I did offer to build a new boat — hull—for $11,000. They decided then that I should go on, and make' the' old hull new. Mr. Witte told me, ‘All right; go ahead.’ I told him I did not have the means to do that much work. He said he would furnish me the means every week to pay my men, which he did, and I went along with the work and completed it.”

And this is Mr. Witte’s account of the same interview: In reply to the question whether he remembered tlie occasion, and to state just what occurred, he answers:

“I remember it distinctly. Capt. Cherry and Mr. Pregnall came down to the office, as they said that the vessel was not in as bad a condition as represented by some people, — making mention of some certain parties at the time, — and that she could be repaired, and be a stronger and stouter vessel than before; stating that, putting these keelsons on, and which were in the contract, the vessel would be stouter and better than before. The question about how much it would cost to build a new hull came up in this way: As some people said it would be cheaper to build a new than repair the old, this was reported to me that such had been said; and I asked Mr. Pregnall how much could we build a new hull for. and he said $11,000, and I said, ‘Well, I was told it could be done for $8,000 or $9,000.’ He said his price was $11,000.”

Replying to tbe question, “Did you, in consequence of that conversation, say, ‘All right; go ahead’?” he answers:

“No; I told them after that that we concluded to go on with the contract, —that was the result of the conversation, — and finish the vessel, and finish it in the time agreed upon; and not a word was said about the boat, and that the ferry company had plenty of money. Everybody knew it hadn’t. And I had no occasion to say the bank had plenty of money. Everybody knew it had.”

The last part of this answer obviously refers to testimony previously given by Cherry, wherein, in replying to questions as to why he had acquiesced in certain work being done which was outside the contract, he- had said that it was because Pregnall had informed him that he [369]*369was authorized by Mr. Witte to do it, and supposed he had made a written contract, and had repeated as Mr. Witte’s some expressions of this nature. Capt. Cherry, the only witness present at this interview', replying to the question, “At the time that Mr. Pregnall went with you to O. O. Witte’s office, did you understand from what Mr. Witte said in Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eagle, Star & British Dominions v. Tadlock
14 F. Supp. 933 (S.D. California, 1936)
Mack S. S. Co. v. Thompson
176 F. 499 (Sixth Circuit, 1910)
The Sappho
94 F. 545 (Fourth Circuit, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
89 F. 366, 1898 U.S. Dist. LEXIS 184, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-sappho-scd-1898.