The Haskell Company

CourtArmed Services Board of Contract Appeals
DecidedOctober 1, 2025
Docket63332, 63586
StatusPublished

This text of The Haskell Company (The Haskell Company) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Haskell Company, (asbca 2025).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) The Haskell Company ) ASBCA Nos. 63332, 63586 ) Under Contract No. N69450-19-D-0909 ) Task Order No. N69450-19-F-0874 )

APPEARANCES FOR THE APPELLANT: James E. Krause, Esq. James A. Galloway, Esq. James E. Krause, P.A. Jacksonville, FL

APPEARANCES FOR THE GOVERNMENT: Allison M. McDade, Esq. Navy Chief Trial Attorney J. Alexandra Fitzmaurice, Esq. Amy L. Zobel, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE WITWER ON RESPONDENT’S MOTION FOR SUMMARY JUDGMENT

This appeal arises from the Department of the Navy’s year-long closure of the Atlantic Undersea Test and Evaluation Center (AUTEC) on Andros Island in the Bahamas undertaken in response to the COVID-19 pandemic. The Haskell Company, a construction contractor performing work at AUTEC under a fixed-price task order, alleges that its work was hindered, disrupted, impacted, and delayed by the Navy’s actions and inactions during the pandemic. The Navy has moved for summary judgment on the ground that the sovereign acts doctrine bars Haskell’s claims.

We grant the Navy’s motion in part and deny it in part. We hold that the decision to close AUTEC and exclude Haskell from the base was a valid exercise of sovereign authority. Haskell has not raised a genuine dispute of material fact that the closure was specifically directed at Haskell or undertaken to financially benefit the government in connection with this contract. Accordingly, Haskell’s claim for costs arising from the base closure is barred by the sovereign acts doctrine. We also grant the Navy’s motion with respect to costs Haskell incurred in replanning the project following the base’s reopening, including implementing public health measures that made base access more difficult.

We deny the motion with respect to offsite work that may not have required base access, as the Navy has not demonstrated that such work was rendered impossible or that no material facts remain in dispute. We also deny summary judgment with respect to one category of replanning costs that Haskell attributes to coordination conflicts that allegedly arose after the base reopened, when multiple projects resumed concurrently (hereinafter “logistical bottleneck costs”). Regarding these costs, we find the briefing and record insufficiently developed for us to grant summary judgment.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

The Base Contract

1. The following facts are undisputed. On February 22, 2019, the Naval Facilities Engineering Systems Command (NAVFAC) Southeast awarded Contract No. N69450-19-D-0909 to Haskell (hereinafter the “base contract”) (GSUMF ¶ 1; app. resp. to GSUMF ¶; R4, tab 1). 1 The base contract was one of five fixed-price, indefinite-delivery, indefinite-quantity (IDIQ) contracts awarded under a multiple- award construction contract for NAVFAC Southeast’s area of responsibility (R4, tab 1 at GOV5).

2. The base contract incorporated by reference two Federal Acquisition Regulation (FAR) clauses relevant to the dispute: 52.242-14, SUSPENSION OF WORK (APR 1984), and 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)) (GSUMF ¶¶ 2, 5; app. resp. to GSUMF ¶¶ 2, 5; R4, tab 1 at GOV12).

The Task Order

3. On September 26, 2019, NAVFAC issued Haskell a fixed-price, design- build task order for the construction of austere housing quarters at AUTEC located on Andros Island, Bahamas (R4, tab 3 at GOV977-78). AUTEC is a Navy test facility that supports Research, Development, Test and Evaluation (RDT&E) efforts, as well as fleet training, certification, and proficiency exercises. It operates a deep-water range facility, which is used by agreement with the Royal Navy of the United Kingdom and the Bahamas. The base supports both a permanent onsite workforce and visiting users who conduct exercises and tests at the range. 2 (GSUMF ¶¶ 7-8, 10-12; app. resp. to GSUMF ¶¶ 7-8, 10-12; gov’t mot., ex. A at GOV2629; Woodcock aff. ¶ 3-6; R4, tab 2 at GOV344)

1 GSUMF refers to the Government’s Statement of Undisputed Material Facts. 2 AUTEC is a detachment of the Naval Undersea Warfare Center (NUWC) Newport Division in Newport, Rhode Island. The NUWC Newport Division is a Field Activity of Naval Sea Systems Command (NAVSEA). (GSUMF ¶¶ 7-8, 10-12; app. resp. to GSUMF ¶¶ 7-8, 10-12; gov’t mot., ex. A at GOV2629; Woodcock aff. ¶ 3-6; R4, tab 2 at GOV344)

2 4. The task order was intended to address deficiencies in AUTEC’s existing housing. It required Haskell to remove substandard existing housing units and construct a new, two-story austere housing facility. (R4, tab 2 at GOV344)

5. The task order included a clause titled “Anticipated Restricted Delays,” which provided that, if the installation were closed for more than five lost workdays in a calendar year, the contracting officer would issue a no-cost contract modification extending the contract completion date if the critical path was impacted (R4, tab 2 at GOV84).

6. NAVFAC issued Haskell written Notice to Proceed with the design phase in October 2019 (R4, tab 20A-Ex.2 at GOV1727). Under the task order, Haskell was to complete construction within 816 calendar days from the date of award (R4, tab 3 at GOV982; app. opp’n at 9).

COVID-19 Pandemic and the Base Closure

7. We take judicial notice that, on March 11, 2020, the World Health Organization declared COVID-19 a global pandemic. In response, the Government of the Bahamas issued a series of emergency public health orders throughout 2020 and 2021. These orders imposed travel bans, quarantine requirements, and access restrictions, both within the country and for those entering from abroad. (GSUMF ¶ 23; app. resp. to GSUMF ¶ 23; gov’t mot., ex. B; app. opp’n at 1-2, 9; app. supp. R4, tabs 7-62, 69)

8. The Navy command at AUTEC also implemented preventative measures to minimize the spread of the virus. On March 18, 2020, AUTEC’s Officer-in-Charge, Commander Michael Woodcock, ordered the base closed to non-essential personnel “to minimize the potential threat of the coronavirus spread to the base” (GSUMF ¶¶ 24-25; app. resp. to GSUMF ¶¶ 24-25; app. opp’n at 2, 9; R4, tab 20B-Ex.2 at GOV1802-03). He emphasized that the primary purpose of the closure was to protect the health and safety of those on base (R4, tab 20B-Ex.2 at GOV1803).

9. In a follow-up communication, the Officer-in-Charge described the Restriction of Movement (ROM) protocols that would apply to personnel arriving at AUTEC. He reiterated that preventing the virus from reaching the base was his top priority, while ensuring that the base remained available for mission-essential operations. (Gov’t mot, ex. C)

10. Haskell’s contract was not deemed mission-essential (R4, tab 20B-Ex.2 at GOV1802, GOV1826). On March 19, 2020, NAVFAC forwarded the Officer-in- Charge’s order to the Haskell and instructed the company to recall its personnel and

3 suspend all onsite activities at AUTEC (GSUMF ¶ 25; app. resp. to GSUMF ¶ 25; R4, tab 20B-Ex.2 at GOV1802-03).

11. That same day, Haskell acknowledged the directive, stating that it “appreciated the command’s decision to mitigate the potential transmission of the COVID-19 virus considering the remoteness of the location and heightened risk to personnel” (GSUMF ¶ 27; app. resp. to GSUMF ¶ 26; R4, tab 20B-Ex2 at GOV1804). Anticipating a prolonged closure, Haskell requested weekly coordination meetings with NAVFAC and AUTEC personnel to plan for eventual remobilization (R4, tab 20B-Ex. 2 at GOV1804).

12. AUTEC remained closed to Haskell for approximately one year. During that time, NAVFAC did not issue a Suspension of Work Order or a Notice to Proceed with construction. (R4, tab 20 at GOV1693, GOV1696)

Contract Performance During the Base Closure

13.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Horowitz v. United States
267 U.S. 458 (Supreme Court, 1925)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
United States v. Winstar Corp.
518 U.S. 839 (Supreme Court, 1996)
Stockton East Water District v. United States
583 F.3d 1344 (Federal Circuit, 2009)
CONNER BROS. CONST. CO., INC. v. Geren
550 F.3d 1368 (Federal Circuit, 2008)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
Lakeshore Engineering Services, Inc. v. United States
748 F.3d 1341 (Federal Circuit, 2014)
Walter Dawgie Ski Corp. v. United States
39 Cont. Cas. Fed. 76,583 (Federal Claims, 1993)
Klamath Irrigation District v. United States
75 Fed. Cl. 677 (Federal Claims, 2007)
Stoumbos ex rel. Whitesides v. Kilimnik
988 F.2d 949 (Ninth Circuit, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
The Haskell Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-haskell-company-asbca-2025.