The Midland Land & Improvement Co. v. United States

58 Ct. Cl. 671, 1923 U.S. Ct. Cl. LEXIS 342, 1923 WL 2152
CourtUnited States Court of Claims
DecidedApril 2, 1923
DocketNo. 33713
StatusPublished
Cited by5 cases

This text of 58 Ct. Cl. 671 (The Midland Land & Improvement Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Midland Land & Improvement Co. v. United States, 58 Ct. Cl. 671, 1923 U.S. Ct. Cl. LEXIS 342, 1923 WL 2152 (cc 1923).

Opinion

Booth, Judge,

delivered the opinion of the court.

Under the terms of a written contract the plaintiff company assumed obligations to dredge and dispose of 4,177,110 cubic yards of material, scow measurement, in Newark Bay and Passaic Biver for the sum of 16¿ cents per cubic yard. The dredging work provided for in the contract was intended to secure for the defendant a channel 16 feet deep at mean low water, extending 10.8 miles from Staten Island Sound to the Montclair & Greenwood Lake Bailroad bridge. It was to be 300 feet wide for a distance of 9.7 miles and 200 feet from there on, a distance of 1.1 miles, and the contract so provided. Work was to commence within a month after the contractor received notice of the approval of the contract, and was to be prosecuted faithfully and diligently. The specifications, which are made a part of the contract, contained a provision for the retention by the defendant of 10 per cent of all payments made thereunder until half of the work was completed, a fact to be determined by the engineer, and thereafter the plaintiff was to receive payment in full. The work under the contract progressed without any undue friction, and in a manner satisfactory to both parties, until January 1, 1910. As a matter of fact, there was no complaint lodged against the contractor, and none could have been. Subsequent to this time trouble began to develop. The plaintiff fell far below its theretofore efficiency, until at last on September 24,1912, it ceased work entirely, ascribing its difficulties to a distinct change in the character of the material encountered, a difference so violent as to amount, according to the allegations of the petition, to misrepresentation upon the part of the defendant in its specifications. On November 1, 1912, the plaintiff wrote the Secretary of War asking to be relieved from its contract, and predicating its request upon the substantial difference between the character of the material to be dredged, as shown in the specifications, and that actually encountered in the performance of the work, stating the difference to be such as to make the cost of removing the same inequitable and unjust to the contractor. The Chief of Engineers declined to accede to plaintiff’s request, notified the company to proceed with the work, and upon its failure to do so annulled the contract on March 14, [682]*6821913. The contract provided for such, a proceeding, and paragraph 4 thereof authorized the defendant to relet the work and recoup the difference in price, if any, from the first contractor. This course was followed by the defendant. The plaintiff company had been paid for all work done up to September 24, 1912, except an alleged mistake in computation included in this suit, and $33,998.15 retained percentages withheld by the defendant under the provisions of the contract. This suit is for the recovery of both items, the $33,998.15 retained and $14,543.26, an alleged underpayment. We have not said anything about the supplemental agreement between the parties executed August 3,1911, because it in no way varies the issue except argumentatively.

If the facts in this case correspond with the facts in the cases of Christie v. United States, 237 U. S. 234, and Hollerbach v. United States, 233 U. S. 165, the plaintiff is entitled to judgment. Of course, such a result might follow, even though there be no such similarity. Inasmuch, therefore, as the contention made indispensably involves a discussion of the facts, the court has endeavored to find them from a record not especially contradictory nor involved.

The contract sued upon was the result of a public advertisement for bids to do the contemplated work. As usual, the defendant made public and available to bidders such information respecting the work as it possessed, which bidders might call for. The plaintiff company was manifestly anxious and deeply concerned in its efforts to procure the contract, for its bid for the same was so decidedly beneath all others that it is inconceivable that experienced engineers would have dreamed of the undertaking at such a figure, unless some other and outside consideration inspired it. The plaintiff company, prior to submitting its bid, had before it subdivision (c) of paragraph 19 of the specifications, as follows :

“ Character of Material. The material to be excavated is believed to be mud, sand, and gravel, but bidders are expected to examine the work and decide for themselves as to its character and make their bids accordingly, as the United States will not guarantee the accuracy of this description. The price per cubic yard will cover the removal of all material encountered except ledge rock.”

[683]*683It also bad before it borings or soundings shown on three separate sheets, 143 in number, made in November and December, 1906, disclosing conditions found over a distance of 10.8 miles, and conveniently divided into three separate areas, the first sheet disclosing borings in 42 separate places over a distance of 2.2 miles, the second indicating the result at 32 separate places over a distance of 3.1 miles, and the third showing the balance of the 143 over a distance of 5.5 miles. In addition to the above three blue prints, a report made by the Chief of Engineers of the Army to Congress and published as a public document was furnished to the contractor by the defendant, in which it was said, among other things: “ On the whole, the dredging would be comparatively easy and the cost moderate.” Irrespective of this information, the plaintiff company in its proposal, without solicitation or requirement, voluntarily stated that it possessed “ full knowledge of the kind, quantity, and quality of the work required,” and agreed to do the work for 16J cents per cubic yard, when the estimate of cost prepared by the engineers ran from 26 cents, for the lower, to 32 cents for the upper reaches of the area, and no other bidder had submitted a figure less than 22 cents.

Fraud and misrepresentation is frequently difficult to prove, but in this class of cases, wherein it most generally is to be deduced from printed documents, maps, and blue prints, and the influential effect of the same upon bidders, the conclusion as to its existence or nonexistence is not quite so involved as the reconciliation and analysis of oral testimony, keeping in mind, of course, that we are speaking of constructive rather than actual and intended deceit. However, the rule is not to be relaxed. The court must not only find the representations to have been false, but, being so, did actually mislead the bidder who obtained the contract. Christie, v. United States, sufra.

The burden of proving misrepresentation rests upon the party making the allegation. It is not to be presumed, and one may not, either under the Christie or Hollerbach case, simply show a different condition in some respects from that which the chart or blue prints of borings discloses, and rest his case upon the theory that the court must infer a mis[684]*684representation. There must be some degree oí culpability attached to the makers of the maps and charts, either that they were knowingly untrue or were prepared as the result of such a serious and egregious error that the court may imply bad faith. The many contract cases in this court, too many to cite, sustain this principle.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

International Technology Corp. v. Winter
523 F.3d 1341 (Federal Circuit, 2008)
Tree Preservation Co. v. United States
172 Ct. Cl. 577 (Court of Claims, 1965)
Archie and Allan Spiers, Inc. v. United States
296 F.2d 757 (Court of Claims, 1961)
W. H. French Dredging & Wrecking Co. v. United States
62 Ct. Cl. 97 (Court of Claims, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
58 Ct. Cl. 671, 1923 U.S. Ct. Cl. LEXIS 342, 1923 WL 2152, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-midland-land-improvement-co-v-united-states-cc-1923.