The Rapides Parish School Board v. Zurich American Insurance Company

Louisiana Court of Appeal·Decided August 21, 2019·No. CW-0019-0329·Unknown

Opinion

STATE OF LOUISIANA

COURT OF APPEAL, THIRD CIRCUIT

19-312 Consolidated With 19-329

THE RAPIDES PARISH SCHOOL BOARD VERSUS ZURICH AMERICAN INSURANCE COMPANY, ET AL

**********

ON APPLICATION FOR SUPERVISORY WRITS FROM THE NINTH JUDICIAL DISTRICT COURT PARISH OF RAPIDES, NO. 254,644 F HONORABLE GEORGE C. METOYER, DISTRICT JUDGE

**********

JOHN E. CONERY

JUDGE

**********

Court composed of Sylvia R. Cooks, John E. Conery, and Van H. Kyzar, Judges.

WRITS DENIED.

Adrian G. Nadeau J. Weston Clark Long Law Firm, L.L.P. 1800 City Farm Drive, Building 6 Baton Rouge, Louisiana 70806 (225) 922-5110 COUNSEL FOR DEFENDANTS/RELATORS/RESPONDENTS:

Alliance Design Group, LLC XL Specialty Insurance Company

Temple A. Stephens Comeaux, Stephens & Grace One Lakeway Center, Suite 1060 3900 North Causeway Boulevard Metairie, Louisiana 70002 (504) 219-2030 COUNSEL FOR DEFENDANTS/RELATORS/RESPONDENTS:

Ratcliff Construction Company, LLC Zurich Insurance Company

James C. Downs Attorney At Law 1254 Dorchester Drive Alexandria, Louisiana 71303 (318) 448-3439 COUNSEL FOR PLAINTIFF/RELATOR/RESPONDENT:

The Rapides Parish School Board

CONERY, Judge.

This matter is before the court on the parties’ consolidated writ applications.

In writ application number 19-312, Relators Alliance Design Group, L.L.C. (Alliance), Alliance’s Insurer, XL Specialty Insurance Company (XL Specialty Insurance), Ratcliff Construction Company, L.L.C. (Ratcliff), and Ratcliff’s insurer, Zurich American Insurance Company (Zurich) (collectively Defendants), seek review of a trial court’s judgment denying its exception of peremption in part. In writ application number 19-329, Relator is the plaintiff, Rapides Parish School Board (RPSB), and via that writ application, RPSB seeks review of the trial court’s decision to partially grant Defendants’ exception of peremption. For the following reasons, we deny both writ applications.

FACTS AND PROCEDURAL HISTORY This case involves a claim for property damages originally sustained when a fire sprinkler head discharged water at a junior high school in Woodworth, Louisiana. On December 26, 2014, at 3:00 a.m., a fire alarm activated at Caroline Dormon Junior High. When responding to the alarm, the local fire department did not find any fire, smoke, or heat. However, the fire department observed that a fire-sprinkler head in the principal’s office had activated and released water, causing flooding in that office and a substantial part of the administrative wing of the school. Allegedly, the sprinkler discharge was caused by a defect in the design and construction of the school’s fire suppression system. Defendant Alliance was the architect for the school, and Defendant Ratcliff was the general contractor for the construction of the school. On August 17, 2012, RPSB signed a Certificate of Substantial Completion and accepted Ratcliff’s construction of the school with a few limited reservations.

As a result of the flooding on December 26, 2014, RPSB timely filed the instant lawsuit on December 18, 2015, against Alliance and Ratcliff and their insurers, XL Specialty Insurance and Zurich, respectively. In the original petition, RPSB alleges that the design and construction of the fire suppression system caused the sprinkler system to discharge, and RPSB seeks to recover for damages resulting from the discharge of water from the sprinkler head. RPSB alleges that the water throughout the sprinkler system pipe was able to freeze and expand due to below freezing temperatures in the attic space above the ceiling and that this expansion affected the sprinkler head’s internal mechanisms, thus causing water to leak. RPSB also alleges that the temperature in the attic where the pipes are located dropped below freezing because the walls in the attic were not sufficiently insulated and because some ceiling panels in the principal’s office were covered with insulation which prevented warmer air from the building from rising to the attic area. In its original petition, RPSB alleges that it is entitled to recover for the costs of repairing the water damage to the school and to recover for future school repairs which may be necessary due to defective conditions in the school.

Because Defendants Alliance and Ratcliff made allegations that the spontaneous discharge of the sprinkler system at the school was caused by third party fault, RPSB filed a first amended petition on July 28, 2017, adding claims against Tyco Fire and Building Products (Tyco), which is the manufacturer of the sprinkler head, and Anderson Fire Protection of Alexandria, L.L.C. (Anderson Fire Protection), which is the subcontractor that installed the fire suppression system. However, Tyco was subsequently dismissed from the lawsuit on an unopposed motion for summary judgment. Although Anderson Fire Protection remains a

defendant in the lawsuit, that defendant is not involved in the instant writ applications.

In its first amended petition, RPSB also alleges that a post-incident inspection of the fire suppression system revealed that the wrong sprinkler head had been installed throughout the school and that many of the sprinkler heads were clogged with a foreign material such that RPSB was required to replace the sprinkler heads throughout the school. RPSB seeks to recover damages from Defendants due to those defects.

On December 20, 2018, the trial court granted leave of court to allow RPSB to file a second amended petition. In Paragraphs 34-35 of that petition, RPSB adds allegations of the following deficiencies: 1) the failure to install a lower level of insulation below the metal roof throughout the school; 2) the use of unfaced batt insulation instead of foil-faced insulation throughout the school; 3) the failure to put the proper vapor barrier behind the brick masonry; 4) the failure to properly supervise the installation of an electric solar panel and electric conduit; 5) the use of improper fan motors and circuit breakers in the heating, ventilation, and air conditioning systems; 6) the failure to obtain a successful final electrical inspection for the issuance of the certificate of occupancy; and 7) the making of false assurances that the school would be built to higher than usual standards with regard to environmental design and energy consumption. Given those deficiencies, RPSB sought damages related both to property damage and to higher utility costs, plus additional personnel costs resulting from monitoring the suspect systems.

Defendants filed an exception of peremption as to the second amended petition, asserting that the newly-raised claims are barred by the five-year peremptive periods set forth in La.R.S. 9:5607, which governs claims against

architects, and La.R.S. 9:2772, which governs claims against building contractors. Following a hearing, the trial court signed a judgment granting Defendants’ exception of peremption in part and dismissing a list of some of the specific allegations raised in RPSB’s second amended petition.

The trial court also denied the exception of peremption in part, holding that any allegations/claims in RPSB’s second amended petition not included in the list of dismissed claims would be allowed to proceed.1 All Relators now seek review of the trial court’s ruling by their respective applications for supervisory writs. In writ application number 19-312, Defendants-Relators assert that the trial court erred when it partially denied their exception of peremption. In writ number 19-329, RPSB-Relator asserts that the trial court erred when it partially granted Defendants’ exception of peremption. Thus, Defendants take the position that the trial court should have granted the exception of peremption in its entirety and dismissed all claims raised in RPSB’s second amended petition. On the other hand, RPSB takes the position that the trial court should have denied the exception of peremption in its entirety and allowed all claims raised in its second amended petition to proceed.

LAW AND DISCUSSION

Free access — add to your briefcase to read the full text and ask questions with AI

The Rapides Parish School Board v. Zurich American Insurance Company, (La. Ct. App. 2019).

The Rapides Parish School Board v. Zurich American Insurance Company (The Rapides Parish School Board v. Zurich American Insurance Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ristroph v. Public Facilities Authority
943 So. 2d 492 (Louisiana Court of Appeal, 2006)
Rando v. Anco Insulations Inc.
16 So. 3d 1065 (Supreme Court of Louisiana, 2009)
Naghi v. Brener
17 So. 3d 919 (Supreme Court of Louisiana, 2009)
Ramey v. DeCaire
869 So. 2d 114 (Supreme Court of Louisiana, 2004)
Reilly v. State
533 So. 2d 1341 (Louisiana Court of Appeal, 1988)
Robin v. Allstate Ins. Co.
844 So. 2d 41 (Louisiana Court of Appeal, 2003)
Borel v. Young
989 So. 2d 42 (Supreme Court of Louisiana, 2008)
Gunter v. Plauche
439 So. 2d 437 (Supreme Court of Louisiana, 1983)
CAPITOL HOUSE PRESERVATION v. Perryman
745 So. 2d 1194 (Louisiana Court of Appeal, 1999)
Ray v. Alexandria Mall
434 So. 2d 1083 (Supreme Court of Louisiana, 1983)
Marsh Engineering Inc. v. Parker
883 So. 2d 1119 (Louisiana Court of Appeal, 2004)
Brown v. Sanders
960 So. 2d 931 (Louisiana Court of Appeal, 2007)
Herlitz Const. Co., Inc. v. Hotel Investors of New Iberia, Inc.
396 So. 2d 878 (Supreme Court of Louisiana, 1981)
Albach v. Kennedy
801 So. 2d 476 (Louisiana Court of Appeal, 2001)
Scaglione v. Juneau
40 So. 3d 127 (Supreme Court of Louisiana, 2010)
Tracy Ray Lomont v. Michelle Myer-Bennett and Xyz Insurance Company
172 So. 3d 620 (Supreme Court of Louisiana, 2015)
Udomeh v. Joseph
103 So. 3d 343 (Supreme Court of Louisiana, 2012)
Thrasher Construction, Inc. v. Gibbs Residential, L.L.C.
197 So. 3d 283 (Louisiana Court of Appeal, 2016)
Duvio v. Specialty Pools Co.
216 So. 3d 999 (Louisiana Court of Appeal, 2016)
Russo v. Texas & Pac. R. R.
131 So. 70 (Louisiana Court of Appeal, 1930)