The M/V Cape Ann v. United States

199 F.3d 61, 1999 U.S. App. LEXIS 32828, 1999 WL 1178991
CourtCourt of Appeals for the First Circuit
DecidedDecember 17, 1999
DocketNo. 98-2224
StatusPublished
Cited by13 cases

This text of 199 F.3d 61 (The M/V Cape Ann v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The M/V Cape Ann v. United States, 199 F.3d 61, 1999 U.S. App. LEXIS 32828, 1999 WL 1178991 (1st Cir. 1999).

Opinion

TORRUELLA, Chief Judge.

This case comes to us on appeal from the United States District Court for the District of Massachusetts and calls into question the level of government assistance required by the Uniform Relocation Assistance and Real Property Acquisition Policies Act (“Uniform Relocation Act” or “URA”), 42 U.S.C. § 4622 (1994). Congress passed this Act in 1970 to standardize federal legislation regarding relocation assistance and to provide “fair and equitable” treatment to parties displaced by federal programs. See Pou Pacheco v. Soler Aquino, 833 F.2d 392, 395 (1st Cir.1987). The plaintiff-appellant A.C. Cruise Line, [63]*63Inc.1 (“Cruise Line”) sought review of an award provided by the General Services Administration (“GSA”), alleging that the relocation assistance it received was far short of fair and equitable treatment. The district court did not agree and granted summary judgment in favor of the GSA. Because we find that the GSA’s decision was a reasonable application of the regulations, we affirm.

I. BACKGROUND

Drawing all inferences in favor of the appellant, we summarize the facts as follows. The Cruise Line conducted its passenger vessel business at the Fan Pier on the Boston Harbor waterfront from 1976 until 1992, when it was evicted in order for the United States to construct the new federal courthouse.2 Although ultimately unsuccessful, the GSA in coordination with Anthony Athanas, one of the principals of the Fan Pier Land Company, assisted the Cruise Line in its search for a new location, specifically by engaging the services of a harbor consultant and by contacting the World Trade Center. In November 1992, the Cruise Line made a temporary move to Commercial Wharf, even though it would not be permitted to operate its business from that location. Then, in June 1993, the Cruise Line moved permanently to Pier 8, 290 Northern Avenue, Boston.

On February 15, 1993, the Cruise Line filed a claim with the GSA requesting relocation benefits in the amount of $80,017.05 and relocation assistance as provided for in the Uniform Relocation Act. In May 1994, the GSA referred the claim to its Office of the Inspector General for an internal audit and review, which was completed on August 2, 1994. The audit found that $23,903 of the total proposed amount were actual expenses “allocable to the permanent relocation” of the appellant — $3900 for moving expenses and $20,003 for reestablishment expenses. Of the $3900 in moving expenses, $2000 in search related expenses were subject to a $1000 regulatory cap reducing the total moving expenses to $2900. See Uniform Relocation Assistance and Real Property Acquisition for Federal and Federally Assisted Programs, 49 C.F.R. § 24.303(a)(13) (1999). Likewise, the reestablishment expenses were reduced to reflect the $10,000 cap. See 49 C.F.R. § 24.304 (1999). The final award was $12,900. Subsequent to the audit, a GSA contracting officer increased the award by $452.03, and the Cruise Line received benefits of $13,352.03.

II. STANDARD OF REVIEW

We review a district court’s grant of summary judgment de novo and review the facts in a light most favorable to the nonmoving party. See EEOC v. Green, 76 F.3d 19, 23-24 (1st Cir.1996); Udo v. Tomes, 54 F.3d 9, 12 (1st Cir.1995). A party challenging GSA’s award of benefits under the Uniform Relocation. Act bears the burden of establishing that the Agency acted arbitrarily or capriciously or otherwise abused its discretion. See Administrative Procedure Act, 5 U.S.C. § 706(2)(A) (1996); NLRB v. Beverly Enters.-Mass., Inc., 174 F.3d 13, 23 (1st Cir.1999); see also Pou Pacheco, 833 F.2d at 398 (applying standard to GSA decision). In applying the arbitrary and capricious standard, the task of the reviewing court is to determine whether the agency considered the pertinent evidence and relative factors and sufficiently articulated an explanation for its action. See Beverly Enters.-Mass., 174 F.3d at 23 & n. 2. So long as the agency’s determination is “within the bounds of reasoned decisionmaking,” [64]*64we may not set it aside, regardless of whether we may have reached an opposite decision. See Baltimore Gas & Elec. Co. v. Natural Resources Defense Council, Inc., 462 U.S. 87, 105-06, 103 S.Ct. 2246, 76 L.Ed.2d 437 (1983).

III. DISCUSSION

The main thrust of appellant's claim is that the GSA failed to provide adequate relocation assistance, causing the appellant to incur unusual relocation expenses. The appellant primarily challenges the GSA award of relocation benefits on two grounds: (1) the GSA failed to provide the relocation assistance required by law, thereby necessitating appellant’s interim move to Commercial Wharf; and (2) the GSA arbitrarily and capriciously reclassified relocation expenses so that they would fall within the regulatory caps for search and reestablishment expenses. 49 C.F.R. §§ 24.303(a)(13), 24.304; see also 42 U.S.C. § 4622.

. A. THE INTERIM MOVE

The Uniform Relocation Act provides for payment to “displaced persons” of “actual reasonable expenses” incurred in moving a business, searching for a new location, and reestablishing the business at the new location. See 42 U.S.C. § 4622. The Act also requires that the displacing agency take measures to:

(2) provide current and continuing information on the availability, sales prices, and rental charges ... suitable locations for business;
(4) assist a person displaced from a business or farm operation in obtaining and becoming established in a suitable replacement location;
(6) provide other advisory services to displaced person in order to minimize hardships to such persons in adjusting to relocation.

42 U.S.C. § 4625(c).

The appellant insists that its interim move was necessitated by the GSA’s failure to provide “current and continuing” assistance within the meaning of the statutory scheme. The appellants rely on our opinion in

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Victim Rights Law Center v. DeVos
D. Massachusetts, 2021
Collins v. Esper
D. Massachusetts, 2018
Boston Redevelopment Authority v. National Park Service
125 F. Supp. 3d 325 (D. Massachusetts, 2015)
Western Sea Fishing Co., Inc. v. Locke
722 F. Supp. 2d 126 (D. Massachusetts, 2010)
NH v. Blind Vendors
2003 DNH 054 (D. New Hampshire, 2003)
Little Bay v. US Commerce
2002 DNH 096 (D. New Hampshire, 2002)
A.M.L. International, Inc. v. Daley
107 F. Supp. 2d 90 (D. Massachusetts, 2000)
The M v.
199 F.3d 61 (First Circuit, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
199 F.3d 61, 1999 U.S. App. LEXIS 32828, 1999 WL 1178991, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-mv-cape-ann-v-united-states-ca1-1999.