The Hansen Company, Inc. v. Rednet Environmental Services, L.L.C., Lynn Knudsen, and Robert Knudsen, Rednet Environmental Services, L.L.C., Lynn Knudsen, and Robert Knudsen, Counterclaim v. the Hansen Company, Inc., Counterclaim

CourtCourt of Appeals of Iowa
DecidedOctober 11, 2017
Docket16-0735
StatusPublished

This text of The Hansen Company, Inc. v. Rednet Environmental Services, L.L.C., Lynn Knudsen, and Robert Knudsen, Rednet Environmental Services, L.L.C., Lynn Knudsen, and Robert Knudsen, Counterclaim v. the Hansen Company, Inc., Counterclaim (The Hansen Company, Inc. v. Rednet Environmental Services, L.L.C., Lynn Knudsen, and Robert Knudsen, Rednet Environmental Services, L.L.C., Lynn Knudsen, and Robert Knudsen, Counterclaim v. the Hansen Company, Inc., Counterclaim) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Hansen Company, Inc. v. Rednet Environmental Services, L.L.C., Lynn Knudsen, and Robert Knudsen, Rednet Environmental Services, L.L.C., Lynn Knudsen, and Robert Knudsen, Counterclaim v. the Hansen Company, Inc., Counterclaim, (iowactapp 2017).

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 16-0735 Filed October 11, 2017

THE HANSEN COMPANY, INC., Plaintiff-Appellant,

vs.

REDNET ENVIRONMENTAL SERVICES, L.L.C., LYNN KNUDSEN, and ROBERT KNUDSEN, Defendants-Appellees. ___________________________________

REDNET ENVIRONMENTAL SERVICES, L.L.C., LYNN KNUDSEN, and ROBERT KNUDSEN, Counterclaim Plaintiffs,

THE HANSEN COMPANY, INC., Counterclaim Defendant. ________________________________________________________________

Appeal from the Iowa District Court for Polk County, Jeffrey D. Farrell,

Judge.

The Hansen Company, Inc. appeals from an adverse jury verdict in this

breach-of-contract action. AFFIRMED IN PART, REVERSED IN PART, AND

REMANDED WITH DIRECTIONS. 2

Martin J. Demoret and Ross W. Johnson of Faegre Baker Daniels L.L.P.,

Des Moines, and Jeffrey D. Stone of Whitfield & Eddy, P.L.C., Des Moines, for

appellant.

Matthew G. Sease of Kemp and Sease, Des Moines, Todd M. Lantz of the

Weinhardt Law Firm, Des Moines, and Jeremy R. Masterson of Masterson &

Bottenberg, L.L.P., Waukee, for appellees.

Heard by Danilson, C.J., and Tabor and McDonald, JJ. 3

DANILSON, Chief Judge.

The Hansen Company, Inc.1 appeals from an adverse jury verdict after a

five-day trial. The parties had entered into a contract involving a demolition

project of the Younkers building located in Des Moines. The jury determined

Hansen breached the contract and committed willful and wanton conduct

resulting in a verdict for compensatory damages in the amount of $1,381,387 and

punitive damages of $250,000. In a nutshell, Hansen contends the claim for

punitive damages should have been dismissed, the compensatory verdict should

have been set aside because of insufficiency of the evidence, and the damages

awarded were not supported by the evidence and were excessive. We affirm on

the compensatory-damages verdict and reverse the award of punitive damages.

I. Background Facts & Proceedings.

The trial began upon RedNet’s2 breach-of-contract and fraudulent-

misrepresentation claims, but RedNet withdrew the fraud claim at the close of its

evidence.3 On appeal, Hansen contends the district court erred in overruling its

motions for directed verdict, motion for judgment notwithstanding the verdict, and

alternative motion for new trial.

The parties entered into a stipulation prior to trial that the following facts

were true and undisputed:

1 Hereafter referred to as “Hansen.” 2 We shall refer to all of the appellees—RedNet Environmental Services, L.L.C., Lynn Knudsen, and Robert Knudsen—as “RedNet” unless otherwise identified. Lynn Knudsen was president and Robert Knudsen was vice president of RedNet. 3 The action was initiated by Hansen’s petition claiming damages for RedNet’s libelous conduct, but that claim was dismissed before trial. RedNet’s claims arose by counterclaim. 4

1. In the spring of 2013 RedNet Environmental Services and the Hansen Company entered into a contract to perform work on the property located at 713 Walnut Street, Des Moines, Iowa. 2. Pursuant to the contract, RedNet Environmental Services was to perform asbestos abatement, lead abatement, PCB/Mercury disposal and demolition on the property. 3. Before RedNet Environmental Services was allowed to perform any of the contracted work on the project, the Hansen Company terminated RedNet Environmental Services’ contract on August 23, 2013.

We adopt the following partial summary of the preliminary facts noted by

the district court in its ruling on post-trial motions:

RedNet was a business owned by Robert and Lynn Knudsen that performed demolition and hazardous material abatement work. The Knudsens owned other companies that were interrelated, most prominently, Redstone Painting, which was started in 2006. The Knudsens started RedNet in 2011. Lynn Knudsen was the president of RedNet and Rob Knudsen was vice president. However, Rob Knudsen was the face of the company and actively managed its activities in the field. Lynn primarily performed office work. Hansen is a general contractor [that] was hired to renovate the former Younkers Building in downtown Des Moines. On April 1, 2013, Hansen issued a request for proposal (RFP) for demolition and hazardous material abatement at the Younkers building. Rob Knudsen was very familiar with the building as he had worked in the building for Hansen for approximately [twenty] years. RedNet had submitted a bid based on an earlier RFP in 2011, but the project did not proceed forward at that time. In April of 2013, RedNet submitted a bid of $3,330,100, which did not include pricing on options. Tony Garcia from Hansen informed Mr. Knudsen that RedNet was not the low bidder, but invited an amendment with a breakdown on the work so he could better compare it with other bidders. Following that, Mr. Knudsen informed Mr. Garcia that RedNet would pass on the project. In mid-June of 2013, Hansen contacted RedNet and asked if it would be willing to submit a new bid. Hansen had learned that the subcontractor would not have to pay Davis-Bacon wages, which was expected to substantially reduce the cost of project. RedNet agreed to submit a new bid in light of the new information. RedNet ultimately presented a bid of $2,655,100 that allowed it to keep and sell all scrap pulled from the building. RedNet estimated the scrap as an additional $257,000 in revenue. This bid was accepted by Hansen. The parties stipulated that a contract was formed at that 5

time, although they dispute some terms of the contract. The parties agreed that work often begins on a project before a final written contract is executed. RedNet prepared for work on the Younkers project. Work was initially scheduled to start on July 15, 2013. RedNet applied for a permit to remove asbestos from the building and filed notices with other government agencies. RedNet purchased needed supplies. The start date was delayed, but Hansen continued to confer with RedNet while preparing for the project. As an example, the parties met on July 11, 2013, to sort through contract terms, scope of work, schedules, and other matters. As of that meeting, work was expected to begin on August 5, 2013.

(Footnote omitted.)

However, by late July 2013 circumstances began to arise that gave cause

for the instant action. On July 26, 2013, Knudsen sent a letter to the president of

Hansen, Craig Faber, regarding discrepancies with the asbestos and lead

inspection reports provided by Hansen. The discrepancies, according to

Knudsen, could result in widespread exposure to asbestos to other

subcontractors and violate many laws and even result in imprisonment. About

the same time, and although the parties had worked together in many prior

projects, Hansen had become increasingly concerned about the financial viability

of RedNet and Knudsen’s related companies. Redstone was providing space for

RedNet’s headquarters but Redstone’s landlord filed a forcible entry and detainer

action to evict Redstone in mid-July. RedNet had also subcontracted some of

the labor on the demolition contract to Redstone, and Hansen received notice

that Redstone’s workers’ compensation policy had been cancelled. On behalf of

Hansen, Garcia contacted Knudsen on two occasions expressing concern about

RedNet’s ability to complete the demolition project and the rumors that the 6

Knudsen companies were near bankruptcy. Knudsen insisted Redstone’s

problems would not affect RedNet.

Ultimately, Hansen’s bonding company recommended that Hansen obtain

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wolf v. Wolf
690 N.W.2d 887 (Supreme Court of Iowa, 2005)
Molo Oil Co. v. River City Ford Truck Sales, Inc.
578 N.W.2d 222 (Supreme Court of Iowa, 1998)
Van Sickle Construction Co. v. Wachovia Commercial Mortgage, Inc.
783 N.W.2d 684 (Supreme Court of Iowa, 2010)
Kiesau v. Bantz
686 N.W.2d 164 (Supreme Court of Iowa, 2004)
Lloyd v. Drake University
686 N.W.2d 225 (Supreme Court of Iowa, 2004)
Pexa v. Auto Owners Insurance Co.
686 N.W.2d 150 (Supreme Court of Iowa, 2004)
Claude v. Weaver Construction Company
158 N.W.2d 139 (Supreme Court of Iowa, 1968)
Royal Indemnity Co. v. Factory Mutual Insurance Co.
786 N.W.2d 839 (Supreme Court of Iowa, 2010)
Magnusson Agency v. Public Entity National Co.-Midwest
560 N.W.2d 20 (Supreme Court of Iowa, 1997)
Meier v. SENECAUT III
641 N.W.2d 532 (Supreme Court of Iowa, 2002)
Tarrell v. Erdmann
221 N.W.2d 504 (Supreme Court of Iowa, 1974)
Dutcher v. Lewis
221 N.W.2d 755 (Supreme Court of Iowa, 1974)
Vogan v. Hayes Appraisal Associates, Inc.
588 N.W.2d 420 (Supreme Court of Iowa, 1999)
WSH Properties, L.L.C. v. Daniels
761 N.W.2d 45 (Supreme Court of Iowa, 2008)
Seastrom v. Farm Bureau Life Insurance Co.
601 N.W.2d 339 (Supreme Court of Iowa, 1999)
Employee Benefits Plus, Inc. v. Des Moines General Hospital
535 N.W.2d 149 (Court of Appeals of Iowa, 1995)
Graves v. Iowa Lakes Community College
639 N.W.2d 22 (Supreme Court of Iowa, 2002)
Berryhill v. Hatt
428 N.W.2d 647 (Supreme Court of Iowa, 1988)
Pogge v. Fullerton Lumber Co.
277 N.W.2d 916 (Supreme Court of Iowa, 1979)
Orkin Exterminating Co., Inc.(Arwell Div.) v. Burnett
160 N.W.2d 427 (Supreme Court of Iowa, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
The Hansen Company, Inc. v. Rednet Environmental Services, L.L.C., Lynn Knudsen, and Robert Knudsen, Rednet Environmental Services, L.L.C., Lynn Knudsen, and Robert Knudsen, Counterclaim v. the Hansen Company, Inc., Counterclaim, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-hansen-company-inc-v-rednet-environmental-services-llc-lynn-iowactapp-2017.