The Moosehead Sanitary District v. S. G. Phillips Corporation, Etc., State of Maine

610 F.2d 49, 28 Fed. R. Serv. 2d 753, 13 ERC (BNA) 2196, 1979 U.S. App. LEXIS 9777, 13 ERC 2196
CourtCourt of Appeals for the First Circuit
DecidedDecember 11, 1979
Docket79-1205
StatusPublished
Cited by80 cases

This text of 610 F.2d 49 (The Moosehead Sanitary District v. S. G. Phillips Corporation, Etc., State of Maine) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Moosehead Sanitary District v. S. G. Phillips Corporation, Etc., State of Maine, 610 F.2d 49, 28 Fed. R. Serv. 2d 753, 13 ERC (BNA) 2196, 1979 U.S. App. LEXIS 9777, 13 ERC 2196 (1st Cir. 1979).

Opinion

LEVIN H. CAMPBELL, Circuit Judge.

Appellant, the State of Maine, is seeking permission to intervene pursuant to Fed.R.Civ.P. 24(a) in a consolidated diversity action now pending in the Maine District Court. That action was brought by The Moosehead Sanitary District (Moosehead) against several private contractors for damages stemming from the allegedly faulty design and construction of a sewage treatment plant at Moosehead Lake near the town of Greenville, Maine. The plant has never worked properly, and Moosehead asserts that it has been abandoned. Maine bases its claim to intervention as of right on its contribution of one fourth of the $2 million construction cost of the facility. The district court denied the state’s motion to intervene. We affirm.

I.

Moosehead’s action has apparently not advanced beyond the pleading stage, and we must refer to the various complaints, counterclaims, third-party claims, and so forth as constituting the record to date. The parties seem to agree that the facts necessary to decision of this appeal are not in dispute.

Plaintiff-appellee Moosehead is a sanitary district organized under the laws of Maine, 38 Me.Rev.Stat.Ann. § 1061 et seq., and governed by a board of trustees elected by the residents of the district. Moosehead was created in order to construct and operate a sewage system in Greenville. In October 1971, Moosehead entered into two contracts with Wright, Pierce, Barnes and *51 Wyman (Wright, Pierce), a Maine corporation, for design and construction supervision of a sewage system, including a collection system, pumping station, force mains and a tertiary sewage treatment plant. Moosehead contracted with S. G. Phillips Corporation (Phillips), a Vermont corporation, in December 1973 for construction of interceptor sewers, pumping stations and the treatment plant. In connection with construction of the treatment plant, Phillips purchased two flocculation-filtration units (also known as moving bed filter (MBF) units) from Johns-Manville, a Colorado corporation. 1 The MBF units were delivered to the project in early 1974 and were installed at the plant by Phillips.

In September 1976, Moosehead commenced this litigation by suing Phillips in the Piscataquis County Superior Court in Maine; $76,000 in liquidated damages was sought for Phillips’ alleged failure to finish the project by the date specified in the contract. Phillips removed the action to federal court on the basis of diversity of citizenship. Moosehead then amended its complaint to add a count for breach of warranty with respect to the MBF units and breach of the construction contract. The amended complaint sought damages in excess of $2 million, alleging that the plant was essentially unworkable. (According to Maine, a new plant has since been built with additional state and federal funds.) Phillips counterclaimed against Moosehead which then brought a third-party claim against Wright, Pierce, asserting that Wright, Pierce- was liable for any claims that might be realized against Moosehead. Because both Moosehead and Wright, Pierce are located in Maine, jurisdiction was premised on the court’s ancillary jurisdiction. 2

In December 1977, Moosehead filed another action, this one against Johns-Man-ville for breach of warranty and negligence regarding the design, manufacture and sale of the MBF units. Damages were claimed in the amount of $3 million on each count. In each of these actions, the private defendants cross-claimed against each other. On motion of the plaintiff, the two actions were consolidated. At the preliminary pretrial conference on July 18, 1978, the State of Maine made known its intention to file a motion to intervene.

On August 1, 1978, the state moved to intervene as a party-plaintiff to assert a cross-claim against Moosehead and to assert claims against defendants Phillips and Johns-Manville. The theory of the cross-claim was that the provision of funds for the project by Maine gave rise to contractual or quasi-contractual liability on the part of Moosehead. The claims against defendants were based on the theory that Maine was a third-party beneficiary of the contracts between Moosehead and the defendants. Intervention was sought both as of right, Fed.R.Civ.P. 24(a), 3 and by permission of the court, Fed.R.Civ.P. 24(b). 4 Maine’s *52 motion was argued to a magistrate, who rejected both grounds. Intervention of right was not available, the magistrate ruled, because Maine had not shown that “ ‘as a practical matter’ its interest will be impaired or impeded if it simply waits for the plaintiff to secure whatever recovery it can in this Court and then sues the plaintiff in state court.” The magistrate also held that permissive intervention would “cause delay and . . . unnecessarily complicate the present actions.”

The district court, after hearing, affirmed the magistrate’s decision denying Maine the right to intervene under Rule 24(a). 5 The court held that Maine was not a third-party beneficiary of the contracts between Moosehead and the private contractors, and thus did not have an interest in the subject matter of the litigation sufficient to support intervention as of right. The court also found that Maine’s interest in recovering from Moosehead a portion of any sums Moosehead won from the defendants would not be impaired or impeded as a practical matter if intervention were denied, and that Moosehead would adequately represent Maine’s interest in ensuring an adequate recovery.

II.

Rule 24(a) establishes four basic requirements which must be met before a party is permitted to intervene as of right: 6 (1) the application must be timely; (2) the applicant must claim “an interest relating to the property or transaction which is the subject of the action”; (3) the applicant must be “so situated that the disposition of the action may as a practical matter impair or impede his ability to protect that interest”; and (4) it must be shown that the applicant’s interest will not be “adequately represented by existing parties.” The district court assumed that Maine’s application to intervene was timely, and as the parties do not contest this point on appeal, we also assume the timeliness requirement is met. At issue is the correctness of the district court’s ruling that Maine did not meet the other three requirements.

A.

Maine asserts two separate “interests” in the subject matter of this litigation. The first of these is its asserted interest in recovering against Phillips and Johns-Man-ville as a third-party beneficiary of the contracts between Moosehead and these parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

T-Mobile Northeast LLC v. The Town of Barnstable
969 F.3d 33 (First Circuit, 2020)
GUMM v. JACOBS
M.D. Georgia, 2020
Photographic Illustrators Corp. v. Orgill, Inc.
316 F.R.D. 45 (D. Massachusetts, 2016)
Shanley v. Cadle
277 F.R.D. 63 (D. Massachusetts, 2011)
Aref v. Holder
774 F. Supp. 2d 147 (District of Columbia, 2011)
Ungar v. Arafat
634 F.3d 46 (First Circuit, 2011)
Costa v. Marotta, Gund, Budd & Dzera, LLC
281 F. App'x 5 (First Circuit, 2008)
Amgen, Inc. v. F. Hoffman-LaRoche Ltd.
456 F. Supp. 2d 267 (D. Massachusetts, 2006)
Grace United Methodist Church v. City Of Cheyenne
451 F.3d 643 (Tenth Circuit, 2006)
B. Fernández & Hnos., Inc. v. Kellogg USA, Inc.
440 F.3d 541 (First Circuit, 2006)
Prete v. Bradbury Et
438 F.3d 949 (Ninth Circuit, 2006)
Langone v. Flint Ink North America Corp.
231 F.R.D. 114 (D. Massachusetts, 2005)
Maine v. Norton
203 F.R.D. 22 (D. Maine, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
610 F.2d 49, 28 Fed. R. Serv. 2d 753, 13 ERC (BNA) 2196, 1979 U.S. App. LEXIS 9777, 13 ERC 2196, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-moosehead-sanitary-district-v-s-g-phillips-corporation-etc-state-ca1-1979.