The Fallstaff Group, Inc., Etc. v. Mpa Brickell Key, LLC, Etc.

143 So. 3d 1139, 2014 WL 3844021, 2014 Fla. App. LEXIS 12040
CourtDistrict Court of Appeal of Florida
DecidedAugust 6, 2014
Docket3D13-2183
StatusPublished
Cited by6 cases

This text of 143 So. 3d 1139 (The Fallstaff Group, Inc., Etc. v. Mpa Brickell Key, LLC, Etc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Fallstaff Group, Inc., Etc. v. Mpa Brickell Key, LLC, Etc., 143 So. 3d 1139, 2014 WL 3844021, 2014 Fla. App. LEXIS 12040 (Fla. Ct. App. 2014).

Opinion

EMAS, J.

The Fallstaff Group, Inc. (“Fallstaff’) and Courvoisier Courts, LLC (“Courvoisier”) appeal a final judgment, an amended final judgment, and two orders entering partial summary judgment in favor of MPA Brickell Key, LLC (“MPA”). For the reasons that follow, we affirm in part and reverse in part.

BACKGROUND

In November 2004, MPA entered into an agreement to sell real property on Brickell Key to Fallstaff. A portion of the real property was subject to a Shared Facilities Agreement (“SFA”) with a neighboring property owner, FBEC-Brickell Key Cen-tre, L.P. (“FBEC”). The SFA addressed, in part, apportionment of ad valorem taxes for properties separately owned by MPA and FBEC, but billed by the property appraiser under a single folio number. Pursuant to the SFA, MPA paid the real property taxes billed under the single folio number — Folio No. 11 — and thereafter, MPA would invoice FBEC for its 1% share.

At the time of the proposed sale by MPA to Fallstaff, certain disputes between Fallstaff and FBEC had arisen, which required a postponement of the closing date. Accordingly, MPA and Fallstaff entered into a separate letter agreement, which postponed the closing and further provided, in relevant part:

2. Reference is made to certain disputes between [MPA] and Jones Lang LaSalle (“JLL”) 1 concerning a certain Shared Facilities Agreement (“the SFA”). [MPA] and Fallstaff have agreed that [MPA] will, at Closing under the Agreement, pay Fallstaff $110,000 (including within the $110,000, $10,000 for gate removal) in full payment of all of [MPA’s] obligations with respect to *1141 these disputes (the “SFA Dispute”) and all amounts owed by [MPA] under the SFA through the date of the Closing. In recognition of this fact, Fallstaff hereby agrees to indemnify and hold harmless [MPA] and all of its equity holders, officer, employees, agents and representatives with respect to any liability under or in connection with the SFA (including any liability with respect to legal fees or court costs).

On the day of closing, Fallstaff assigned the sales agreement to an affiliate, Cour-voisier, and agreed that Fallstaff and Courvoisier would “be jointly and severally liable under and pursuant to the Agreement.” The assignment further provided that Courvoisier “shall perform all obligations, duties and liabilities of [Fallstaff] under the Agreement.” At closing, Cour-voisier received the $110,000 credit as set forth in the letter agreement, and the letter agreement was included in the closing binder.

Unbeknownst to the parties, the tax appraiser had created a new tax folio in 2002 (“Folio No. 12”), splitting FBEC’s and MPA’s property from one another, but the tax bills were never sent to MPA or FBEC. Thus, although its property was being taxed separately from 2002 on, FBEC continued to pay its portion of the ad valorem taxes on Folio No. 11 up to the date of the Fallstaff closing in 2004.

A few months after the closing, FBEC discovered the folio split when tax certificates were issued against its property and, thereafter, demanded from MPA “$43,-215.07 (the amount paid by [FBEC] to MPA), plus $7,593.56 (the amount of costs penalties and interest paid).” In response, MPA, through counsel, notified FBEC that it had no knowledge of the tax folio split, that the real property in question was sold, and that all issues should be directed to the new owner, Fallstaff. When Fallstaff also refused to reimburse FBEC, FBEC filed suit against MPA.

In response, MPA filed a third-party complaint against Fallstaff, seeking indemnification as provided under the terms of the letter agreement. The third party complaint was dismissed without prejudice, pending the resolution of FBEC’s suit against MPA. After discovery, FBEC acknowledged that MPA did not have knowledge of the tax folio split when it invoiced FBEC for the 2002-2004 taxes, and MPA and FBEC settled their lawsuit for $17,000.

Following that settlement, MPA filed an amended complaint against Fallstaff and Courvoisier, asserting a claim for contractual indemnification, seeking the $17,000 MPA paid to FBEC, plus attorney’s fees and costs incurred by MPA in that action (Count I). In the alternative, MPA asserted a claim against Courvoisier for unjust enrichment based on the $110,000 credit Courvoisier received at closing (Count II).

Fallstaff and Courvoisier moved for summary judgment as to the claim for contractual indemnification. At the hearing, the trial court agreed with Fallstaffs and Courvoisier’s assertion that, although MPA’s initial conduct in billing FBEC for the 2002-2004 property taxes was an innocent mistake, once MPA confirmed the tax folio split, MPA should have returned the wrongfully collected money to FBEC. Instead, MPA forced FBEC to pursue an action against MPA to recoup the wrongfully collected money, and as a result of this wrongful conduct, MPA was not entitled to indemnity. As to Courvoisier, the trial court further ruled that Courvoisier did not agree to indemnify MPA. Based on these rulings, the trial court granted summary judgment in favor of Fallstaff and Courvoisier as to MPA’s claim for contractual indemnification.

*1142 Courvoisier then moved for summary-judgment as to MPA’s alternative claim for unjust enrichment. At the hearing, the trial court ruled that Courvoisier was not unjustly enriched, and therefore, granted summary judgment in favor of Courvoisier. The trial court later entered final judgment in favor of Fallstaff and Courvoisier, and MPA appealed.

On appeal, this court held that the trial court erred in granting summary judgment in favor of Fallstaff and Courvoisier. MPA Brickell Key, LLC v. Fallstaff Group, Inc., 92 So.3d 879 (Fla. 3d DCA 2012). Specifically, we held that (1) the indemnification provision in the letter agreement (including the provision, to indemnify MPA) was binding on Courvoisier; and (2) that MPA did not act wrongfully in failing to tender the amounts set forth in FBEC’s demand letter or in defending the action because the amount demanded was more than the amount FBEC paid MBA and because MPA believed it was no longer responsible for “resolving any disputes, past or present, under the Shared Facilities Agreement.” Accordingly, this court reversed the final judgment and remanded for further proceedings, “including a determination of whether the claim FBEC and MPA settled was covered by the indemnification provision in the letter agreement.” Id. at 882.

On remand, MPA moved for partial summary judgment on liability, asserting the settled claim was covered by the indemnification provision in the letter agreement, and therefore, it was entitled to the $17,000 it paid to settle the claims with FBEC, plus interest, as well as attorney’s fees and costs for its defense of those claims for four years, and the attorney’s fees and costs for its prosecution of the indemnity claim against Fallstaff and Courvoisier, at both the trial court and the appellate court levels.

After a hearing on March 11, 2013, the court granted MPA’s motion for partial summary judgment on liability, finding Fallstaff and Courvoisier had breached the contract and were jointly and severally liable for the $17,000 settlement payment. It reserved ruling on other damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

STEPHEN HESS v. PMG-S2 SUNNY ISLES, LLC
District Court of Appeal of Florida, 2023
41 ACQUISITION HOLDINGS, LLC, etc. v. ANN SCHRAEDEL HAFF
District Court of Appeal of Florida, 2023
MARITZA RAMOS v. IN RE: THE ESTATE OF ELEIDA RAMOS
District Court of Appeal of Florida, 2021
Nature's Products, Inc. v. NXXI Inc.
216 F. Supp. 3d 381 (S.D. New York, 2016)
Moriber v. Dreiling
194 So. 3d 369 (District Court of Appeal of Florida, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
143 So. 3d 1139, 2014 WL 3844021, 2014 Fla. App. LEXIS 12040, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-fallstaff-group-inc-etc-v-mpa-brickell-key-llc-etc-fladistctapp-2014.