In the United States Court of Federal Claims
THE QED GROUP LLC d/b/a Q2 IMPACT,
Plaintiff,
v. No. 24-1961C Filed August 5, 2025 THE UNITED STATES,
Defendant.
Ryan C. Bradel, Ward & Berry, PLLC, Washington, DC, for plaintiff. Grant D. Johnson, Civil Division, United States Department of Justice, Washington, DC, for de- fendant.
OPINION AND ORDER Denying Q2 Impact’s Motion for Attorney’s Fees and Costs
QED, doing business as Q2 Impact, protested its disqualification from eligibility for a con-
tract under a large solicitation issued by the General Services Administration.1 The parties re-
quested a statutory interpretation, arguing that the court’s interpretation would resolve the dispute,
and the court issued a decision agreeing with the interpretation proposed by Q2 Impact. Now that
the case has been finally resolved, Q2 impact requests attorney’s fees and costs under the Equal
Access to Justice Act, 28 U.S.C. § 2412. The government responds that its position in the case was
substantially justified, so Q2 Impact is not entitled to fees and costs. The government’s position in
this case was substantially justified. Thus, the court will deny Q2 Impact’s motion for attorney’s
fees and costs.
1 This opinion was originally issued under seal on July 21, 2025. The parties had no proposed redactions. The court reissues the opinion publicly.
1 I. Background
The merits of this case turned on the meaning of section 889 of the John S. McCain Na-
tional Defense Authorization Act for Fiscal Year 2019, which prohibits government agencies from
contracting with any entity that uses certain high-risk telecommunications equipment or services
in its work. Section 889 allows waivers under some conditions. Pub L. No. 115-232, § 889(d)(1)-
(2). Section 889(d)(1) allows executive agency heads to issue waivers, and section 889(d)(2) al-
lows the Director of National Intelligence (DNI) to issue waivers. Id.
Here, the DNI issued a waiver allowing contractors, including Q2 Impact, to connect to
telecommunications equipment covered by section 889 for a USAID contract in Egypt, where
Egypt had no compliant telecommunications service providers. ECF No. 1 at 7-8 [¶¶27-31]. The
waiver was valid through 2028. Id. at 7 [¶28].
Q2 Impact later bid on GSA’s One Acquisition Solution for Integrated Services Plus
(OASIS+) program. See generally ECF No. 1. Q2 Impact did not propose to use covered equip-
ment for OASIS+ but disclosed that it used covered equipment for its USAID contract in Egypt.
GSA disqualified Q2 Impact from the OASIS+ program, explaining that Q2 Impact’s existing DNI
waiver covered only the USAID contract, not GSA’s proposed contract, and GSA was prohibited
under section 889 from contracting with Q2 Impact. Id. at 8-10 [¶¶32-40]. Q2 Impact filed a bid
protest challenging that disqualification. Q2 Impact argued that its disqualification was based on
an incorrect reading of section 889 and that it could still contract with GSA despite its use of
covered equipment for its USAID contract. The parties requested that the court interpret the statute.
The specifics of the parties’ dispute are covered in detail in this court’s opinion in QED Group
LLC v. United States, 175 Fed. Cl. 349 (2025), which is available at ECF No. 39.
2 The court agreed with the interpretation proposed by Q2 Impact, holding that GSA was not
prohibited from contracting with Q2 Impact under section 889. See ECF No. 39. The court con-
cluded that GSA’s decision to disqualify Q2 Impact from the OASIS+ program was based on a
misinterpretation of section 889, granted Q2 Impact’s motion for a permanent injunction, and or-
dered GSA to reevaluate Q2 Impact’s proposal under the court’s interpretation of the statute. Id.;
ECF No. 38 at 5. After the reevaluation, GSA made an award to Q2 Impact, and the parties filed a
joint stipulation of dismissal. ECF No. 55.
Q2 Impact now moves for attorney’s fees and costs under the Equal Access to Justice Act
(EAJA), 28 U.S.C. § 2412. See ECF No. 56.
II. The government’s position in this litigation was substantially justified
Q2 Impact argues that it satisfies the EAJA requirements and is entitled to $73,599.93 in
fees and costs plus an additional $8,812.68 for preparation of its fee motion. ECF No. 56 at 19;
ECF No. 60 at 19.2 The government argues that GSA’s position in the litigation was substantially
justified, so Q2 Impact is not entitled to recover attorney’s fees and costs. See ECF No. 59.
EAJA provides the Court of Federal Claims with the authority to award attorney’s fees and
costs in actions over which it has jurisdiction. 28 U.S.C. § 2412(a)(1); see Burkhardt v. Gober,
232 F.3d 1363, 1367 (Fed. Cir. 2000). To recover under EAJA, among other things, “the party
applying for fees and expenses [must have] prevailed” in a case in which “the position of the
2 Q2 Impact filed its reply brief, ECF No. 60, a week after the deadline, and did not seek an exten- sion of that deadline. See Rules 7.2(a)(2) and 6(b), Rules of the Court of Federal Claims (setting a deadline of one week for a reply brief, which fell on June 30, 2025, and requiring a motion to extend time after the deadline; Q2 Impact filed its brief on July 7, 2025). As there is no prejudice to the government, the court has nevertheless considered Q2 Impact’s reply brief, despite the delay. See Cohen v. Board of Trustees of the University of the District of Columbia, 819 F.3d 476, 481- 84 (D.C. Cir. 2016) (discussing “the clear preference of the Federal Rules to resolve disputes on their merits”).
3 United States was not substantially justified.” Burkhardt, 232 F.3d at 1367; see 28 U.S.C.
§ 2412(d)(1)(A).
“The government bears the burden of establishing that its position was substantially justi-
fied.” Patrick v. Shinseki, 668 F.3d 1325, 1330 (Fed. Cir. 2011) (citation omitted). An EAJA award
is precluded if the government shows its position to be “justified in substance or in the main—that
is, justified to a degree that could satisfy a reasonable person.” Pierce v. Underwood, 487 U.S.
552, 565 (1988) (quotation marks omitted). When determining whether the government’s position
was substantially justified, the court does not examine the government’s stance on every individual
issue in the case but rather determines “whether the government’s overall position had a reasonable
basis in both law and fact.” Chiu v. United States, 948 F.2d 711, 714-15 (Fed. Cir. 1991). The
government’s position could be substantially justified even if it was ultimately incorrect. KWV,
Inc. v. United States, 113 Fed. Cl. 534, 538 (2013); see Stillwell v. Brown, 46 F.3d 1111, 1113
(Fed. Cir.
Free access — add to your briefcase to read the full text and ask questions with AI
In the United States Court of Federal Claims
THE QED GROUP LLC d/b/a Q2 IMPACT,
Plaintiff,
v. No. 24-1961C Filed August 5, 2025 THE UNITED STATES,
Defendant.
Ryan C. Bradel, Ward & Berry, PLLC, Washington, DC, for plaintiff. Grant D. Johnson, Civil Division, United States Department of Justice, Washington, DC, for de- fendant.
OPINION AND ORDER Denying Q2 Impact’s Motion for Attorney’s Fees and Costs
QED, doing business as Q2 Impact, protested its disqualification from eligibility for a con-
tract under a large solicitation issued by the General Services Administration.1 The parties re-
quested a statutory interpretation, arguing that the court’s interpretation would resolve the dispute,
and the court issued a decision agreeing with the interpretation proposed by Q2 Impact. Now that
the case has been finally resolved, Q2 impact requests attorney’s fees and costs under the Equal
Access to Justice Act, 28 U.S.C. § 2412. The government responds that its position in the case was
substantially justified, so Q2 Impact is not entitled to fees and costs. The government’s position in
this case was substantially justified. Thus, the court will deny Q2 Impact’s motion for attorney’s
fees and costs.
1 This opinion was originally issued under seal on July 21, 2025. The parties had no proposed redactions. The court reissues the opinion publicly.
1 I. Background
The merits of this case turned on the meaning of section 889 of the John S. McCain Na-
tional Defense Authorization Act for Fiscal Year 2019, which prohibits government agencies from
contracting with any entity that uses certain high-risk telecommunications equipment or services
in its work. Section 889 allows waivers under some conditions. Pub L. No. 115-232, § 889(d)(1)-
(2). Section 889(d)(1) allows executive agency heads to issue waivers, and section 889(d)(2) al-
lows the Director of National Intelligence (DNI) to issue waivers. Id.
Here, the DNI issued a waiver allowing contractors, including Q2 Impact, to connect to
telecommunications equipment covered by section 889 for a USAID contract in Egypt, where
Egypt had no compliant telecommunications service providers. ECF No. 1 at 7-8 [¶¶27-31]. The
waiver was valid through 2028. Id. at 7 [¶28].
Q2 Impact later bid on GSA’s One Acquisition Solution for Integrated Services Plus
(OASIS+) program. See generally ECF No. 1. Q2 Impact did not propose to use covered equip-
ment for OASIS+ but disclosed that it used covered equipment for its USAID contract in Egypt.
GSA disqualified Q2 Impact from the OASIS+ program, explaining that Q2 Impact’s existing DNI
waiver covered only the USAID contract, not GSA’s proposed contract, and GSA was prohibited
under section 889 from contracting with Q2 Impact. Id. at 8-10 [¶¶32-40]. Q2 Impact filed a bid
protest challenging that disqualification. Q2 Impact argued that its disqualification was based on
an incorrect reading of section 889 and that it could still contract with GSA despite its use of
covered equipment for its USAID contract. The parties requested that the court interpret the statute.
The specifics of the parties’ dispute are covered in detail in this court’s opinion in QED Group
LLC v. United States, 175 Fed. Cl. 349 (2025), which is available at ECF No. 39.
2 The court agreed with the interpretation proposed by Q2 Impact, holding that GSA was not
prohibited from contracting with Q2 Impact under section 889. See ECF No. 39. The court con-
cluded that GSA’s decision to disqualify Q2 Impact from the OASIS+ program was based on a
misinterpretation of section 889, granted Q2 Impact’s motion for a permanent injunction, and or-
dered GSA to reevaluate Q2 Impact’s proposal under the court’s interpretation of the statute. Id.;
ECF No. 38 at 5. After the reevaluation, GSA made an award to Q2 Impact, and the parties filed a
joint stipulation of dismissal. ECF No. 55.
Q2 Impact now moves for attorney’s fees and costs under the Equal Access to Justice Act
(EAJA), 28 U.S.C. § 2412. See ECF No. 56.
II. The government’s position in this litigation was substantially justified
Q2 Impact argues that it satisfies the EAJA requirements and is entitled to $73,599.93 in
fees and costs plus an additional $8,812.68 for preparation of its fee motion. ECF No. 56 at 19;
ECF No. 60 at 19.2 The government argues that GSA’s position in the litigation was substantially
justified, so Q2 Impact is not entitled to recover attorney’s fees and costs. See ECF No. 59.
EAJA provides the Court of Federal Claims with the authority to award attorney’s fees and
costs in actions over which it has jurisdiction. 28 U.S.C. § 2412(a)(1); see Burkhardt v. Gober,
232 F.3d 1363, 1367 (Fed. Cir. 2000). To recover under EAJA, among other things, “the party
applying for fees and expenses [must have] prevailed” in a case in which “the position of the
2 Q2 Impact filed its reply brief, ECF No. 60, a week after the deadline, and did not seek an exten- sion of that deadline. See Rules 7.2(a)(2) and 6(b), Rules of the Court of Federal Claims (setting a deadline of one week for a reply brief, which fell on June 30, 2025, and requiring a motion to extend time after the deadline; Q2 Impact filed its brief on July 7, 2025). As there is no prejudice to the government, the court has nevertheless considered Q2 Impact’s reply brief, despite the delay. See Cohen v. Board of Trustees of the University of the District of Columbia, 819 F.3d 476, 481- 84 (D.C. Cir. 2016) (discussing “the clear preference of the Federal Rules to resolve disputes on their merits”).
3 United States was not substantially justified.” Burkhardt, 232 F.3d at 1367; see 28 U.S.C.
§ 2412(d)(1)(A).
“The government bears the burden of establishing that its position was substantially justi-
fied.” Patrick v. Shinseki, 668 F.3d 1325, 1330 (Fed. Cir. 2011) (citation omitted). An EAJA award
is precluded if the government shows its position to be “justified in substance or in the main—that
is, justified to a degree that could satisfy a reasonable person.” Pierce v. Underwood, 487 U.S.
552, 565 (1988) (quotation marks omitted). When determining whether the government’s position
was substantially justified, the court does not examine the government’s stance on every individual
issue in the case but rather determines “whether the government’s overall position had a reasonable
basis in both law and fact.” Chiu v. United States, 948 F.2d 711, 714-15 (Fed. Cir. 1991). The
government’s position could be substantially justified even if it was ultimately incorrect. KWV,
Inc. v. United States, 113 Fed. Cl. 534, 538 (2013); see Stillwell v. Brown, 46 F.3d 1111, 1113
(Fed. Cir. 1995) (“This quintessentially discretionary inquiry necessarily involves the determina-
tion of facts and the application of the substantially justified standard of the EAJA to those facts.”
(cleaned up)). “[S]ubstantial justification occurs somewhere between winning the case and being
‘merely undeserving of sanctions for frivolousness.’” Dalles Irrigation District v. United States,
91 Fed. Cl. 689, 697 (2010) (quoting Pierce, 487 U.S. at 566).
The government argues that, although its statutory interpretation did not prevail, its posi-
tion was reasonable, supported by law and fact, and substantially justified because GSA had ap-
plied the same interpretation of section 889 since the statute’s enactment. ECF No. 59 at 7. The
government adds that, as the court acknowledged, “[n]either the statutory text nor the accompany-
ing regulation at issue … directly addresses the interpretive issue in this case” (id. (quoting ECF
No. 39 at 11)), so GSA operated under the assumption that the language and guidance provided by
4 the Federal Acquisition Regulation (FAR) and the Federal Register regarding section 889(d)(1)
similarly applied to section 889(d)(2). ECF No. 59 at 8. Q2 Impact argues that GSA’s position was
not substantially justified because it “focused its interpretation of the scope of Section 889 prohi-
bitions and waivers on the wrong statutory clause, advanced a reading of Section 889 that was at
odds with the plain text and meaning of the statute and implementing regulations, and completely
failed to present GSA guidance that was [consistent] with its interpretation.” ECF No 56 at 18.
Therefore, Q2 Impact argues, GSA’s position did not have a “reasonable basis in law or fact.” Id.
(citing Chiu, 948 F.2d at 711).
GSA’s interpretation of section 889(d)(2), while ultimately incorrect, had a reasonable ba-
sis in law and fact. See Chiu, 948 F.2d at 715 (The court is tasked with “look[ing] at the entirety
of the government’s conduct and make a judgment call whether the government’s overall position
had a reasonable basis in both law and fact.”). Indeed, this court noted that section 889(d)(2) “is
brief … [and] does not address whether a DNI waiver allowing an entity to use covered equipment
in performing a contract with one agency means that other agencies are prohibited from contracting
with that entity.” ECF No. 39 at 11. The court also pointed out that the FAR and the Federal
Register “discussed and addressed only the agency-head waiver process,” and neither “released
considered guidance related to” section 889(d)(2). Id. at 12-13. The court further noted “limited
real-world examples” applying section 889(d)(2) on which either party could rely. Id. at 14.
GSA, not having much to work with, analogized to section 889(d)(1) to try to interpret
section 889(d)(2) in a manner consistent with the concerns suggested by Congress. For example,
the government noted Congress’s intent to avoid national security threats, particularly cybersecu-
rity threats, with section 889. ECF No. 17 at 16-17 (citing Huawei Technologies USA, Inc. v.
5 United States, 440 F. Supp. 3d 607, 638-39 (E.D. Tex. 2020)). The court acknowledged this “un-
derstandabl[e]” concern and, while disagreeing with the government’s statutory interpretation,
noted that agencies have room to create carve-outs for security-sensitive solicitations. ECF No. 39
at 16-17. The government’s approach to interpreting section 889(d)(2) was substantially justified,
as it was concerned with the core purposes of the statute and relied on the limited guidance in the
FAR and the Federal Register. See generally KWV, Inc., 113 Fed. Cl. at 538-39 (finding the gov-
ernment’s position substantially justified even when it improperly relied on an administrative de-
cision).
The government argues that this case raised a novel statutory interpretation, further justi-
fying the government’s interpretation. ECF No. 59 at 6 (citing, among others, Norris v. Securities
and Exchange Commission, 695 F.3d 1261, 1265 (Fed. Cir. 2012)). While a novel interpretive
issue may imply that there are multiple reasonable interpretations, as Q2 Impact points out (ECF
No. 60 at 1 & n.2; id. at 12-14), it is also possible that an interpretation becomes necessary only
because the government for the first time took an unreasonable position, which it had never taken
before, on the meaning of a statute. Thus, the court does not weigh the novelty of the issue in either
party’s favor here.
While Q2 Impact notes that it is a small business struggling to stay afloat and incurred
significant fees because of having to litigate here (ECF No. 60 at 2), EAJA shifts fees only when
the government’s position is not substantially justified. Because the government advanced a sub-
stantially justified interpretation of the statute, the court will deny Q2 Impact’s motion for attor-
ney’s fees and costs under EAJA.
III. Conclusion
For the reasons stated above, this court denies Q2 Impact’s motion for attorney’s fees and
costs.
6 IT IS SO ORDERED.
/s/ Molly R. Silfen MOLLY R. SILFEN Judge